PMC📊 Reports — Daily / Weekly / MonthlyLabour Histogram

Labour Histogram

chart
PMC-RPT-CHT-003·v1.0-beta·⚠ Beta — review before use

This template is used to track and visually represent the number of workers on site, categorized by their trade (e.g., mason, carpenter, helper). It helps in comparing planned vs. actual manpower deployment, justifying resource needs, and ensuring labour compliance.

ReferencesBOCW Act, 1996Contract Labour (R&A) Act, 1970FIDIC Red Book (2017) Sub-clause 4.21CPWD Works Manual (Chapter on Site Records)
Download
📍 When to use this template
  • Prepared weekly or monthly as a key component of the Monthly Progress Report (MPR).
  • Triggered when analyzing resource allocation, productivity, or delays due to manpower shortage.
  • Typically compiled by the Planning Engineer or Site Engineer and submitted to the Project Manager and Client/PMC.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract Package No.
_____________
Document No.
_____________
Report for the Month/Week of
_____________
Date of Preparation
_____________
Prepared By (Name & Designation)
_____________
Approved By (Name & Designation)
_____________
2Overall Manpower Summary7 fields
Reporting Period (e.g., Week 24, June 2024)
_____________
Total Mandays Planned for Period
_____________
Total Mandays Actual for Period
_____________
Variance (Actual - Planned)
_____________
Peak Manpower Planned
_____________
Peak Manpower Achieved
_____________
Average Manpower Deployed
_____________
3Trade-wise Daily/Weekly Labour Count9 fields
Trade Category (e.g., Civil, MEP, Finishes)
_____________
Trade (e.g., Mason, Carpenter, Plumber, Electrician)
_____________
Unit (Nos.)
_____________
Day 1 / Week 1 Count
_____________
Day 2 / Week 2 Count
_____________
...
_____________
Day 31 / Week 4 Count
_____________
Total Mandays for Trade
_____________
Average Count for Trade
_____________
4Contractor / Agency Wise Deployment6 fields
Contractor / Sub-contractor Name
_____________
Trades Supplied
_____________
Total Mandays Supplied this Period
_____________
Cumulative Mandays Supplied
_____________
Statutory Compliance Status (PF/ESIC/Wages)
_____________
Remarks on Performance/Shortfall
_____________
5Histogram Chart & Analysis6 fields
Chart Title (e.g., Labour Histogram - June 2024)
_____________
X-Axis (Time - Days/Weeks)
_____________
Y-Axis (Number of Labour)
_____________
Planned Manpower Curve (Data Series)
_____________
Actual Manpower Curve (Data Series)
_____________
Key Observations / Reasons for Variance
_____________
💡 Sample filled excerpt
Trade: Mason | Day 1: 25 | Day 2: 28 | Day 3: 30 | Total Mandays: 83 | Avg: 27.6
Trade: Helper | Day 1: 40 | Day 2: 42 | Day 3: 45 | Total Mandays: 127 | Avg: 42.3
Analysis: Manpower ramped up from Day 2 for raft foundation concrete pour. Actual deployment is 5% above plan due to accelerated schedule.
⚖ Compliance notes
  • Provides essential data for Form XIII (Register of Workmen) as per the Contract Labour (Regulation and Abolition) Act, 1970.
  • Helps demonstrate compliance with the Building and Other Construction Workers (BOCW) Act, 1996, regarding maintenance of worker records.
  • Supports progress reporting requirements under FIDIC Sub-clause 4.21 [Progress Reports] which mandates details of Contractor's Personnel.
  • Crucial evidence during audits by Labour Department, PF/ESIC inspectors, or client's internal audit team.