📍 When to use this template
- Typically prepared weekly or monthly to monitor equipment performance and cost.
- Triggered when project costs are high, to identify potential savings in equipment rental or ownership.
- Filled by the Site Engineer or Plant & Machinery (P&M) In-charge, reviewed by the Project Manager.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract / Package No.
_____________
Report Period (From Date / To Date)
_____________
Date of Submission
_____________
Prepared By (Name & Designation)
_____________
Approved By (Name & Designation)
_____________
2Equipment Fleet Summary6 fields
Total Equipment on Site (Nos.)
_____________
Total Equipment Deployed (Nos.)
_____________
Total Equipment Idle (Nos.)
_____________
Overall Fleet Utilization Percentage (%)
_____________
Total Breakdown Hours (All Equipment)
_____________
Total Fuel Consumed (Litres)
_____________
3Detailed Utilization Log (Per Equipment)11 fields
Equipment Type (e.g., Excavator, Crane, Dumper)
_____________
Equipment ID / Registration No.
_____________
Capacity (e.g., 20T, 500 TPH)
_____________
Ownership (Own / Hired)
_____________
Working Hours
_____________
Breakdown Hours
_____________
Total Shift Hours
_____________
Utilization % (Working / Total Shift)
_____________
Remarks (e.g., 'Awaiting front', 'Operator absent', 'Under PM')
_____________
4Fuel Consumption Log10 fields
Equipment ID / Registration No.
_____________
Opening Reading (HMR/KMR)
_____________
Closing Reading (HMR/KMR)
_____________
Total Hours/Kms Run
_____________
Fuel Issued (Litres)
_____________
Standard Consumption (Ltr/Hr)
_____________
Actual Consumption (Ltr/Hr)
_____________
Variance (+/- %)
_____________
Reason for Variance
_____________
5Maintenance & Breakdown Analysis7 fields
Equipment ID / Registration No.
_____________
Date & Time of Breakdown
_____________
Nature of Fault / Problem Description
_____________
Action Taken / Spares Used
_____________
Time Taken for Rectification (Hrs)
_____________
Preventive Maintenance Due Date
_____________
Status (Rectified / Awaiting Spares / Under Observation)
_____________
6Mobilization / Demobilization Status6 fields
Equipment Type & ID
_____________
Status (Mobilized / Demobilized)
_____________
Reason (e.g., 'Scope completed', 'New front opened')
_____________
From / To Location
_____________
💡 Sample filled excerpt
Equipment: JCB 3DX, ID: MH-04-AB-1234, Ownership: Hired, Working Hrs: 8.5, Idle Hrs: 1.5, Breakdown Hrs: 0, Utilization: 85%, Remarks: Working on trench excavation at Grid A-C.
⚖ Compliance notes
- Provides data for Monthly Progress Reports (MPR) as required by FIDIC Sub-clause 4.21 [Progress Reports].
- Helps justify claims for idle machinery charges under specific contract conditions (e.g., delay caused by Employer).
- Supports cost control and internal/external audit processes by tracking a major project expenditure.
- Ensures compliance with BOCW Rules, 1998, Rule 55 regarding the safe condition and maintenance of lifting appliances and machinery.