QA/QC  › Method Statements  › Plastering Method Statement
Form · QC-MST-FRM-007

Plastering Method Statement

26 checkpoints across 8 sections. Before starting the activity — submit to consultant for approval
26 Checkpoints
8 Sections
Per activity, per project
Contractor PM, QA/QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SCOPE & REFERENCES
A1Scope: internal plaster (12-15 mm), external plaster (18-20 mm two-coat), ceiling plaster
Acceptance: All plaster areas, thicknesses, and mixes listed per drawing and specification
Cl. 1 — Scope
OK
NC
NA
HOLD
A2Mix — CM 1:4 or 1:5 (int), CM 1:4 with waterproofing (ext); double-coat external per IS 2402
Acceptance: Approved mix per location; waterproofing admixture approved; dosage calibrated
Cl. 4 — Mix
OK
NC
NA
HOLD
A3References: IS 1661, IS 1542 (sand), IS 2402 (external render), drawings, finishes schedule
Acceptance: Applicable codes and finishes schedule available at workface
Cl. 2 — References
OK
NC
NA
HOLD
B. MATERIALS & EQUIPMENT
B1Cement stored dry; sand per IS 1542 — FM 1.5-2.2, silt ≤5%, no organic matter
Acceptance: Cement fresh (no lumps); sand washed, sieved; silt test <5%
Cl. 5 — Materials
OK
NC
NA
HOLD
B2Water per IS 456 Cl.5.4 — potable, clean, no deleterious matter
Acceptance: Water test report if source is not potable mains; pH 6-8; chloride <500 ppm
Cl. 5 — Water
OK
NC
NA
HOLD
B3Tools — trowel, float, darby, straight-edge, hawk, plumb, line — at workface
Acceptance: All tools provided; straight-edge ≥2 m; aluminium darby for floating
Cl. 6 — Tools
OK
NC
NA
HOLD
C. SITE PREPARATION / PRE-REQUISITES
C1All MEP chases cut, conduits laid, boxes installed; chicken mesh over chases / joints
Acceptance: Chases filled flush; chicken mesh 150 mm wide over chases and junctions
Cl. 6 — Substrate prep
OK
NC
NA
HOLD
C2Substrate — brickwork cured 7 days / RCC hacked; dust removed; surface wetted before plaster
Acceptance: Masonry age ≥7 d; RCC hacked 50 cuts/dm² or bonding agent; surface SSD
Cl. 6.1 — Surface preparation
OK
NC
NA
HOLD
C3Plaster dots (pads) and screeds set — gauge blocks at 1.5 m c/c for uniform thickness
Acceptance: Dots plumb; screeds connected between dots; thickness gauge verified
Cl. 7 — Screeds
OK
NC
NA
HOLD
Showing 9 of 26 checkpoints ·
A. SCOPE & REFERENCES
A1Scope: internal plaster (12-15 mm), external plaster (18-20 mm two-coat), ceiling plaster
Cl. 1 — Scope (IS 1661)
All plaster areas, thicknesses, and mixes listed per drawing and specification
OKNCNAHOLD
A2Mix — CM 1:4 or 1:5 (int), CM 1:4 with waterproofing (ext); double-coat external per IS 2402
Cl. 4 — Mix (IS 1661)
Approved mix per location; waterproofing admixture approved; dosage calibrated
OKNCNAHOLD
A3References: IS 1661, IS 1542 (sand), IS 2402 (external render), drawings, finishes schedule
Cl. 2 — References (IS 1661)
Applicable codes and finishes schedule available at workface
OKNCNAHOLD
B. MATERIALS & EQUIPMENT
B1Cement stored dry; sand per IS 1542 — FM 1.5-2.2, silt ≤5%, no organic matter
Cl. 5 — Materials (IS 1542)
Cement fresh (no lumps); sand washed, sieved; silt test <5%
OKNCNAHOLD
B2Water per IS 456 Cl.5.4 — potable, clean, no deleterious matter
Cl. 5 — Water (IS 1661)
Water test report if source is not potable mains; pH 6-8; chloride <500 ppm
OKNCNAHOLD
B3Tools — trowel, float, darby, straight-edge, hawk, plumb, line — at workface
Cl. 6 — Tools (IS 1661)
All tools provided; straight-edge ≥2 m; aluminium darby for floating
OKNCNAHOLD
C. SITE PREPARATION / PRE-REQUISITES
C1All MEP chases cut, conduits laid, boxes installed; chicken mesh over chases / joints
Cl. 6 — Substrate prep (IS 1661)
Chases filled flush; chicken mesh 150 mm wide over chases and junctions
OKNCNAHOLD
C2Substrate — brickwork cured 7 days / RCC hacked; dust removed; surface wetted before plaster
Cl. 6.1 — Surface preparation (IS 1661)
Masonry age ≥7 d; RCC hacked 50 cuts/dm² or bonding agent; surface SSD
OKNCNAHOLD
C3Plaster dots (pads) and screeds set — gauge blocks at 1.5 m c/c for uniform thickness
Cl. 7 — Screeds (IS 1661)
Dots plumb; screeds connected between dots; thickness gauge verified
OKNCNAHOLD
Showing 9 of 26 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED — NCR RAISED
Remarks
Name / Sign / Date
Prepared By
Name / Sign / Date
Approved By
Name / Sign / Date