QA/QC  › Roofing & Insulation  › Roofing Installation Register
Register · QC-ROF-REG-001
Roofing Installation Register
11 checkpoints across 1 sections. Maintained throughout roofing works; updated after each inspection batch
11 Checkpoints
1 Sections
Daily/per batch entry
QC Engineer, Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. REGISTER COLUMNS & DEFINITIONS
A1Column 1: Date - Date of roofing work/inspection (DD-MM-YYYY format)
Acceptance: Sequential dates recorded; No gaps; Format consistent
Cl. 1 — Date tracking
OK
NC
NA
HOLD
A2Column 2: Zone / Area - Specific roof zone/building section (e.g., Wing-A, Floor-3, Zone-North)
Acceptance: Zone clearly identified; Consistent naming per building plan; No ambiguity
Cl. 2 — Location identification
OK
NC
NA
HOLD
A3Column 3: Area (m²) - Roofing area laid/inspected on that date
Acceptance: Area measured and recorded (±5%); Cumulative area tracked; Running total maintained
Cl. 3 — Quantity tracking
OK
NC
NA
HOLD
A4Column 4: Material Batch / Lot No. - Manufacturing batch number of sheets used
Acceptance: Batch number from invoice/cert; Links to test results; Traceability maintained
Cl. 4 — Material traceability
OK
NC
NA
HOLD
A5Column 5: Thickness / Gauge - Sheet gauge (e.g., 0.70mm, 0.90mm, 18 SWG)
Acceptance: Gauge matches design; Consistent per zone; Variation documented if multi-gauge
Cl. 5 — Specification verification
OK
NC
NA
HOLD
A6Column 6: Fastener Type & Spacing - Type (screw/bolt) and spacing pattern (e.g., 300mm c/c)
Acceptance: Fastener type noted; Spacing per design; Consistent application per zone
Cl. 6 — Fastening specification
OK
NC
NA
HOLD
A7Column 7: Sealant Applied - Sealant type and extent (e.g., all lap joints, penetrations marked)
Acceptance: Sealant brand noted; Application areas identified; Completion marked
Cl. 7 — Waterproofing tracking
OK
NC
NA
HOLD
A8Column 8: QC Inspection Status - Inspection done (YES/NO) and checklist reference (e.g., QC-ROF-CHK-001)
Acceptance: Inspection status recorded; Checklist ID noted; Links to formal QC report
Cl. 8 — QC linkage
OK
NC
NA
HOLD
A9Column 9: QC Result - PASS / NC / HOLD based on checklist inspection
Acceptance: Result clearly stated (PASS/NC/HOLD); Links to NCR if NC; No blank entries
Cl. 9 — QC verdict
OK
NC
NA
HOLD
A10Column 10: Issues / NCR Raised - If NC, NCR number and brief description (e.g., NCR-001: loose fasteners)
Acceptance: NCR number recorded; Description concise; Links to NCR management system
Cl. 10 — Non-conformance tracking
OK
NC
NA
HOLD
A11Column 11: Inspector Name & Date - QC inspector who conducted inspection and date
Acceptance: Inspector name printed/signed; Inspection date recorded; No blank entries
Cl. 11 — Accountability
OK
NC
NA
HOLD
A. REGISTER COLUMNS & DEFINITIONS
A1Column 1: Date - Date of roofing work/inspection (DD-MM-YYYY format)
Cl. 1 — Date tracking (IS 13592)
Sequential dates recorded; No gaps; Format consistent
OKNCNAHOLD
A2Column 2: Zone / Area - Specific roof zone/building section (e.g., Wing-A, Floor-3, Zone-North)
Cl. 2 — Location identification (IS 13592)
Zone clearly identified; Consistent naming per building plan; No ambiguity
OKNCNAHOLD
A3Column 3: Area (m²) - Roofing area laid/inspected on that date
Cl. 3 — Quantity tracking (IS 13592)
Area measured and recorded (±5%); Cumulative area tracked; Running total maintained
OKNCNAHOLD
A4Column 4: Material Batch / Lot No. - Manufacturing batch number of sheets used
Cl. 4 — Material traceability (IS 277)
Batch number from invoice/cert; Links to test results; Traceability maintained
OKNCNAHOLD
A5Column 5: Thickness / Gauge - Sheet gauge (e.g., 0.70mm, 0.90mm, 18 SWG)
Cl. 5 — Specification verification (IS 13592)
Gauge matches design; Consistent per zone; Variation documented if multi-gauge
OKNCNAHOLD
A6Column 6: Fastener Type & Spacing - Type (screw/bolt) and spacing pattern (e.g., 300mm c/c)
Cl. 6 — Fastening specification (IS 13592)
Fastener type noted; Spacing per design; Consistent application per zone
OKNCNAHOLD
A7Column 7: Sealant Applied - Sealant type and extent (e.g., all lap joints, penetrations marked)
Cl. 7 — Waterproofing tracking (IS 13592)
Sealant brand noted; Application areas identified; Completion marked
OKNCNAHOLD
A8Column 8: QC Inspection Status - Inspection done (YES/NO) and checklist reference (e.g., QC-ROF-CHK-001)
Cl. 8 — QC linkage (IS 13592)
Inspection status recorded; Checklist ID noted; Links to formal QC report
OKNCNAHOLD
A9Column 9: QC Result - PASS / NC / HOLD based on checklist inspection
Cl. 9 — QC verdict (IS 13592)
Result clearly stated (PASS/NC/HOLD); Links to NCR if NC; No blank entries
OKNCNAHOLD
A10Column 10: Issues / NCR Raised - If NC, NCR number and brief description (e.g., NCR-001: loose fasteners)
Cl. 10 — Non-conformance tracking (IS 13592)
NCR number recorded; Description concise; Links to NCR management system
OKNCNAHOLD
A11Column 11: Inspector Name & Date - QC inspector who conducted inspection and date
Cl. 11 — Accountability (IS 13592)
Inspector name printed/signed; Inspection date recorded; No blank entries
OKNCNAHOLD
Inspection Sign-Off
REGISTER COMPLETE & VERIFIED
REGISTER IN PROGRESS
REGISTER SUSPENDED — ISSUES PENDING
Total Area Completed (m²)
Name / Sign / Date
Percentage Completion
Name / Sign / Date
Total NCRs Raised
Name / Sign / Date
Outstanding NCRs
Name / Sign / Date
Remarks
Name / Sign / Date
Register Prepared By
Name / Sign / Date
Reviewed By
Name / Sign / Date