IS 2911 Part 4

: 2013

Design and Construction of Pile Foundations - Testing of Piles

CurrentFrequently UsedTesting MethodGeotechnical · Bridges and Bridge Engineering
Download PDFBIS PortalGoogle

This part of IS 2911 prescribes methodologies for conducting initial and routine load tests on pile foundations. It establishes the procedures for vertical compression, lateral, and pull-out tests, along with the detailed interpretation criteria for deriving safe working loads from load-settlement data.

Specifies methods for testing of piles, including routine load tests, initial load tests, and integrity tests, to verify their load-carrying capacity and structural integrity.

Quick Reference Values
Routine Test Load (Vertical)1.5 times the estimated safe load
Initial Test Load (Vertical)2.5 times the estimated safe load
Minimum rest period (Bored Cast-in-situ)28 days
Safe Load Settlement Criterion (< 600mm dia)Load at 12 mm total settlement
Safe Lateral Load CriterionLoad at 5 mm deflection at pile head
Number of Dial Gauges (Vertical Test)Minimum 3, preferably 4
Key Formulas
Safe Load = Two-thirds of final load at which total displacement attains a value of 12 mm (for piles < 600mm dia)
Safe Load = 50 percent of the final load at which total displacement is 10 percent of pile diameter (for piles >= 600mm dia)
Practical Notes
Ensure the reaction frame or kentledge capacity is at least 1.25 times the maximum anticipated test load for safety.
Always place dial gauges symmetrically around the pile to average out the effect of pile head rotation or tilting.
The pile head must be properly chipped and capped with strong concrete or structural steel plates to ensure purely axial load transfer without eccentricity.