PMC📊 Reports — Daily / Weekly / MonthlyMonthly Cost Report

Monthly Cost Report

report
PMC-RPT-RPT-006·v1.0-beta·⚠ Beta — review before use

This report tracks all project costs for the month against the approved budget (BOQ). It helps the project manager and client understand if the project is overspending or underspending and provides reasons for any variance.

ReferencesFIDIC Sub-clause 4.21 (Progress Reports)FIDIC Sub-clause 14 (Contract Price and Payment)CPWD Works Manual (Chapter on Project Accounts & Financial Control)IS 7861 (Part 1): Code of practice for extreme weather concreting
Download
📍 When to use this template
  • To summarize all project expenditures (direct and indirect) and compare them with the sanctioned budget.
  • Prepared monthly, usually submitted within the first 7-10 days of the following month.
  • Typically prepared by the Quantity Surveyor (QS) or Project Controls Engineer, and reviewed by the Project Manager before submission to the client.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract / Package No.
_____________
Report No.
_____________
For the Month of (e.g., May 2024)
_____________
Date of Submission
_____________
Prepared By (Name & Designation)
_____________
Approved By (Name & Designation)
_____________
2Executive Summary9 fields
Overall Cost Status (Over/Under Budget)
_____________
Original Contract Value (CA Value)
_____________
Anticipated Final Cost (AFC)
_____________
Cost Incurred This Month
_____________
Cumulative Cost Incurred to Date
_____________
Financial Progress (%)
_____________
Cost Performance Index (CPI)
_____________
Key Reasons for Variance
_____________
Proposed Corrective Actions
_____________
3Cost Breakdown (BOQ Items)9 fields
BOQ Item No.
_____________
Description of Work
_____________
Budgeted Cost (As per BOQ)
_____________
Cost Booked This Month
_____________
Cumulative Cost Booked
_____________
Balance Cost
_____________
Variance (₹)
_____________
Variance (%)
_____________
Remarks / Justification
_____________
4Indirect / Non-BOQ Costs6 fields
Cost Head (e.g., PMC Staff, Site Office Rent, Utilities, Statutory Fees, T&P)
_____________
Monthly Budget
_____________
Actual Expense This Month
_____________
Cumulative Expense
_____________
Variance
_____________
Remarks
_____________
5Cash Flow Status6 fields
Opening Balance
_____________
Inflow (RA Bills Certified, Advances Received)
_____________
Outflow (Contractor Payments, Material Purchases, Labour Wages, Overheads)
_____________
Closing Balance
_____________
Projected Cash Flow for Next Month
_____________
Pending Payments to Contractors/Vendors
_____________
6Variation & Extra Item Status6 fields
Variation Order (VO) / Deviation Item No.
_____________
Description
_____________
Status (Approved / Pending / Rejected)
_____________
Approved Cost Impact (₹)
_____________
Cost Incurred Against VO to Date
_____________
Potential Cost Impact of Pending Items
_____________
7Material Reconciliation Cost Impact6 fields
Material (Cement, Steel)
_____________
Theoretical Consumption (as per IS codes/drawings)
_____________
Actual Consumption (from Store Records)
_____________
Wastage / Variance (%)
_____________
Permissible Wastage (%)
_____________
Cost Impact of Excess Wastage (₹)
_____________
💡 Sample filled excerpt
Section: Cost Breakdown (BOQ Items)
BOQ Item No.: 4.2.1
Description: Reinforcement Steel Fe-500D
Budgeted Cost: ₹85,00,000
Cost Booked This Month: ₹12,50,000
Cumulative Cost Booked: ₹60,00,000
Variance (%): +4.5% (Overrun due to market price hike)
⚖ Compliance notes
  • Provides essential data for Earned Value Management (EVM) analysis as per project management best practices and the CPWD Works Manual.
  • Supports the 'Progress Reports' requirement under FIDIC Sub-clause 4.21, which mandates reporting on project costs.
  • Forms a critical part of the documentation required for substantiating cost overrun claims and Extension of Time (EOT) applications.
  • Crucial for internal and external financial audits to verify project financial health and adherence to the sanctioned budget.