IS 4926:2003 · IS 4926 — Ready-Mixed Concrete & IS 456 Cl. 16.1 — Acceptance Criteria
Complete acceptance criteria for ready-mixed concrete at site. Covers delivery ticket verification, slump testing, transit time limits, cube casting frequency, and strength acceptance rules per IS 4926 and IS 456.
Average of 3 cores ≥ 0.85 × fck; no individual core < 0.75 × fck
If cores also fail, structural assessment required — may need strengthening or demolition
Temperature & Time Limits
Transport and placing temperature requirements for RMC
Check
Requirement
Tolerance
If Failed
Concrete temperature at discharge
Measure with stem thermometer at point of discharge
5°C to 40°C (normal range); preferred ≤ 30°C in hot weather
Reject if outside 5–40°C range
Transit time — normal weather
≤ 2 hours from time of adding water to cement
No extension without retarder
Reject concrete exceeding 2 hours transit
Transit time — hot weather (> 35°C)
≤ 1 hour recommended; max 1.5 hours with retarder
Use retarding admixture per IS 9103
Reject if workability is lost even within time limit
Placing time after discharge
Place within 30 minutes of discharge from transit mixer
No holding in chutes or pumps beyond 30 min
Discard concrete that has been standing for > 30 min after discharge
Retempering with water
Not permitted under any circumstances
Zero tolerance
Reject immediately — water addition alters w/c ratio and destroys mix design
Notes
• Retempering (adding water at site to increase slump) is strictly prohibited by IS 4926. Only addition of superplasticiser by trained RMC technician is permitted for slump recovery.
• Pump line losses: expect 25–50 mm slump loss through the pipeline. Order slump 25 mm higher than required at point of placing when using a boom pump.
• Rejection protocol: rejected loads must be documented with ticket number, reason, time, and photographed. Notify RMC supplier immediately and confirm in writing.
• For structural concrete, insist on RMC plants certified under IS 4926 with current BIS licence. Uncertified plants may not follow proper batching and QC procedures.
• Cube moulds must be oiled and kept on a level vibration-free surface. Cubes should be covered with wet cloth within 30 minutes of casting.
• Maintain a concrete register at site recording: date, structural element, grade, ticket number, supplier, transit mixer number, slump, temperature, cube IDs, and acceptance/rejection status.