QA/QC  › Soil & Foundation  › Geotechnical ITP
Plan · QC-SOL-PLN-001
Geotechnical ITP
23 checkpoints across 6 sections. Prepared at project start before any earthwork; serves as master control plan for foundation construction; referenced daily during execution; updated if scope changes; closed upon project foundation completion
23 Checkpoints
6 Sections
One ITP per project; activities scheduled per construction phase; maintained and updated throughout foundation and soil work phase
Geotechnical Engineer, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. Geotechnical Investigation Phase
A1Geotechnical investigation report review — Verify report completeness: stratum profile, soil parameters (c, φ, γ, E), bearing capacity, settlement analysis, water table, founding recommendations
Acceptance: Report dated and approved; stratum layers with thickness and description; SPT N-values; lab test results; bearing capacity calculation with factor of safety ≥3.0 for SBC; settlement ≤25 mm; founding depth and type recommended
IS 1892 Clause 7 (Report); IS 1904 Clause 2.2 (Investigation data)
OK
NC
NA
HOLD
B. Excavation Phase
B1Excavation setting out — Verify pile/footing grid layout, RL bench marks, survey markers established
Acceptance: Excavation perimeter marked with paint/chalk; RL bench marks fixed at ≥2 locations and verified by independent survey; offsets recorded from permanent structures; level of precision ±50 mm
IS 1904 Clause 10.1 (Setting out); IS 3764 Clause 5.2 (Preliminary work)
OK
NC
NA
HOLD
B2Excavation depth/level verification — Final excavation level checked against design RL ±25 mm before PCC placement
Acceptance: Survey level taken at ≥4 locations in pit; depth tolerance ±25 mm (e.g., design RL 100.00 m = 99.975 to 100.025 m acceptable); surface firm and level; no soft soil remaining; level report documented
IS 1904 Clause 3.1 (Foundation preparation); IS 3764 Clause 6.2 (Excavation)
OK
NC
NA
HOLD
B3Bearing stratum verification — Geotechnical engineer inspects pit base; stratum type (color, consistency, SPT), bearing capacity adequate
Acceptance: Geotechnical engineer on-site inspection; stratum matches bore log (e.g., 'dense sand, fine to medium, SPT N~35'); bearing capacity per geotechnical report confirmed adequate; rock socketing checked if required; approval certificate issued
IS 1904 Clause 3.2 (Approval of excavation); IS 1892 Clause 6 (Field identification)
OK
NC
NA
HOLD
B4Shoring and slope stability — Daily inspection of temporary support (if any), slopes within IS 3764 Table 1 limits, no signs of failure
Acceptance: Slopes (if any) follow IS 3764 Table 1 angles (1H:1V for clay, 1H:1.5V for sand); props and lagging inspected daily for cracks, bowing >50 mm not acceptable; settlement/inclinometer data reviewed; daily inspection log maintained
IS 3764 Clause 7 (Support systems); IS 3764 Clause 9 (Monitoring)
OK
NC
NA
HOLD
B5Dewatering adequacy — Water level maintained ≥500 mm below working level; sump pump functioning, no flooding
Acceptance: Daily water level measurement from standpipes; level ≥500 mm below excavation base (e.g., base at RL 100 m, water ≤100.5 m); pump capacity adequate for inflow; sump pit clean; discharge location noted
IS 3764 Clause 8 (Dewatering management); IS 1904 Clause 4 (Groundwater)
OK
NC
NA
HOLD
B6PCC blinding placement — Grade M10, thickness ≥75 mm, level surface, test cubes taken
Acceptance: PCC M10 (or per design); thickness ≥75 mm verified at ≥4 locations; surface level ±20 mm; cubes cast (1 set per 50 m²); curing for 7 days before loading; strength test results ≥10 MPa at 7 days
IS 456 Clause 11 (Foundation concrete); IS 1904 Clause 3.2 (Blinding)
OK
NC
NA
HOLD
C. Backfill and Compaction
C1Backfill material approval — Grading per IS 2720 Part 4, free from organics, clay fines <15% (for granular backfill)
Acceptance: Material grading checked (sieve analysis per IS 2720 Part 2); no organic matter, roots, or debris; clay fines <15% for sand/gravel backfill; approved source documented; material sample retained
IS 2720 Part 4 (Grain size analysis); IS 1904 Clause 5 (Backfill)
OK
NC
NA
HOLD
C2Compaction testing — Field density test per IS 2720 Part 28 (sand replacement) or Part 29 (core cutter); ≥95% Modified DD (MDD)
Acceptance: Field density test (sand replacement or core cutter) per layer (300 mm lift typical); density ≥95% MDD; moisture content within ±2% of optimum (from lab proctor test); test results documented per location
IS 2720 Part 28/29 (Compaction testing); IS 1904 Clause 5.2 (Compaction control)
OK
NC
NA
HOLD
Showing 9 of 23 checkpoints ·
A. Geotechnical Investigation Phase
A1Geotechnical investigation report review — Verify report completeness: stratum profile, soil parameters (c, φ, γ, E), bearing capacity, settlement analysis, water table, founding recommendations
IS 1892 Clause 7 (Report); IS 1904 Clause 2.2 (Investigation data) (IS 1892:2014 & IS 1904:1986)
Report dated and approved; stratum layers with thickness and description; SPT N-values; lab test results; bearing capacity calculation with factor of safety ≥3.0 for SBC; settlement ≤25 mm; founding depth and type recommended
OKNCNAHOLD
B. Excavation Phase
B1Excavation setting out — Verify pile/footing grid layout, RL bench marks, survey markers established
IS 1904 Clause 10.1 (Setting out); IS 3764 Clause 5.2 (Preliminary work) (IS 1904:1986 & IS 3764:1992)
Excavation perimeter marked with paint/chalk; RL bench marks fixed at ≥2 locations and verified by independent survey; offsets recorded from permanent structures; level of precision ±50 mm
OKNCNAHOLD
B2Excavation depth/level verification — Final excavation level checked against design RL ±25 mm before PCC placement
IS 1904 Clause 3.1 (Foundation preparation); IS 3764 Clause 6.2 (Excavation) (IS 1904:1986 & IS 3764:1992)
Survey level taken at ≥4 locations in pit; depth tolerance ±25 mm (e.g., design RL 100.00 m = 99.975 to 100.025 m acceptable); surface firm and level; no soft soil remaining; level report documented
OKNCNAHOLD
B3Bearing stratum verification — Geotechnical engineer inspects pit base; stratum type (color, consistency, SPT), bearing capacity adequate
IS 1904 Clause 3.2 (Approval of excavation); IS 1892 Clause 6 (Field identification) (IS 1904:1986 & IS 1892:2014)
Geotechnical engineer on-site inspection; stratum matches bore log (e.g., 'dense sand, fine to medium, SPT N~35'); bearing capacity per geotechnical report confirmed adequate; rock socketing checked if required; approval certificate issued
OKNCNAHOLD
B4Shoring and slope stability — Daily inspection of temporary support (if any), slopes within IS 3764 Table 1 limits, no signs of failure
IS 3764 Clause 7 (Support systems); IS 3764 Clause 9 (Monitoring) (IS 3764:1992)
Slopes (if any) follow IS 3764 Table 1 angles (1H:1V for clay, 1H:1.5V for sand); props and lagging inspected daily for cracks, bowing >50 mm not acceptable; settlement/inclinometer data reviewed; daily inspection log maintained
OKNCNAHOLD
B5Dewatering adequacy — Water level maintained ≥500 mm below working level; sump pump functioning, no flooding
IS 3764 Clause 8 (Dewatering management); IS 1904 Clause 4 (Groundwater) (IS 3764:1992 & IS 1904:1986)
Daily water level measurement from standpipes; level ≥500 mm below excavation base (e.g., base at RL 100 m, water ≤100.5 m); pump capacity adequate for inflow; sump pit clean; discharge location noted
OKNCNAHOLD
B6PCC blinding placement — Grade M10, thickness ≥75 mm, level surface, test cubes taken
IS 456 Clause 11 (Foundation concrete); IS 1904 Clause 3.2 (Blinding) (IS 456:2000 & IS 1904:1986)
PCC M10 (or per design); thickness ≥75 mm verified at ≥4 locations; surface level ±20 mm; cubes cast (1 set per 50 m²); curing for 7 days before loading; strength test results ≥10 MPa at 7 days
OKNCNAHOLD
C. Backfill and Compaction
C1Backfill material approval — Grading per IS 2720 Part 4, free from organics, clay fines <15% (for granular backfill)
IS 2720 Part 4 (Grain size analysis); IS 1904 Clause 5 (Backfill) (IS 2720:2011 & IS 1904:1986)
Material grading checked (sieve analysis per IS 2720 Part 2); no organic matter, roots, or debris; clay fines <15% for sand/gravel backfill; approved source documented; material sample retained
OKNCNAHOLD
C2Compaction testing — Field density test per IS 2720 Part 28 (sand replacement) or Part 29 (core cutter); ≥95% Modified DD (MDD)
IS 2720 Part 28/29 (Compaction testing); IS 1904 Clause 5.2 (Compaction control) (IS 2720:2011 & IS 1904:1986)
Field density test (sand replacement or core cutter) per layer (300 mm lift typical); density ≥95% MDD; moisture content within ±2% of optimum (from lab proctor test); test results documented per location
OKNCNAHOLD
Showing 9 of 23 ·
Inspection Sign-Off
All ITP activities completed and accepted
All H-point activities completed; project ready for next phase
Outstanding items (noted below) — work may proceed with conditions
Non-conformances resolved by engineering — project approved to continue
Geotechnical Engineer Name
Name / Sign / Date
Geotechnical Engineer Signature
Name / Sign / Date
QC Engineer Name
Name / Sign / Date
QC Engineer Signature
Name / Sign / Date
Project Manager Name
Name / Sign / Date
Project Manager Signature
Name / Sign / Date