This template tracks the cumulative progress of your project over time, comparing the planned schedule (baseline) with the actual work completed. It helps you visually see if the project is ahead of schedule, behind schedule, or on track.
Period: Week 12 (ending 24-Mar-2024) | Planned Cum. %: 25.50% | Actual Cum. %: 22.75% | Schedule Variance (SV) %: -2.75% | Remarks: Delay due to unexpected hard rock encountered during excavation and delay in reinforcement steel supply.