QA/QC  › Method Statements  › Concreting Method Statement
Form · QC-MST-FRM-005
Concreting Method Statement
26 checkpoints across 8 sections. Before starting the activity — submit to consultant for approval
26 Checkpoints
8 Sections
Per activity, per project
Contractor PM, QA/QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SCOPE & REFERENCES
A1Scope: batching (site / RMC), transport, placing, compacting, finishing, curing of all RCC/PCC elements
Acceptance: Scope covers grade, elements, production source, and pour sequence
Cl. 1 — Scope
OK
NC
NA
HOLD
A2Approved mix design per IS 10262 for each concrete grade — trial batches verified
Acceptance: Trial mix 28-day strength ≥ target mean strength; workability OK; approved
Cl. 9 (IS 456) — Mix design
OK
NC
NA
HOLD
A3RMC supplier pre-qualified per IS 4926 — plant audit, calibration, QAP reviewed
Acceptance: QCI/NRMCA certified RMC plant; weigh batchers calibrated; QAP approved
Cl. 5 (IS 4926) — Supplier QA
OK
NC
NA
HOLD
B. MATERIALS & EQUIPMENT
B1Cement per IS 269/1489/12269, aggregates per IS 383, water per IS 456 Cl.5.4, admixtures per IS 9103
Acceptance: All materials meet respective IS; MTC/test reports on file; admixture dosage verified
Cl. 5 (IS 456) — Materials
OK
NC
NA
HOLD
B2Placing equipment — boom pump/line pump/bucket — mobilised; standby pump arranged
Acceptance: Pump capacity adequate; standby pump on site; line cleaned prior to pour
Cl. 13 (IS 456) — Placing
OK
NC
NA
HOLD
B3Vibrators — needle, form, screed — ≥1 standby per 2 working; power backup arranged
Acceptance: Vibrators checked; standby available; DG back-up tested
Cl. 13.3 (IS 456) — Compaction
OK
NC
NA
HOLD
C. SITE PREPARATION / PRE-REQUISITES
C1Formwork, rebar, MEP inserts inspected and approved; joint inspection report signed
Acceptance: All prior RFIs closed; pre-pour checklist (QC-CON-CHK-XXX) signed by consultant
Cl. 10 — Pre-pour
OK
NC
NA
HOLD
C2Construction joint treatment done — laitance removed, surface roughened, bonding slurry applied
Acceptance: Surface clean, saturated-surface-dry; cement slurry or bond agent applied just before pour
Cl. 13.4 — Joints
OK
NC
NA
HOLD
C3Cube moulds, slump cone, thermometer, sample trays ready on site; cube curing tank filled
Acceptance: 6 cubes per 50 m³ (min 1 per pour); moulds cleaned and oiled; curing tank temp 27±2 °C
Cl. 15 — Testing setup
OK
NC
NA
HOLD
Showing 9 of 26 checkpoints ·
A. SCOPE & REFERENCES
A1Scope: batching (site / RMC), transport, placing, compacting, finishing, curing of all RCC/PCC elements
Cl. 1 — Scope (IS 456)
Scope covers grade, elements, production source, and pour sequence
OKNCNAHOLD
A2Approved mix design per IS 10262 for each concrete grade — trial batches verified
Cl. 9 (IS 456) — Mix design (IS 10262)
Trial mix 28-day strength ≥ target mean strength; workability OK; approved
OKNCNAHOLD
A3RMC supplier pre-qualified per IS 4926 — plant audit, calibration, QAP reviewed
Cl. 5 (IS 4926) — Supplier QA (IS 4926)
QCI/NRMCA certified RMC plant; weigh batchers calibrated; QAP approved
OKNCNAHOLD
B. MATERIALS & EQUIPMENT
B1Cement per IS 269/1489/12269, aggregates per IS 383, water per IS 456 Cl.5.4, admixtures per IS 9103
Cl. 5 (IS 456) — Materials (IS 456)
All materials meet respective IS; MTC/test reports on file; admixture dosage verified
OKNCNAHOLD
B2Placing equipment — boom pump/line pump/bucket — mobilised; standby pump arranged
Cl. 13 (IS 456) — Placing (IS 456)
Pump capacity adequate; standby pump on site; line cleaned prior to pour
OKNCNAHOLD
B3Vibrators — needle, form, screed — ≥1 standby per 2 working; power backup arranged
Cl. 13.3 (IS 456) — Compaction (IS 456)
Vibrators checked; standby available; DG back-up tested
OKNCNAHOLD
C. SITE PREPARATION / PRE-REQUISITES
C1Formwork, rebar, MEP inserts inspected and approved; joint inspection report signed
Cl. 10 — Pre-pour (IS 456)
All prior RFIs closed; pre-pour checklist (QC-CON-CHK-XXX) signed by consultant
OKNCNAHOLD
C2Construction joint treatment done — laitance removed, surface roughened, bonding slurry applied
Cl. 13.4 — Joints (IS 456)
Surface clean, saturated-surface-dry; cement slurry or bond agent applied just before pour
OKNCNAHOLD
C3Cube moulds, slump cone, thermometer, sample trays ready on site; cube curing tank filled
Cl. 15 — Testing setup (IS 456)
6 cubes per 50 m³ (min 1 per pour); moulds cleaned and oiled; curing tank temp 27±2 °C
OKNCNAHOLD
Showing 9 of 26 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED — NCR RAISED
Remarks
Name / Sign / Date
Prepared By
Name / Sign / Date
Approved By
Name / Sign / Date