CONCRETE

Tremie Concrete (Underwater)

Concrete placement under water using a tremie pipe

Also calledtremietremie concreteunderwater concretepile concretetremie pipe
Related on InfraLens
Definition

Tremie concrete is concrete placed underwater or in deep, narrow excavations using a vertical pipe (tremie pipe) to deliver concrete from above the water surface. The pipe ensures continuous concrete flow without segregation, water displacement of cement, or aggregate settlement. Per IS 456:2000 Cl. 13.7, IS 2911 (piles), IS 9556 (diaphragm walls), and IRC 78 (bridges), tremie placement is essential for: (1) Cast-in-situ piles (bored cast-in-situ); (2) Diaphragm walls; (3) Underwater concreting; (4) Deep narrow excavations; (5) Slurry-stabilised foundations.

Key tremie procedure: (1) Mix design — typically high cement content (380-450 kg/m³ for M30), high slump (150-200 mm), use of PCE superplasticisers; aggregate maximum 12-16 mm to prevent segregation in narrow pipes. (2) Tremie pipe — typically 150-300 mm diameter, made of mild steel; diameter at least 6× maximum aggregate size. (3) Pipe insertion — to bottom of excavation; ensures concrete is deposited below the water/slurry. (4) Concrete pumping — continuous from bottom up, displacing water/slurry from above. (5) Pipe extraction — gradual, maintaining concrete level above pipe outlet to prevent washing in.

The most-overlooked aspect of Indian tremie concrete: pipe management during pumping. The pipe must remain submerged in concrete (typically 1.5-3.0 m below the surface) to prevent slurry/water entering. If pipe is lifted too high, slurry is included in concrete causing voids and weak zones. Pipe management requires skilled operator + on-line concrete level monitoring. Pile load tests (PLT) and Pile Integrity Tests (PIT) detect tremie-related defects.

Where used
  • Bored cast-in-situ pile concreting
  • Diaphragm wall construction
  • Underwater concreting (bridge piers, marine)
  • Deep narrow excavation concreting
  • Slurry-stabilised foundation construction
Acceptance / threshold
Per IS 456 Cl. 13.7 + IS 2911 + IS 9556: high cement content (≥ 380 kg/m³), high slump (150-200 mm), maximum aggregate 12-16 mm; tremie pipe management with continuous submersion (1.5-3.0 m); Pile Integrity Test (PIT) for defects.
Frequently asked
What is tremie concrete?
Tremie concrete is concrete placed underwater or in deep, narrow excavations using a vertical pipe (tremie pipe) to deliver concrete from above the water surface. Used for cast-in-situ piles, diaphragm walls, underwater concreting, deep excavations. Per IS 456 Cl. 13.7 + IS 2911 + IS 9556.
How does tremie concrete placement work?
(1) Mix design — high cement (380-450 kg/m³), high slump (150-200 mm), small aggregate (12-16 mm). (2) Tremie pipe (150-300 mm dia) inserted to bottom of excavation. (3) Concrete pumped continuously from bottom up. (4) Slurry/water displaced from above. (5) Pipe extracted gradually, maintaining concrete level. (6) Pipe must remain submerged 1.5-3.0 m in concrete to prevent slurry inclusion.
What can go wrong in tremie concrete?
Common defects: (1) Slurry/water inclusion if pipe lifted too high during pumping. (2) Necking (local concrete reduction) from soil collapse. (3) Voids from interrupted pumping. (4) Mix segregation in narrow pipes. Detection: Pile Integrity Test (PIT) — sonic/mechanical impulse on pile head; reflected wave detected for defects. PIT should be 100% on important structures; 50%+ on others.
Related concrete terms