S-Curve (Planned vs Actual)

chart
PMC-RPT-CHT-001·v1.0-beta·⚠ Beta — review before use

This template tracks the cumulative progress of your project over time, comparing the planned schedule (baseline) with the actual work completed. It helps you visually see if the project is ahead of schedule, behind schedule, or on track.

ReferencesFIDIC Red Book (1999/2017) Sub-clause 4.21 [Progress Reports]FIDIC Red Book (1999/2017) Sub-clause 8.4 [Extension of Time for Completion]IS 15883 (Part 1): 2009 - Construction Project Management GuidelinesCPWD Works Manual, Chapter 20 [Reports and Returns]
Download
📍 When to use this template
  • To visualize project progress for Monthly Progress Reports (MPR) or client/management review meetings.
  • Updated weekly or fortnightly, and always included in the MPR.
  • Prepared by the Planning Engineer or Project Controls team, based on site progress data.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract / Package No.
_____________
Document Number
_____________
Report Period (e.g., Upto DD-MM-YYYY)
_____________
Prepared By (Planning Engineer)
_____________
Reviewed By (Project Manager)
_____________
Approved By (Project Director/Client Rep)
_____________
2Baseline Plan Data (Planned S-Curve)5 fields
Baseline Schedule ID / Version (e.g., Primavera P6 Rev.0)
_____________
Total Project Duration (Days)
_____________
Total Project Value (INR)
_____________
Planned Start Date
_____________
Planned Finish Date
_____________
3Tabular Data for Chart7 fields
Period (e.g., Week 1, Week 2... or Jan-24, Feb-24...)
_____________
Planned % Progress (for period)
_____________
Planned Cumulative % Progress
_____________
Actual % Progress (for period)
_____________
Actual Cumulative % Progress
_____________
Schedule Variance (SV) % (Actual Cum. % - Planned Cum. %)
_____________
Data Source (e.g., MPR-05, WPR-22)
_____________
4Key Performance Indicators (KPIs) & Analysis6 fields
Schedule Performance Index (SPI) = EV/PV
_____________
Schedule Variance (SV) = EV - PV
_____________
Current Slippage / Gain (Days)
_____________
Forecasted Completion Date (Based on current SPI)
_____________
Major Reasons for Slippage (if any)
_____________
Proposed Corrective Actions / Mitigation Plan
_____________
5Chart Area5 fields
Graphical representation of Planned vs. Actual cumulative progress % against time.
_____________
X-Axis: Time (Days/Weeks/Months)
_____________
Y-Axis: Cumulative Progress (%)
_____________
Plot Line 1: Planned Progress (Baseline)
_____________
Plot Line 2: Actual Progress
_____________
💡 Sample filled excerpt
Period: Week 12 (ending 24-Mar-2024) | Planned Cum. %: 25.50% | Actual Cum. %: 22.75% | Schedule Variance (SV) %: -2.75% | Remarks: Delay due to unexpected hard rock encountered during excavation and delay in reinforcement steel supply.
⚖ Compliance notes
  • Fulfills reporting requirements under FIDIC Sub-clause 4.21 [Progress Reports], which mandates comparison of actual progress with the planned programme.
  • Serves as key evidence for Extension of Time (EOT) claims by demonstrating delays and their cumulative impact over the project lifecycle.
  • Required as a standard component of Monthly Progress Reports (MPR) as per CPWD Works Manual and most private sector PMC contracts.
  • Used by auditors and Lenders' Independent Engineers (LIE) to quickly assess project health and disbursement eligibility.