📍 When to use this template
- Used after the Taking-Over Certificate is issued and the project enters the Defect Liability Period.
- Updated whenever a new defect is reported by the client/end-user or when a previously reported defect's status changes.
- Maintained by the PMC/Engineer's site team, in coordination with the Contractor and the Client's facility management team.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information8 fields
Project Name
_____________
Contract / Package No.
_____________
Document Number
_____________
Date of Taking Over
_____________
DLP Start Date
_____________
DLP End Date
_____________
Prepared By (Name/Designation)
_____________
Approved By (Name/Designation)
_____________
2Defect Identification7 fields
Defect ID No.
_____________
Date Reported
_____________
Reported By (Name/Dept)
_____________
Location (Building/Floor/Grid/Room No.)
_____________
System / Trade (Civil/Elec/Plumb/HVAC/FA)
_____________
Description of Defect
_____________
Photograph/Reference Doc No.
_____________
3Contractor Notification & Action Plan6 fields
Date Notified to Contractor
_____________
Notification Ref. No. (Email/Letter)
_____________
Acknowledged by Contractor (Date)
_____________
Target Rectification Date
_____________
Assigned to (Contractor's Rep Name)
_____________
Proposed Method of Rectification
_____________
4Rectification & Inspection6 fields
Date Rectification Started
_____________
Date Rectification Completed
_____________
Contractor's Rectification Report No.
_____________
Materials Used for Rectification
_____________
Joint Inspection Date
_____________
Inspection By (PMC/Client/Engineer)
_____________
5Closure & Verification5 fields
Status (Open/In-Progress/Closed/Rejected)
_____________
Client's Acceptance Date
_____________
Remarks / Reason for Rejection
_____________
Final Closure Date
_____________
Closed By (PMC/Engineer)
_____________
6Cost & Time Impact4 fields
Is it a Latent Defect? (Yes/No)
_____________
Cost Borne By (Contractor/Client/Insurance)
_____________
Associated Cost (if applicable)
_____________
Time Extension Claimed (if any)
_____________
💡 Sample filled excerpt
Defect ID: DLP-021; Date Reported: 15-Jan-2024; Location: Tower A, 5th Floor, Pantry; Description: Water seepage from under the sink counter; Status: Closed; Final Closure Date: 28-Jan-2024; Remarks: P-trap joint re-sealed and tested. Client accepted.
⚖ Compliance notes
- Helps in administering the 'Defects Notification Period' as per FIDIC Conditions of Contract (e.g., Sub-Clause 11).
- Provides a formal record for releasing the second half of the Retention Money / Performance Security at the end of the DLP, as per contract terms.
- Acts as evidence of contractor's performance in fulfilling post-completion obligations, crucial during final account settlement.
- Essential documentation for the issuance of the Performance Certificate under FIDIC Sub-Clause 11.9.