Pre-Commissioning Method Statement
26 checkpoints across 8 sections. Before starting the activity — submit to consultant for approval
26 Checkpoints
8 Sections
Per activity, per project
Contractor PM, QA/QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SCOPE & REFERENCES
A1Scope: pre-commissioning of MEP — electrical (LV/HV), HVAC, plumbing, fire-fighting, lifts, BMS
Acceptance: All systems for pre-commissioning listed; sequence and dependencies mapped
NBC 2016 Pt 8 Cl.1 — Scope
OK
NC
NA
HOLD
A2References: NBC 2016 Part 8, IS 732 (electrical), IS 1172 (plumbing), system datasheets, ISO 9001 QAP
Acceptance: Codes, drawings, vendor manuals, and approved QAP at site
NBC 2016 Pt 8 Cl.2 — References
OK
NC
NA
HOLD
A3Pre-commissioning team — site engineers, vendor reps, consultant — identified with R&R
Acceptance: Team chart with names / roles / contacts; vendor commissioning engineers confirmed
ISO 9001 Cl.7.2 — Competence
OK
NC
NA
HOLD
B. MATERIALS & EQUIPMENT
B1Test instruments calibrated within validity — multimeter, IR tester, pressure gauge, anemometer, lux-meter
Acceptance: Calibration certificates valid (NABL); instruments tagged with due-date
ISO 9001 Cl.7.1.5 — Calibration
OK
NC
NA
HOLD
B2Test consumables — flushing water, lubricants, refrigerants, fuel for DG, dummy loads — arranged
Acceptance: All consumables on site; vendor representative present for refrigerant / fuel handling
NBC 2016 Pt 8 Cl.5 — Consumables
OK
NC
NA
HOLD
B3Spare parts kit and start-up tool kit per vendor manual on site for first-fix issues
Acceptance: Spare parts list checked; commissioning kit complete
NBC 2016 Pt 8 Cl.5 — Spares
OK
NC
NA
HOLD
C. SITE PREPARATION / PRE-REQUISITES
C1All MEP installation works mechanically completed — punch-list closed for system under test
Acceptance: Mechanical completion certificate issued; snag list <5%; safety clearances obtained
NBC 2016 Pt 8 Cl.5 — Mech. complete
OK
NC
NA
HOLD
C2Permanent / temporary power, water, drainage available for pre-commissioning activities
Acceptance: Power, water, drainage tied in; capacity adequate for testing loads
NBC 2016 Pt 8 Cl.5 — Utilities
OK
NC
NA
HOLD
C3Statutory clearances initiated — Electrical Inspectorate, Fire NOC, Lift Inspectorate, BWSSB
Acceptance: Applications filed; inspections scheduled; preliminary clearances received
NBC 2016 Pt 8 Cl.10 — Statutory
OK
NC
NA
HOLD
Showing 9 of 26 checkpoints ·
A. SCOPE & REFERENCES
A1Scope: pre-commissioning of MEP — electrical (LV/HV), HVAC, plumbing, fire-fighting, lifts, BMS
NBC 2016 Pt 8 Cl.1 — Scope (NBC 2016)
All systems for pre-commissioning listed; sequence and dependencies mapped
OKNCNAHOLD
A2References: NBC 2016 Part 8, IS 732 (electrical), IS 1172 (plumbing), system datasheets, ISO 9001 QAP
NBC 2016 Pt 8 Cl.2 — References (NBC 2016)
Codes, drawings, vendor manuals, and approved QAP at site
OKNCNAHOLD
A3Pre-commissioning team — site engineers, vendor reps, consultant — identified with R&R
ISO 9001 Cl.7.2 — Competence (ISO 9001)
Team chart with names / roles / contacts; vendor commissioning engineers confirmed
OKNCNAHOLD
B. MATERIALS & EQUIPMENT
B1Test instruments calibrated within validity — multimeter, IR tester, pressure gauge, anemometer, lux-meter
ISO 9001 Cl.7.1.5 — Calibration (ISO 9001)
Calibration certificates valid (NABL); instruments tagged with due-date
OKNCNAHOLD
B2Test consumables — flushing water, lubricants, refrigerants, fuel for DG, dummy loads — arranged
NBC 2016 Pt 8 Cl.5 — Consumables (NBC 2016)
All consumables on site; vendor representative present for refrigerant / fuel handling
OKNCNAHOLD
B3Spare parts kit and start-up tool kit per vendor manual on site for first-fix issues
NBC 2016 Pt 8 Cl.5 — Spares (NBC 2016)
Spare parts list checked; commissioning kit complete
OKNCNAHOLD
C. SITE PREPARATION / PRE-REQUISITES
C1All MEP installation works mechanically completed — punch-list closed for system under test
NBC 2016 Pt 8 Cl.5 — Mech. complete (NBC 2016)
Mechanical completion certificate issued; snag list <5%; safety clearances obtained
OKNCNAHOLD
C2Permanent / temporary power, water, drainage available for pre-commissioning activities
NBC 2016 Pt 8 Cl.5 — Utilities (NBC 2016)
Power, water, drainage tied in; capacity adequate for testing loads
OKNCNAHOLD
C3Statutory clearances initiated — Electrical Inspectorate, Fire NOC, Lift Inspectorate, BWSSB
NBC 2016 Pt 8 Cl.10 — Statutory (NBC 2016)
Applications filed; inspections scheduled; preliminary clearances received
OKNCNAHOLD
Showing 9 of 26 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED — NCR RAISED
Remarks
Name / Sign / Date
Prepared By
Name / Sign / Date
Approved By
Name / Sign / Date