QA/QC  › Roofing & Insulation  › Roofing Installation Method
Form · QC-ROF-FRM-001
Roofing Installation Method Statement
28 checkpoints across 9 sections. Before roofing work commences; must be approved by client and consultant
28 Checkpoints
9 Sections
Once per project or per major phase
Contractor, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. 1. SCOPE OF WORK
A1Scope statement: What specific roofing activities are covered (e.g., sheet laying, insulation, waterproofing, fastening)
Acceptance: Clear description of all activities; Boundaries defined; Exclusions noted if any
Clause 1.1 — Work scope definition
OK
NC
NA
HOLD
A2Materials & specifications: Sheet type, gauge, insulation type, fasteners, sealants specified with part numbers
Acceptance: All materials listed with IS code reference; Part numbers/batch specs noted; Approved source documented
Clause 1.2 — Material specification
OK
NC
NA
HOLD
B. 2. MATERIALS & STORAGE
B1Material storage location: Site location, elevation, weather protection specified
Acceptance: Storage area identified on site plan; Elevation above ground specified; Protection method stated
Clause 2.1 — Storage site identification
OK
NC
NA
HOLD
B2Storage conditions: Temperature range (5-35°C), humidity (<80% RH), UV protection, ventilation requirements stated
Acceptance: Storage method described; Temp/humidity limits stated; Monitoring plan included
Clause 2.2 — Environmental controls
OK
NC
NA
HOLD
B3Material testing plan: Outline of tests to be conducted (thermal conductivity, water absorption, pull-out tests)
Acceptance: Tests listed with reference to IS codes; Sampling plan included; Lab identified
Clause 2.3 — QC testing plan
OK
NC
NA
HOLD
C. 3. SUBSTRATE PREPARATION
C1Roof structure inspection: Visual inspection and confirmation of structural readiness (purlins, level, alignment)
Acceptance: Inspection method described; Acceptance criteria stated (±5mm/m levelness); Sign-off requirement noted
Clause 3.1 — Structural verification
OK
NC
NA
HOLD
C2Substrate cleaning: Method for removing dust, debris, loose paint, corrosion from purlin surface
Acceptance: Cleaning method (wire brush, vacuum, etc.) described; Acceptable surface condition specified
Clause 3.2 — Surface preparation
OK
NC
NA
HOLD
C3Underlayment installation: Membrane type, overlap (150mm), fastening pattern (300mm c/c) specified
Acceptance: Membrane type named; Overlap dimension stated; Fastening method and spacing defined
Clause 3.3 — Moisture barrier
OK
NC
NA
HOLD
Showing 8 of 28 checkpoints ·
A. 1. SCOPE OF WORK
A1Scope statement: What specific roofing activities are covered (e.g., sheet laying, insulation, waterproofing, fastening)
Clause 1.1 — Work scope definition (IS 13592)
Clear description of all activities; Boundaries defined; Exclusions noted if any
OKNCNAHOLD
A2Materials & specifications: Sheet type, gauge, insulation type, fasteners, sealants specified with part numbers
Clause 1.2 — Material specification (IS 13592)
All materials listed with IS code reference; Part numbers/batch specs noted; Approved source documented
OKNCNAHOLD
B. 2. MATERIALS & STORAGE
B1Material storage location: Site location, elevation, weather protection specified
Clause 2.1 — Storage site identification (IS 13592)
Storage area identified on site plan; Elevation above ground specified; Protection method stated
OKNCNAHOLD
B2Storage conditions: Temperature range (5-35°C), humidity (<80% RH), UV protection, ventilation requirements stated
Clause 2.2 — Environmental controls (IS 13592)
Storage method described; Temp/humidity limits stated; Monitoring plan included
OKNCNAHOLD
B3Material testing plan: Outline of tests to be conducted (thermal conductivity, water absorption, pull-out tests)
Clause 2.3 — QC testing plan (IS 13592)
Tests listed with reference to IS codes; Sampling plan included; Lab identified
OKNCNAHOLD
C. 3. SUBSTRATE PREPARATION
C1Roof structure inspection: Visual inspection and confirmation of structural readiness (purlins, level, alignment)
Clause 3.1 — Structural verification (IS 13592)
Inspection method described; Acceptance criteria stated (±5mm/m levelness); Sign-off requirement noted
OKNCNAHOLD
C2Substrate cleaning: Method for removing dust, debris, loose paint, corrosion from purlin surface
Clause 3.2 — Surface preparation (IS 13592)
Cleaning method (wire brush, vacuum, etc.) described; Acceptable surface condition specified
OKNCNAHOLD
C3Underlayment installation: Membrane type, overlap (150mm), fastening pattern (300mm c/c) specified
Clause 3.3 — Moisture barrier (IS 13592)
Membrane type named; Overlap dimension stated; Fastening method and spacing defined
OKNCNAHOLD
Showing 8 of 28 ·
Inspection Sign-Off
APPROVED
APPROVED WITH MODIFICATIONS
REJECTED — RESUBMIT
Remarks / Conditions
Name / Sign / Date
Prepared By
Name / Sign / Date
Approved By (Contractor)
Name / Sign / Date
Accepted By (Client/Consultant)
Name / Sign / Date