📍 When to use this template
- Compiled every week, usually on a Friday or Saturday, for the weekly progress meeting.
- Crucial during the finishing stages of a building or area, leading up to joint inspection and handover.
- Prepared by the PMC/Client's site engineers and reviewed jointly with the Contractor's team to agree on status.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Week Ending Date
_____________
Prepared By (PMC Name/Signature)
_____________
Reviewed By (Contractor Name/Signature)
_____________
2Weekly Snag Summary5 fields
Snags Brought Forward (from last week)
_____________
New Snags Identified (this week)
_____________
Snags Rectified / Closed (this week)
_____________
Total Snags Outstanding (at week end)
_____________
Percentage Closure Rate (for the week)
_____________
3New Snags Identified This Week7 fields
Date Identified
_____________
Location / Grid / Room No.
_____________
Description of Snag / Defect
_____________
Trade / Agency Responsible (Civil, Electrical, Plumbing, etc.)
_____________
Photo Reference No.
_____________
Severity (Critical, Major, Minor)
_____________
4Snags Rectified & Closed This Week6 fields
Original Date Identified
_____________
Date Rectified
_____________
Description of Rectification Work
_____________
Verified By (PMC Engineer)
_____________
Closure Photo Reference No.
_____________
5Outstanding Snags (Pending Rectification)7 fields
Age of Snag (in days)
_____________
Location / Grid / Room No.
_____________
Description of Snag
_____________
Agency Responsible
_____________
Reason for Delay / Remarks
_____________
Target Closure Date
_____________
6Agency-wise Snag Analysis5 fields
Trade / Agency Name
_____________
Total Outstanding Snags
_____________
Snags Outstanding > 7 days
_____________
Snags Outstanding > 14 days
_____________
Remarks on Agency Performance
_____________
💡 Sample filled excerpt
Snag ID: SN-CIV-234 | Location: Tower A, 15th Floor, Flat 1502, Master Bedroom | Description: Uneven plaster finish on the west wall near the window. | Agency: M/s Sharma Plaster Works | Severity: Minor | Status: Outstanding, Age: 5 days.
⚖ Compliance notes
- Fulfills documentation requirements under FIDIC Sub-clause 11.1 (Completion of Outstanding Work and Remedying Defects) and Sub-clause 11.3 (Extension of Defects Notification Period).
- Provides evidence for joint inspections and de-snagging meetings, forming a basis for issuing the Taking-Over Certificate.
- Acts as a formal record for contract administration, potentially justifying withholding of retention money for unrectified defects as per contract terms.
- Supports compliance with CPWD General Conditions of Contract, Clause 49 (Defects Liability Period).