The 8 formats every Indian construction site uses daily — Excel + PDF, IS / IRC / FIDIC mapped.
| Format | Type | Category | Codes | ID |
|---|---|---|---|---|
| Pre-Qualification (PQ) Application | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-001 |
| Technical Bid Compliance Sheet | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-002 |
| Financial Bid — Item Rate | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-003 |
| Financial Bid — Percentage Rate | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-004 |
| BOQ Format (CPWD-style) | Schedule | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-005 |
| BOQ Format (PWD-style) | Schedule | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-006 |
| EMD (Earnest Money Deposit) Register | Register | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-007 |
| Performance Bank Guarantee (PBG) Tracker | Register | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-008 |
| Pre-Bid Query Register | Register | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-009 |
| Bid Comparison Statement (Techno-Commercial) | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-010 |
| Deviation Sheet — Technical | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-011 |
| Deviation Sheet — Commercial | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-012 |
| Letter of Intent (LOI) | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-013 |
| Letter of Award (LOA) | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-014 |
| Performance BG Submission Letter | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-015 |
| Mobilisation Advance Request | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-016 |
| Interim Payment Certificate (IPC) | Register | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-017 |
| Vendor / Sub-Contractor Empanelment | Form | Tendering & Contracts | CPWD Works Manual 2019FIDIC Red Book+1 | FMT-TND-018 |
| Bar Bending Schedule (BBS) — Beam | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-001 |
| Bar Bending Schedule (BBS) — Column | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-002 |
| Bar Bending Schedule (BBS) — Slab | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-003 |
| Bar Bending Schedule (BBS) — Footing | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-004 |
| Bar Bending Schedule (BBS) — Pile / Pile Cap | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-005 |
| Level Book Format | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-006 |
| Setting-Out / Line-Out Register | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-007 |
| Pour Card — Column | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-008 |
| Pour Card — Beam | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-009 |
| Pour Card — Slab | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-010 |
| Pour Card — Raft / Mat Foundation | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-011 |
| Pour Permit (Concrete) | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-012 |
| Concrete Cube Test Log | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-013 |
| Slump Test Log | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-014 |
| Daily Concrete Pour Register | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-015 |
| Daily Progress Report (DPR) — Site | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-016 |
| Weekly Progress Report — Site | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-017 |
| Brickwork Inspection Checklist | Checklist | Site Execution | IS 456IS 2502+2 | FMT-SIT-018 |
| Plaster Inspection Checklist | Checklist | Site Execution | IS 456IS 2502+2 | FMT-SIT-019 |
| Blockwork Inspection Checklist | Checklist | Site Execution | IS 456IS 2502+2 | FMT-SIT-020 |
| Shuttering / Formwork Inspection | Checklist | Site Execution | IS 456IS 2502+2 | FMT-SIT-021 |
| De-shuttering Permit | Form | Site Execution | IS 456IS 2502+2 | FMT-SIT-022 |
| Reinforcement Fixing Inspection | Checklist | Site Execution | IS 456IS 2502+2 | FMT-SIT-023 |
| Formwork Removal Schedule | Schedule | Site Execution | IS 456IS 2502+2 | FMT-SIT-024 |
| Curing Register | Register | Site Execution | IS 456IS 2502+2 | FMT-SIT-025 |
| GRN (Goods Received Note) | Form | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-001 |
| Indent / MIR (Material Issue Request) | Form | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-002 |
| Issue Voucher | Form | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-003 |
| Material Returns Note | Form | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-004 |
| Bin Card | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-005 |
| Monthly Stores Reconciliation | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-006 |
| Cement Consumption Register | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-007 |
| Steel Consumption Register | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-008 |
| Stores Inward Register | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-009 |
| Dead Stock Register | Register | Stores & Materials | CPWD Works Manual 2019ISO 9001 | FMT-STR-010 |
| Rate Analysis — PCC (Plain Cement Concrete) | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-001 |
| Rate Analysis — RCC M25 | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-002 |
| Rate Analysis — Brickwork (1st class) | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-003 |
| Rate Analysis — Plaster (Internal 1:4) | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-004 |
| Rate Analysis — Plaster (External 1:6) | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-005 |
| Rate Analysis — Shuttering / Formwork | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-006 |
| Labour Productivity Sheet | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-007 |
| Plant Productivity Sheet | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-008 |
| Overhead & Profit Computation | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-009 |
| Escalation / Price Adjustment Calculation | Form | Estimation & Rate Analysis | CPWD DSRIS 1200 | FMT-EST-010 |
| AHU (Air Handling Unit) Commissioning Checklist | Checklist | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-001 |
| Chiller Commissioning Checklist | Checklist | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-002 |
| DG Set Load Test Protocol | Test Report | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-003 |
| Lift / Elevator Testing Protocol | Test Report | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-004 |
| Fire Alarm System (FAS) T&C Protocol | Test Report | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-005 |
| PA / Public Address System T&C | Test Report | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-006 |
| LT Panel Schedule | Schedule | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-007 |
| Cable Schedule | Schedule | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-008 |
| Earthing Test Register | Register | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-009 |
| IR (Insulation Resistance) Test Register | Register | MEP Testing & Commissioning | IS 732IS 13364+1 | FMT-MEP-010 |
| Building Permit Application (BPA) Checklist | Checklist | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-001 |
| Fire NOC Application | Form | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-002 |
| Occupation Certificate (OC) Application | Form | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-003 |
| Completion Certificate (CC) Application | Form | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-004 |
| AERB License Tracker | Register | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-005 |
| Pollution NOC (CPCB / SPCB) Tracker | Register | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-006 |
| Factory License Application | Form | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-007 |
| Rain Water Harvesting (RWH) Compliance | Checklist | Statutory & NOCs | NBC 2016Factories Act 1948+1 | FMT-STA-008 |
| Quarterly Progress Report (QPR) — RERA | Register | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-001 |
| Form 5 — Annual Audit Report (RERA) | Form | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-002 |
| Escrow Account Reconciliation | Register | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-003 |
| Allotment Letter | Form | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-004 |
| Possession Letter | Form | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-005 |
| Customer Ledger / Demand Letter | Register | RERA & Real Estate | RERA Act 2016RERA Rules 2017 | FMT-RER-006 |
| Control Point Register | Register | Survey & Geomatics | IS 14252IS 1892 | FMT-SUR-001 |
| Traverse Register | Register | Survey & Geomatics | IS 14252IS 1892 | FMT-SUR-002 |
| Total Station Reading Sheet | Register | Survey & Geomatics | IS 14252IS 1892 | FMT-SUR-003 |
| DGPS / GPS Observation Log | Register | Survey & Geomatics | IS 14252IS 1892 | FMT-SUR-004 |
| Cross-Section Format | Schedule | Survey & Geomatics | IS 14252IS 1892 | FMT-SUR-005 |
| Bore Log Format | Register | Geotechnical | IS 1892IS 1888+2 | FMT-GEO-001 |
| SPT Test Sheet | Test Report | Geotechnical | IS 1892IS 1888+2 | FMT-GEO-002 |
| Plate Load Test Sheet | Test Report | Geotechnical | IS 1892IS 1888+2 | FMT-GEO-003 |
| CBR Test Sheet | Test Report | Geotechnical | IS 1892IS 1888+2 | FMT-GEO-004 |
| Lab Test Request Form | Form | Geotechnical | IS 1892IS 1888+2 | FMT-GEO-005 |
| 3A / 3D Notification Tracker (NHAI) | Register | Land Acquisition & RoW | NH Act 1956RFCTLARR Act 2013 | FMT-LAN-001 |
| LA Act §4(1) / §6(1) Notice Register | Register | Land Acquisition & RoW | NH Act 1956RFCTLARR Act 2013 | FMT-LAN-002 |
| R&R Compensation Register | Register | Land Acquisition & RoW | NH Act 1956RFCTLARR Act 2013 | FMT-LAN-003 |
Indian construction runs on paperwork — and the paperwork is format-driven. The contractor's site office prints stacks of GRNs, MIRs, bin cards, pour cards, BBS sheets every week. The PMC office tracks IPCs, FPCs, MOMs, and risk registers. The developer files RERA QPRs every quarter. The surveyor maintains traverse and level books from day one of site mobilization. Without standardised formats, you get inconsistency across sites, lost data between contractors, audit failures during ISO/RERA/NABL reviews, and disputes that drag on for years.
The CPWD Works Manual 2019, MoRTH Specifications for Road & Bridge Works, FIDIC Conditions of Contract, IS 456, IS 1786, IS 383, RERA Act 2016, and BOCW Act 1996 all explicitly or implicitly require certain documents — IPCs per the contract, MTC verification per IS 1786, NCRs per ISO 9001, QPRs per RERA Section 11(1)(d). InfraLens Formats provides the operational documents themselves — pre-formatted, code-mapped, ready to print or fill in Excel.
Three role-hubs on InfraLens: PMC Templates is the consultant's toolkit (150 templates for site oversight). QA/QC Templates is the quality engineer's toolkit (300+ checklists, test reports, ITPs). Formats is everything else — the contractor's, storekeeper's, surveyor's, developer's, MEP engineer's day-to-day documents. Together the three hubs cover the full lifecycle: tender → mobilise → execute → bill → quality-check → hand over.
Tendering (18 formats): BOQ format (CPWD + PWD), PQ application, technical bid compliance, financial bid (item rate + percentage rate), EMD register, bid bond tracker, pre-bid query register, bid comparison statement, deviation sheets (tech + commercial), LOI/LOA templates, performance bank guarantee submission, mobilisation advance request, tender schedule, vendor empanelment.
Site Execution (25 formats): Bar Bending Schedule (BBS) for beam / column / slab / footing / pile, level book, setting-out register, pour cards (column / beam / slab / raft), pour permit, concrete cube log, slump test log, daily pour register, site DPR, site WPR, brickwork / plaster / blockwork inspection, shuttering inspection, de-shuttering permit, reinforcement fixing inspection, formwork removal schedule, curing register.
Stores (10 formats): GRN (Goods Received Note), Indent / MIR, issue voucher, material returns note, bin card, monthly reconciliation, cement consumption register, steel consumption register, stores inward register, dead stock register.
Estimation & Rate Analysis (10 formats): Rate analysis for PCC, RCC M25, brickwork, plaster (internal + external), shuttering; labour productivity, plant productivity, overhead & profit computation, escalation calculation per price-adjustment formula.
MEP Testing & Commissioning (10 formats): AHU commissioning, chiller commissioning, DG set load test, lift / elevator testing protocol, fire alarm (FAS) T&C, PA system T&C, LT panel schedule, cable schedule, earthing test register, IR (insulation resistance) test register.
Statutory / NOC (8 formats): Building permit application (BPA) checklist, fire NOC, OC application, CC application, AERB license tracker, pollution NOC (CPCB / SPCB) tracker, factory license application, rain water harvesting compliance.
RERA (6 formats): Quarterly Progress Report (QPR), Form 5 (Annual Audit), escrow account reconciliation, allotment letter, possession letter, customer ledger / demand letter.
Survey (5 formats): Control point register, traverse register, total station reading sheet, DGPS observation log, cross-section format.
Geotechnical (5 formats): Bore log, SPT test sheet, plate load test, CBR test sheet, lab test request form.
Land Acquisition (3 formats): 3A/3D notification tracker (NHAI), LA Act Section 4(1)/6(1) notice register, R&R (Resettlement & Rehabilitation) compensation register.
Contractor's site office — start with the Site Execution family (BBS, pour cards, daily reports) + Stores (GRN, bin card) + Tendering (BOQ formats for the next bid). Roughly 50 of the 100 formats are directly used by a contractor's site team.
PMC / Consultant — primarily use PMC Templates (MOMs, IPC certification, audit reports), but cross-reference Tendering formats during bid evaluation + Statutory trackers for compliance oversight.
Developer / Real-estate — RERA quarterly and annual filings + Statutory (BPA, OC, fire NOC) + selective Site Execution trackers from contractor.
Surveyor — Survey family from day 1 (control points, traverse, level book) + Geotech during initial soil investigation.
MEP contractor — MEP T&C family for system commissioning + Stores for material tracking + Tendering during bidding.
Project manager — uses all 10 work-streams selectively. The Estimation rate analysis sheets and Tendering BOQ formats are the most commercially valuable; the Site Execution + Stores formats are operational backbone.
Each format on InfraLens is downloadable as Excel (editable, with formulas where applicable) and PDF (print-ready). Most are 1-3 pages; the BOQ and rate analysis formats are tabular, ready for population. All formats are mapped to the relevant IS code, IRC code, FIDIC sub-clause, CPWD Works Manual chapter, or statutory Act / Rule wherever applicable.
10 common questions about this topic, answered by civil engineers.
A BBS is a table listing every reinforcement bar in a concrete element — bar mark, diameter, shape, length, number of pieces, weight. It's the procurement document for steel and the issue document for steel-fixers. Prepare per IS 2502:1963 (Code of Practice for Bending and Fixing of Bars). Columns: Bar Mark, Diameter (mm), Type / Shape Sketch, Length (mm), No. of Bars, Total Length (m), Unit Weight (kg/m per IS 1786 Table 3), Total Weight (kg). One BBS per element (footing, column, beam, slab) is standard; site uses it to cut + bend rebar before fixing. Total weight from BBS × wastage factor (~3-5%) = procurement quantity.
GRN (Goods Received Note) is filled when material arrives at site — it records the supplier, invoice number, quantity received, quality check status. The storekeeper signs the GRN to acknowledge receipt; the GRN is the basis for raising the bill. MIR (Material Issue Request) or Indent is filled by the site engineer requesting material from stores — element, quantity, date needed. The storekeeper checks bin card, issues against the MIR. Issue Voucher is the storekeeper's confirmation that material was actually issued to the requesting site engineer, with quantity, date, signature. These three documents — GRN, MIR, Issue Voucher — form the audit trail from supplier to site consumption.
RERA Form 5 is the Annual Audit Report that every promoter must file with the state RERA Authority within 6 months of the end of each financial year. It's a Chartered Accountant's certificate confirming that (a) 70% of amounts collected from allottees were deposited into the project-specific escrow account, (b) withdrawals were proportionate to the percentage of construction completion, (c) project finances are healthy. Required per RERA Act 2016 Section 4(2)(l)(D) and state RERA rules. Quarterly progress reports (QPRs) are separate — they're filed every 3 months, covering work done, photos, money received, money spent, expected completion date. Both forms vary by state RERA; MahaRERA, RERA Karnataka, RERA Haryana each have slightly different templates.
A Performance Bank Guarantee (PBG) is a bank guarantee submitted by the contractor securing performance of the contract — typically 5-10% of contract value per CPWD or 5% per FIDIC Red Book Sub-Clause 4.2. Issued by a scheduled commercial bank, valid for the contract period + defects liability period (usually 12-24 months). The Performance BG Tracker format records: BG number, issuing bank, amount, validity from-to, project, contractor, status (live / extended / claimed / released). Common issues tracked: BG expiry (renewal needed 30 days before expiry), claim invocation (during disputes), release after DLP completion. Every contract has a separate PBG — the tracker maintains the portfolio for the PMC / developer.
Price Adjustment (PA) or Escalation compensates the contractor for cost increases over a long-duration contract. The standard CPWD / MoRTH formula breaks the contract into components (cement, steel, bitumen, labour, fuel, others) each with a weightage and an indexed base + current price. Formula: PA = Contract Value × Σ (Weight × (Index_Now − Index_Base) / Index_Base). Indices used: All India WPI for cement / steel (released monthly by Economic Advisor's office), Labour wage rate from CPWD Schedule, RBI fuel index. The Escalation Calculation format does this computation for each Running Account Bill — typically applied after 24 months from contract date or quarterly depending on contract terms. For DSR-based contracts, the analogous concept is star rate for new items not in the schedule.
The Plate Load Test (PLT) is conducted per IS 1888:1982 to determine the safe bearing capacity and settlement characteristics of soil at the foundation level. A steel plate (300mm × 300mm or 600mm × 600mm) is placed at the test depth, loaded incrementally (5 increments to design load + 50%), and settlement is measured at each increment. Output: load-settlement curve, ultimate bearing capacity (load at which curve becomes asymptotic), safe bearing capacity (ultimate / factor of safety, typically 2.5-3). Test is performed for important structures > 3 floors or wherever soil is variable; minimum 2-3 tests per building. The Plate Load Test format records the apparatus, load increments, settlement readings every 5-10 min until stable, and computed bearing capacity.
Under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 (LA Act 2013, also called RFCTLARR Act), Section 4(1) is the preliminary notification that the government intends to acquire land for a public purpose. It triggers the Social Impact Assessment (SIA) under Section 4(2). After SIA, Section 6(1) is the declaration of acquisition. Section 11 is the public notice + objections period. Section 19 is the award (compensation determination). The LA Act notice register tracks each notification (3A under NHAI Act 1956 for highways, or Section 4(1) under RFCTLARR for general acquisition), dates, area notified, objections received, status. Each highway project from NHAI follows the National Highways Act 1956 Sections 3A, 3D, 3G (faster process for highways, ~1 year).
Insulation Resistance (IR) Test checks the integrity of electrical cable insulation by applying a DC voltage (500V or 1000V depending on system voltage) between conductor and earth using a megger instrument. Per IS 732:2019 (Code of Practice for Electrical Wiring Installations), the minimum acceptable IR value is 1 megohm (for low-voltage systems up to 500V) or higher for HV systems. Test is conducted: (a) Before commissioning every new circuit, (b) After any modification, (c) Periodic preventive maintenance — typically annually for industrial, 5-yearly for residential. The IR Test Register records: circuit ID, cable size, voltage, megger reading at 1 minute, polarisation index (10-min reading / 1-min reading — > 2 is good), pass/fail, signed by electrical engineer.
Yes — all 100 InfraLens formats are free to download, free to edit, and free to use on commercial construction projects. There's no watermark, no licensing fee, no attribution requirement. Use them as-is, modify the heading to add your company name and logo, integrate them into your project quality manual. The underlying IS / IRC / FIDIC / CPWD / RERA references in the formats are public domain — InfraLens's contribution is the synthesis, the cross-references, and the field-tested structure. If you find an error or want to suggest improvements, contact us.
The format structure (table columns, sections, signoff blocks) is universally applicable to any civil construction project. The specific code references (IS, IRC, CPWD, RERA, BOCW) are India-specific. For projects using ASTM, BS, EN, or FIDIC-based contracts internationally, replace the IS code references with the contract-specified standards (e.g., "per IS 456" becomes "per ACI 318" or "per BS 8110"). The pour card, BBS, GRN, level book, traverse register, bore log, plate load test structures are independent of jurisdiction. Tendering formats (BOQ, IPC) follow CPWD format but the FIDIC-style equivalents are very similar. RERA formats are India-specific (no direct international equivalent).