QA/QC  › Roofing & Insulation  › Roofing Works ITP
Plan · QC-ROF-PLN-001
Roofing Works ITP
23 checkpoints across 5 sections. Before roofing works commence; ITP shared with all stakeholders; updated if scope changes
23 Checkpoints
5 Sections
Once per project, updated as needed
Contractor, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. HOLD POINTS (Work Stop - Approval Required)
A1HP-1: Roof Structure Inspection Complete - Before underlayment installation
Acceptance: All purlins level (±5mm/m); No defects; Structural inspection signed off; Checklist QC-ROF-CHK-001 baseline reference
Clause 1.1 — Structural readiness
OK
NC
NA
HOLD
A2HP-2: Material Batch Certification Verified - Before sheet laying begins
Acceptance: Test certificates received; Batch traceability confirmed; Grade/gauge verified; Thermal conductivity (for insulation) confirmed
Clause 1.2 — Material qualification
OK
NC
NA
HOLD
A3HP-3: Substrate Preparation Complete - Before insulation/sheet installation
Acceptance: Surface clean, dry, level (±5mm/m); Primer applied (if required); Moisture test passed; Visual inspection approved
Clause 1.3 — Surface readiness
OK
NC
NA
HOLD
A4HP-4: First Sheet / First Slab Laying - Witness point for correct positioning and fastening
Acceptance: Sheet/slab position correct; Overlap measured (confirmed ±mm); Fastening pattern verified; QC inspector present
Clause 1.4 — Initial installation verification
OK
NC
NA
HOLD
A5HP-5: Insulation Slab Installation Batch Approval - After 100 m² of insulation laid, before proceeding
Acceptance: Running bond verified; Joint gaps ≤5mm; Adhesion test (tap test) passed; Surface level (±3mm/m); Inspector approval
Clause 1.5 — Batch acceptance
OK
NC
NA
HOLD
A6HP-6: Water Test Ready - Before final sealant application cures
Acceptance: All sealant applied; Penetration boots installed; Edge trim fastened; 24h cure minimum; Ready for spray test
Clause 1.6 — Leak prevention verification
OK
NC
NA
HOLD
B. INSPECTION POINTS (QC Inspections - Must Pass)
B1IP-1: Roof Sheet Installation Inspection - Per 500 m² of sheets laid (Checklist QC-ROF-CHK-001)
Acceptance: Lap joints correct (150-200mm); Fastening pattern verified (1 per valley); Sealant applied to all joints; No defects observed
Clause 2.1 — Installation quality
OK
NC
NA
HOLD
B2IP-2: Insulation Laying Inspection - Per 500 m² of insulation (Checklist QC-ROF-CHK-002)
Acceptance: Running bond pattern verified; Joint gaps ≤5mm; Adhesion strength adequate (tap test); Surface level ±3mm/m; No voids
Clause 2.2 — Insulation quality
OK
NC
NA
HOLD
B3IP-3: Waterproofing Inspection - All sealed joints and penetrations (Checklist QC-ROF-CHK-003)
Acceptance: Sealant continuous; No gaps or voids; Penetration boots installed; Overlap correct; Pre-water test visual check passed
Clause 2.3 — Sealing quality
OK
NC
NA
HOLD
B4IP-4: Pull-Out Test (Fastener Strength) - Minimum 5 points (Test report QC-ROF-TST-003)
Acceptance: Pull-out load ≥2.0 kN average; No premature slip; Sheet failure mode preferred; Load capacity >design load (SF ≥1.5)
Clause 2.4 — Fastener integrity
OK
NC
NA
HOLD
C. WITNESS POINTS (Contractor to Notify QC; QC Must Be Present)
C1WP-1: Material Unloading & Storage Setup - At start of project
Acceptance: Material quantity confirmed; Storage area verified (elevated, protected); Initial condition checked; Batch numbers recorded
Clause 3.1 — Material receipt
OK
NC
NA
HOLD
C2WP-2: Underlayment Installation - Before sheet laying
Acceptance: Membrane type confirmed; Overlaps 150mm measured; Stapling pattern verified; No tears observed; QC photos taken
Clause 3.2 — Moisture barrier setup
OK
NC
NA
HOLD
C3WP-3: Fastener Type Confirmation - First fastener installation
Acceptance: Fastener type matches spec (stainless/galvanized); Washer type verified (neoprene, 20-25mm); Spacing confirmed (max 300mm c/c)
Clause 3.3 — Fastener verification
OK
NC
NA
HOLD
C4WP-4: Sealant Application Start - First joint sealed
Acceptance: Sealant product confirmed; Surface prep (cleaning, primer) done; Bead width/depth verified (10-20mm × 5-10mm); Appearance acceptable
Clause 3.4 — Sealant qualification
OK
NC
NA
HOLD
C5WP-5: Penetration Boot Installation - First penetration sealed
Acceptance: Boot type matches spec; Overlap 100-150mm confirmed; Fastening pattern verified; Seal complete; Photo documentation
Clause 3.5 — Penetration protection
OK
NC
NA
HOLD
C6WP-6: Water Test Execution - Final functional test
Acceptance: Spray pressure 30 psi, duration 15 min; Interior inspected during and after test; No water entry observed; Gutters drain freely
Clause 3.6 — Leak test
OK
NC
NA
HOLD
Showing 16 of 23 checkpoints ·
A. HOLD POINTS (Work Stop - Approval Required)
A1HP-1: Roof Structure Inspection Complete - Before underlayment installation
Clause 1.1 — Structural readiness (IS 13592)
All purlins level (±5mm/m); No defects; Structural inspection signed off; Checklist QC-ROF-CHK-001 baseline reference
OKNCNAHOLD
A2HP-2: Material Batch Certification Verified - Before sheet laying begins
Clause 1.2 — Material qualification (IS 13592)
Test certificates received; Batch traceability confirmed; Grade/gauge verified; Thermal conductivity (for insulation) confirmed
OKNCNAHOLD
A3HP-3: Substrate Preparation Complete - Before insulation/sheet installation
Clause 1.3 — Surface readiness (IS 8183)
Surface clean, dry, level (±5mm/m); Primer applied (if required); Moisture test passed; Visual inspection approved
OKNCNAHOLD
A4HP-4: First Sheet / First Slab Laying - Witness point for correct positioning and fastening
Clause 1.4 — Initial installation verification (IS 13592)
Sheet/slab position correct; Overlap measured (confirmed ±mm); Fastening pattern verified; QC inspector present
OKNCNAHOLD
A5HP-5: Insulation Slab Installation Batch Approval - After 100 m² of insulation laid, before proceeding
Clause 1.5 — Batch acceptance (IS 8183)
Running bond verified; Joint gaps ≤5mm; Adhesion test (tap test) passed; Surface level (±3mm/m); Inspector approval
OKNCNAHOLD
A6HP-6: Water Test Ready - Before final sealant application cures
Clause 1.6 — Leak prevention verification (IS 13592)
All sealant applied; Penetration boots installed; Edge trim fastened; 24h cure minimum; Ready for spray test
OKNCNAHOLD
B. INSPECTION POINTS (QC Inspections - Must Pass)
B1IP-1: Roof Sheet Installation Inspection - Per 500 m² of sheets laid (Checklist QC-ROF-CHK-001)
Clause 2.1 — Installation quality (IS 13592)
Lap joints correct (150-200mm); Fastening pattern verified (1 per valley); Sealant applied to all joints; No defects observed
OKNCNAHOLD
B2IP-2: Insulation Laying Inspection - Per 500 m² of insulation (Checklist QC-ROF-CHK-002)
Clause 2.2 — Insulation quality (IS 8183)
Running bond pattern verified; Joint gaps ≤5mm; Adhesion strength adequate (tap test); Surface level ±3mm/m; No voids
OKNCNAHOLD
B3IP-3: Waterproofing Inspection - All sealed joints and penetrations (Checklist QC-ROF-CHK-003)
Clause 2.3 — Sealing quality (IS 13592)
Sealant continuous; No gaps or voids; Penetration boots installed; Overlap correct; Pre-water test visual check passed
OKNCNAHOLD
B4IP-4: Pull-Out Test (Fastener Strength) - Minimum 5 points (Test report QC-ROF-TST-003)
Clause 2.4 — Fastener integrity (IS 13592)
Pull-out load ≥2.0 kN average; No premature slip; Sheet failure mode preferred; Load capacity >design load (SF ≥1.5)
OKNCNAHOLD
C. WITNESS POINTS (Contractor to Notify QC; QC Must Be Present)
C1WP-1: Material Unloading & Storage Setup - At start of project
Clause 3.1 — Material receipt (IS 13592)
Material quantity confirmed; Storage area verified (elevated, protected); Initial condition checked; Batch numbers recorded
OKNCNAHOLD
C2WP-2: Underlayment Installation - Before sheet laying
Clause 3.2 — Moisture barrier setup (IS 13592)
Membrane type confirmed; Overlaps 150mm measured; Stapling pattern verified; No tears observed; QC photos taken
OKNCNAHOLD
C3WP-3: Fastener Type Confirmation - First fastener installation
Clause 3.3 — Fastener verification (IS 13592)
Fastener type matches spec (stainless/galvanized); Washer type verified (neoprene, 20-25mm); Spacing confirmed (max 300mm c/c)
OKNCNAHOLD
C4WP-4: Sealant Application Start - First joint sealed
Clause 3.4 — Sealant qualification (IS 13592)
Sealant product confirmed; Surface prep (cleaning, primer) done; Bead width/depth verified (10-20mm × 5-10mm); Appearance acceptable
OKNCNAHOLD
C5WP-5: Penetration Boot Installation - First penetration sealed
Clause 3.5 — Penetration protection (IS 13592)
Boot type matches spec; Overlap 100-150mm confirmed; Fastening pattern verified; Seal complete; Photo documentation
OKNCNAHOLD
C6WP-6: Water Test Execution - Final functional test
Clause 3.6 — Leak test (IS 13592)
Spray pressure 30 psi, duration 15 min; Interior inspected during and after test; No water entry observed; Gutters drain freely
OKNCNAHOLD
Showing 16 of 23 ·
Inspection Sign-Off
ITP APPROVED & READY TO COMMENCE
ITP APPROVED WITH MODIFICATIONS
ITP REJECTED — RESUBMIT
Remarks / Conditions
Name / Sign / Date
Prepared By (Contractor)
Name / Sign / Date
Reviewed By (QC/Consultant)
Name / Sign / Date
Approved By (Client)
Name / Sign / Date