Earned Value Management (EVM) Sheet

chart
PMC-RPT-CHT-002·v1.0-beta·⚠ Beta — review before use

This EVM sheet helps you track your project's health by comparing the planned work against the actual work done and the money spent. It gives you key performance indicators (KPIs) like CPI and SPI to see if you are on schedule and within budget.

ReferencesIS 15883 (Part 1):2009 - Guidelines for Application of Project ManagementFIDIC Conditions of Contract, Sub-clause 4.21 (Progress Reports)FIDIC Conditions of Contract, Sub-clause 8.4 (Extension of Time for Completion)CPWD Works Manual (Chapter on Project Monitoring and Control)
Download
📍 When to use this template
  • Typically updated weekly or monthly as part of the MPR (Monthly Progress Report).
  • Triggered when the client or senior management requires a detailed performance analysis beyond simple S-curves.
  • Prepared by the Planning Engineer or Project Controls team and reviewed by the Project Manager.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information8 fields
Project Name
_____________
Contract / Package No.
_____________
Document Number
_____________
Report Period (From/To)
_____________
Date of Report
_____________
Prepared By (Planning Engineer)
_____________
Reviewed By (Project Manager)
_____________
Approved By (PMC Head / Client Rep.)
_____________
2Input Data Summary6 fields
Budget at Completion (BAC) in ₹
_____________
Planned Value (PV) - Cumulative to Date
_____________
Earned Value (EV) - Cumulative to Date
_____________
Actual Cost (AC) - Cumulative to Date
_____________
Data Source (e.g., SAP / ERP / RA Bill No.)
_____________
Measurement Cut-off Date
_____________
3Core EVM Performance Metrics6 fields
Schedule Variance (SV = EV - PV)
_____________
Cost Variance (CV = EV - AC)
_____________
Schedule Performance Index (SPI = EV / PV)
_____________
Cost Performance Index (CPI = EV / AC)
_____________
Variance at Completion (VAC = BAC - EAC)
_____________
To-Complete Performance Index (TCPI)
_____________
4Forecasts & Projections6 fields
Estimate at Completion (EAC) - Formula Used (e.g., BAC/CPI)
_____________
Calculated EAC Value
_____________
Estimate to Complete (ETC = EAC - AC)
_____________
Projected Completion Date (Based on SPI)
_____________
Projected Cost Overrun / Underrun
_____________
Management Reserve Status
_____________
5Performance Analysis & Remarks6 fields
Overall Project Status (e.g., On-track, Behind Schedule, Over Budget)
_____________
Root Cause for Variances (e.g., Labour shortage, Material delay, Design change)
_____________
Corrective Actions Proposed
_____________
Impact on Critical Path Activities
_____________
Opportunities for Cost Savings / Schedule Recovery
_____________
Next Period's Target PV & EV
_____________
6Graphical Representation4 fields
S-Curve Chart (PV vs EV vs AC)
_____________
CPI & SPI Trend Chart
_____________
Cash Flow Projection (Actual vs. Planned vs. Forecasted)
_____________
Link to Detailed Primavera / MSP Schedule
_____________
💡 Sample filled excerpt
**Schedule Variance (SV)**: ₹ -25,00,000 (Work worth 2.25 Cr done against a plan of 2.50 Cr) | **Cost Variance (CV)**: ₹ +10,00,000 (Work worth 2.25 Cr done for an actual cost of 2.15 Cr) | **SPI**: 0.90 (Behind Schedule) | **CPI**: 1.04 (Under Budget)
⚖ Compliance notes
  • Helps fulfil reporting requirements under FIDIC Sub-clause 4.21 [Progress Reports] by providing detailed performance metrics.
  • Provides objective data for justifying Extension of Time (EOT) claims (FIDIC 8.4) or cost variation orders by quantifying schedule and cost impacts.
  • Used in high-level Project Review Meetings (PRM) with clients and management to demonstrate project control and forecasting.
  • Supports internal and external audits by providing a transparent view of project performance against the approved baseline.