QA/QC  › Method Statements  › Waterproofing Method Statement
Form · QC-MST-FRM-008

Waterproofing Method Statement

26 checkpoints across 8 sections. Before starting the activity — submit to consultant for approval
26 Checkpoints
8 Sections
Per activity, per project
Contractor PM, QA/QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SCOPE & REFERENCES
A1Scope — terrace (APP/SBS/PU/cementitious), basement (crystalline/membrane), wet areas (acrylic)
Acceptance: All WP locations listed; system per spec; manufacturer + applicator approved
Cl. 1 — Scope
OK
NC
NA
HOLD
A2Approved system TDS, MSDS, warranty terms, and applicator certification available
Acceptance: TDS signed off; 10 yr warranty from applicator + manufacturer; applicator licensed
Cl. 3 — System approval
OK
NC
NA
HOLD
A3References: IS 3067 (general), IS 9918 (bitumen felt), IS 7193 (glass-fibre felt), manufacturer data
Acceptance: Codes and drawings available; details for parapet/drain/penetration approved
Cl. 2 — References
OK
NC
NA
HOLD
B. MATERIALS & EQUIPMENT
B1WP membrane / coating — batches within shelf life; batch no. traceable to MTC
Acceptance: Shelf life valid; original sealed packs; MTC attached; physical test per spec
Cl. 5 — Materials
OK
NC
NA
HOLD
B2Primers, sealants, fillets, reinforcing mesh — compatible system components from same manufacturer
Acceptance: System-compatible primer; fillets at 90° corners; mesh at junctions; no mixing brands
Cl. 5 — Ancillary
OK
NC
NA
HOLD
B3Equipment — torch (APP), rollers, spray rigs, heat blower, spark tester — in working order
Acceptance: Tools operational; calibrated gauges; spark tester 15-25 kV; safety fire extinguishers ready
Cl. 6 — Equipment
OK
NC
NA
HOLD
C. SITE PREPARATION / PRE-REQUISITES
C1Substrate concrete age ≥28 d; moisture <5% (bitumen) or <8% (PU) by CM-meter / calcium-chloride test
Acceptance: Age met; moisture within spec; test reports attached; substrate cured and dry
Cl. 4 — Substrate
OK
NC
NA
HOLD
C2Surface prep — grinding / shot-blasting / power-washing to remove laitance; voids filled
Acceptance: Surface sound, clean, uniform; CSP 2-3; cracks >0.3 mm filled with approved epoxy
Cl. 4 — Surface
OK
NC
NA
HOLD
C3Slope / drainage — 1:60 to 1:100 to drain; ponding eliminated; khurra / drain outlets prepared
Acceptance: Slope verified; no ponding >1:150; drain outlets flared and accessible
Cl. 5 — Slope
OK
NC
NA
HOLD
Showing 9 of 26 checkpoints ·
A. SCOPE & REFERENCES
A1Scope — terrace (APP/SBS/PU/cementitious), basement (crystalline/membrane), wet areas (acrylic)
Cl. 1 — Scope (IS 3067)
All WP locations listed; system per spec; manufacturer + applicator approved
OKNCNAHOLD
A2Approved system TDS, MSDS, warranty terms, and applicator certification available
Cl. 3 — System approval (IS 3067)
TDS signed off; 10 yr warranty from applicator + manufacturer; applicator licensed
OKNCNAHOLD
A3References: IS 3067 (general), IS 9918 (bitumen felt), IS 7193 (glass-fibre felt), manufacturer data
Cl. 2 — References (IS 3067)
Codes and drawings available; details for parapet/drain/penetration approved
OKNCNAHOLD
B. MATERIALS & EQUIPMENT
B1WP membrane / coating — batches within shelf life; batch no. traceable to MTC
Cl. 5 — Materials (IS 3067)
Shelf life valid; original sealed packs; MTC attached; physical test per spec
OKNCNAHOLD
B2Primers, sealants, fillets, reinforcing mesh — compatible system components from same manufacturer
Cl. 5 — Ancillary (IS 3067)
System-compatible primer; fillets at 90° corners; mesh at junctions; no mixing brands
OKNCNAHOLD
B3Equipment — torch (APP), rollers, spray rigs, heat blower, spark tester — in working order
Cl. 6 — Equipment (IS 3067)
Tools operational; calibrated gauges; spark tester 15-25 kV; safety fire extinguishers ready
OKNCNAHOLD
C. SITE PREPARATION / PRE-REQUISITES
C1Substrate concrete age ≥28 d; moisture <5% (bitumen) or <8% (PU) by CM-meter / calcium-chloride test
Cl. 4 — Substrate (IS 3067)
Age met; moisture within spec; test reports attached; substrate cured and dry
OKNCNAHOLD
C2Surface prep — grinding / shot-blasting / power-washing to remove laitance; voids filled
Cl. 4 — Surface (IS 3067)
Surface sound, clean, uniform; CSP 2-3; cracks >0.3 mm filled with approved epoxy
OKNCNAHOLD
C3Slope / drainage — 1:60 to 1:100 to drain; ponding eliminated; khurra / drain outlets prepared
Cl. 5 — Slope (IS 3067)
Slope verified; no ponding >1:150; drain outlets flared and accessible
OKNCNAHOLD
Showing 9 of 26 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED — NCR RAISED
Remarks
Name / Sign / Date
Prepared By
Name / Sign / Date
Approved By
Name / Sign / Date