PMC📊 Reports — Daily / Weekly / MonthlyDaily Site Report (DSR)

Daily Site Report (DSR)

report
PMC-RPT-RPT-001·v1.0-beta·⚠ Beta — review before use

This is your daily diary for the site, a 'roznamcha' of all activities. It records what work was done, how many labourers and machines were used, what materials came in, and any problems or instructions for the day.

ReferencesFIDIC Red Book (1999/2017) Sub-clause 4.21CPWD Works Manual, Chapter 18: Site Records and ReturnsBOCW Act, 1996 and Central Rules, 1998IS 1200 (All Parts): Method of measurement of building and civil engineering works
Download
📍 When to use this template
  • To create a daily, chronological record of all significant site events, progress, and resource deployment.
  • Filled at the end of every working day by the contractor's site engineer and verified by the PMC/Client engineer.
  • It is the primary source document for weekly/monthly reports and for substantiating claims or delays.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header & General Information8 fields
Project Name
_____________
Contract / Package No.
_____________
DSR No.
_____________
Date
_____________
Weather (Morning / Afternoon)
_____________
Temperature (°C Min / Max)
_____________
Prepared By (Contractor)
_____________
Verified By (PMC)
_____________
2Labour Deployment7 fields
Agency / Sub-contractor Name
_____________
Trade (e.g., Mason, Carpenter, Fitter, Helper)
_____________
Skilled Count
_____________
Semi-skilled Count
_____________
Unskilled Count
_____________
Total Mandays
_____________
Remarks (e.g., OT hours)
_____________
3Plant & Machinery (P&M) Deployment7 fields
P&M Description (e.g., JCB, Concrete Pump, Tower Crane)
_____________
Capacity / Size
_____________
Quantity
_____________
Working Hours
_____________
Idle Hours
_____________
Breakdown Hours
_____________
Remarks
_____________
4Work Progress Achieved7 fields
Location / Grid / Floor / Chainage
_____________
Activity Description (as per BOQ / Schedule)
_____________
Unit of Measurement (UoM)
_____________
Planned Qty (Day)
_____________
Achieved Qty (Day)
_____________
Cumulative Qty
_____________
Remarks / RFI Reference
_____________
5Material Received at Site8 fields
Material Description
_____________
Unit
_____________
Supplier Name
_____________
Challan / Invoice No.
_____________
Received Quantity
_____________
Accepted Quantity
_____________
Rejected Quantity
_____________
Remarks / Storage Location / MIR Ref.
_____________
6Safety, Health & Environment (HSE)6 fields
Toolbox Talk (TBT) Topic & Attendance
_____________
Safety Observations (Unsafe Act / Condition)
_____________
Near Miss / Incident / Accident Reported (Y/N, with ref)
_____________
Housekeeping Status (Good/Fair/Poor)
_____________
PPE Compliance Check
_____________
Permits Issued (Hot Work, Confined Space, etc.)
_____________
7Hindrances / Delays / Constraints6 fields
Hindrance Description (e.g., Drawing not available, Material shortage, Access issue)
_____________
Start Time
_____________
End Time / Ongoing
_____________
Responsibility (Client / Consultant / Contractor)
_____________
Action Taken / Proposed
_____________
Reference to Correspondence / Hindrance Register
_____________
8Instructions & Visitors4 fields
Instructions Received (From Client/PMC)
_____________
Instructions Given (To Sub-contractor)
_____________
Official Visitors (Name, Organisation, Purpose)
_____________
Remarks
_____________
💡 Sample filled excerpt
Section: Work Progress Achieved
Location: Tower B, 5th Floor Slab | Activity: Concreting of slab panel S-2 (M30) | UoM: Cum | Planned Qty: 45 | Achieved Qty: 45 | Remarks: Pour completed. Cube samples taken. RFI/CONC/112 cleared.
⚖ Compliance notes
  • Fulfills the requirement for daily records under FIDIC Sub-Clause 4.21 [Progress Reports] and Sub-Clause 8.4 [Extension of Time for Completion].
  • Acts as primary supporting documentation for Measurement Books (MB) and Running Account (RA) Bills.
  • Helps maintain records of workers on site as required under the BOCW Act, 1996, supplementing the official Muster Roll (Form XVI).
  • Provides contemporaneous evidence for claims, variations, and dispute resolution proceedings.