HandbookReady-Mix Concrete Acceptance Criteria

Ready-Mix Concrete Acceptance Criteria

IS 4926:2003 · IS 4926 — Ready-Mixed Concrete & IS 456 Cl. 16.1 — Acceptance Criteria
Complete acceptance criteria for ready-mixed concrete at site. Covers delivery ticket verification, slump testing, transit time limits, cube casting frequency, and strength acceptance rules per IS 4926 and IS 456.
IS 4926
22 items shown
Delivery Checks
Verify before unloading each transit mixer at site
CheckRequirementToleranceIf Failed
Delivery ticket / challanMust accompany every transit mixer and state: batch time, grade, mix design reference, slump ordered, volume, batch plant addressNo tolerance — mandatory documentDo not accept concrete without a valid delivery ticket
Grade ordered vs deliveredGrade on ticket must match site order (e.g., M30, M40)No tolerance — exact match requiredReject the load; do not use higher or lower grade as substitute without engineer's approval
Volume deliveredActual volume must match ordered quantity within tolerance±3% by volumeRecord shortage; raise claim with RMC supplier
Batch time vs arrival timeNote exact time of batching (from ticket) and arrival at siteTransit time ≤ 2 hours from batchingReject if transit time exceeds 2 hours; concrete may have started initial set
Drum revolution counterTotal drum revolutions from batching to discharge must not exceed 300Max 300 revolutions totalReject concrete — over-mixing causes segregation and loss of workability
Seal / lock on water tankWater tank on transit mixer must be sealed to prevent unauthorised water additionSeal must be intactIf seal is broken, reject the load — water may have been added in transit (retempering)
Slump & Workability Tests
Slump test per IS 1199 — at point of discharge before placing
CheckRequirementToleranceIf Failed
Slump test for ordered slump ≤ 75 mmMeasured slump must be within ±25 mm of ordered value±25 mmReject if outside tolerance; record and report to supplier
Slump test for ordered slump 75–100 mmMeasured slump must be within ±25 mm of ordered value±25 mmReject if outside tolerance
Slump test for ordered slump > 100 mmMeasured slump must be within ±25 mm of ordered value±25 mmReject if outside tolerance
Slump testing frequencyTest every transit mixer load at siteNo test = no acceptance — insist on testing every load
Visual check for segregationConcrete must appear uniform with no separation of paste and aggregateNo visible segregation or bleedingReject load; segregated concrete cannot be re-mixed
Shear slump or collapse slumpSlump cone must give a true slump (not shear or collapse)If shear slump occurs, re-test with fresh sampleRepeated shear slump indicates poor mix design — reject and report
Strength Acceptance (IS 456 Cl. 16.1)
Cube strength acceptance based on 28-day compressive strength results
CheckRequirementToleranceIf Failed
Cube casting frequencyMinimum 1 sample per 25 m³ or part thereof1 sample = 3 cubes (150 mm)If frequency not maintained, quality records are considered incomplete
Individual test result (3-cube average)≥ fck − 3 MPaNo individual result shall fall below thisInvestigate — may require core testing of structure (IS 456 Cl. 17.4)
Mean of 3 consecutive results (M20 and above)≥ fck + 0.825σ or ≥ fck + 4 MPa, whichever is higherσ = standard deviation from 30+ results; use assumed σ if < 30 resultsNon-compliant — review mix design, increase cement content, or change supplier
Mean of 3 consecutive results (below M20)≥ fck + 4 MPaMix design to be revised by supplier
Core test (if cubes fail)Core strength ≥ 0.85 × fckAverage of 3 cores ≥ 0.85 × fck; no individual core < 0.75 × fckIf cores also fail, structural assessment required — may need strengthening or demolition
Temperature & Time Limits
Transport and placing temperature requirements for RMC
CheckRequirementToleranceIf Failed
Concrete temperature at dischargeMeasure with stem thermometer at point of discharge5°C to 40°C (normal range); preferred ≤ 30°C in hot weatherReject if outside 5–40°C range
Transit time — normal weather≤ 2 hours from time of adding water to cementNo extension without retarderReject concrete exceeding 2 hours transit
Transit time — hot weather (> 35°C)≤ 1 hour recommended; max 1.5 hours with retarderUse retarding admixture per IS 9103Reject if workability is lost even within time limit
Placing time after dischargePlace within 30 minutes of discharge from transit mixerNo holding in chutes or pumps beyond 30 minDiscard concrete that has been standing for > 30 min after discharge
Retempering with waterNot permitted under any circumstancesZero toleranceReject immediately — water addition alters w/c ratio and destroys mix design
Notes
Retempering (adding water at site to increase slump) is strictly prohibited by IS 4926. Only addition of superplasticiser by trained RMC technician is permitted for slump recovery.
Pump line losses: expect 25–50 mm slump loss through the pipeline. Order slump 25 mm higher than required at point of placing when using a boom pump.
Rejection protocol: rejected loads must be documented with ticket number, reason, time, and photographed. Notify RMC supplier immediately and confirm in writing.
For structural concrete, insist on RMC plants certified under IS 4926 with current BIS licence. Uncertified plants may not follow proper batching and QC procedures.
Cube moulds must be oiled and kept on a level vibration-free surface. Cubes should be covered with wet cloth within 30 minutes of casting.
Maintain a concrete register at site recording: date, structural element, grade, ticket number, supplier, transit mixer number, slump, temperature, cube IDs, and acceptance/rejection status.
← Previous
Rebar Field Testing Requirements
Next →
Site Safety Checklist
Generated by InfraLens · infralens.in