Formats  › Statutory & NOCs  › Building Permit Application
Checklist · FMT-STA-001
Building Permit Application (BPA) Checklist
11 fields across 3 sections. Pre-construction approval — building cannot start without BPA / IOD.
11 Fields
3 Sections
Per project
Architect, Owner

Format Preview

S.No.Field / CheckpointReferenceStatus
A. DOCUMENTS
A1Plot ownership documents — sale deed + 7/12 + mutation
Acceptance: Encumbrance-free
Per state revenue records
OK
NC
NA
A2Architectural drawings — site plan + floor plans + elevations + sections
Acceptance: Stamped + signed
By licensed architect (CoA)
OK
NC
NA
A3Structural design + drawings (RCC consultant)
Acceptance: Stamped + signed
Per IS 456 + IS 13920
OK
NC
NA
A4MEP drawings — electrical, plumbing, HVAC, fire
Acceptance: Stamped + signed
Per applicable codes
OK
NC
NA
A5Soil investigation + foundation design report
Acceptance: Geotech report
Per IS 1892 / IS 2911
OK
NC
NA
B. COMPLIANCE
B1FAR / FSI + ground coverage + setbacks per DCR
Acceptance: Within limits
Per local DCR
OK
NC
NA
B2Parking + green area + rainwater harvesting per DCR
Acceptance: Per requirements
Per DCR
OK
NC
NA
B3Fire safety — staircase, lift, fire NOC plan
Acceptance: Per code
Per NBC 2016 Part 4 + state fire rules
OK
NC
NA
B4Environmental clearance (EC) — if > 20,000 m² built-up area
Acceptance: EC if applicable
Per EIA Notification 2006
OK
NC
NA
C. FEES + SUBMISSION
C1Development charges + scrutiny fee + labour cess (BOCW 1%)
Acceptance: Paid
Per state schedule
OK
NC
NA
C2Online / offline submission to municipal authority
Acceptance: Submitted
Per state portal
OK
NC
NA
A. DOCUMENTS
A1Plot ownership documents — sale deed + 7/12 + mutation
Per state revenue records
Encumbrance-free
OKNCNA
A2Architectural drawings — site plan + floor plans + elevations + sections
By licensed architect (CoA)
Stamped + signed
OKNCNA
A3Structural design + drawings (RCC consultant)
Per IS 456 + IS 13920
Stamped + signed
OKNCNA
A4MEP drawings — electrical, plumbing, HVAC, fire
Per applicable codes
Stamped + signed
OKNCNA
A5Soil investigation + foundation design report
Per IS 1892 / IS 2911
Geotech report
OKNCNA
B. COMPLIANCE
B1FAR / FSI + ground coverage + setbacks per DCR
Per local DCR
Within limits
OKNCNA
B2Parking + green area + rainwater harvesting per DCR
Per DCR
Per requirements
OKNCNA
B3Fire safety — staircase, lift, fire NOC plan
Per NBC 2016 Part 4 + state fire rules
Per code
OKNCNA
B4Environmental clearance (EC) — if > 20,000 m² built-up area
Per EIA Notification 2006
EC if applicable
OKNCNA
C. FEES + SUBMISSION
C1Development charges + scrutiny fee + labour cess (BOCW 1%)
Per state schedule
Paid
OKNCNA
C2Online / offline submission to municipal authority
Per state portal
Submitted
OKNCNA
Approval / Sign-Off
APPROVED
HOLD — REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By — Name / Sign
Name / Sign / Date
Reviewed By — Name / Sign
Name / Sign / Date
Approved By — Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date