QA/QC  › Site Paperwork & Coordination  › Request For Approval
Form · QC-SPW-FRM-002
Request For Approval (RFA)
15 checkpoints across 5 sections. Before procurement, execution, or installation of any material, drawing, method, or sample requiring consultant/client approval
15 Checkpoints
5 Sections
Per material/drawing/method submission
Contractor QA/QC Manager, Project Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SUBMISSION COMPLETENESS
A1Submission raised at least 14 working days before material procurement / execution date
Acceptance: Submission date ≥14 days before required date; critical items ≥21 days lead time
Cl. 8.4 — Control of external providers
OK
NC
NA
HOLD
A2Cover sheet complete: RFA number, subject, spec clause, contractor stamp, date
Acceptance: All cover fields filled; RFA number unique; contractor signature present
Cl. 7.5 — Documented information
OK
NC
NA
HOLD
A3All specified supporting documents attached (technical data, certificates, test reports, drawings)
Acceptance: Attachment checklist verified; no missing items; each document stamped and signed
Part 5 — Materials documentation
OK
NC
NA
HOLD
B. MATERIAL/PRODUCT COMPLIANCE
B1Material/product complies with specification, IS code, or NBC 2016 Part 5 requirements
Acceptance: IS/ISO compliance statement present; spec clause satisfied; deviations listed if any
Part 5 Section 1 — Material standards
OK
NC
NA
HOLD
B2Manufacturer test certificates (MTC) within validity; third-party lab reports where required
Acceptance: MTC not older than 6 months; 3rd-party test by NABL-accredited lab; batch linkage shown
Cl. 5.2 — Quality of material
OK
NC
NA
HOLD
B3ISI mark / BIS license / BEE star rating as applicable; license valid
Acceptance: ISI mark visible; BIS license number valid; BEE rating matches spec (e.g. 5-star AC)
Part 5 — Certification marks
OK
NC
NA
HOLD
B4Previous usage / track record demonstrated (past project references, warranty)
Acceptance: Two past project references minimum; warranty terms clear; duration ≥12 months
Cl. 8.4.2 — Type and extent of control
OK
NC
NA
HOLD
C. DRAWING/METHOD-STATEMENT TECHNICAL REVIEW
C1Shop drawings show all dimensions, materials, connections, tolerances clearly
Acceptance: Title block complete; scale noted; all notes legible; rev cloud on changes
Cl. 5.4 — Design and drawings
OK
NC
NA
HOLD
C2Method statement covers safety, sequence, resources, QA checks, hold points
Acceptance: All MS sections present (safety/sequence/resources/QC/hold); signed by QC and safety
Cl. 8.5.1 — Production controls
OK
NC
NA
HOLD
C3Calculations (structural, thermal, hydraulic) attached where required; signed by qualified engineer
Acceptance: Calcs stamped by licensed engineer; assumptions stated; software/version noted
Cl. 5.4 — Design verification
OK
NC
NA
HOLD
Showing 10 of 15 checkpoints ·
A. SUBMISSION COMPLETENESS
A1Submission raised at least 14 working days before material procurement / execution date
Cl. 8.4 — Control of external providers (ISO 9001)
Submission date ≥14 days before required date; critical items ≥21 days lead time
OKNCNAHOLD
A2Cover sheet complete: RFA number, subject, spec clause, contractor stamp, date
Cl. 7.5 — Documented information (ISO 9001)
All cover fields filled; RFA number unique; contractor signature present
OKNCNAHOLD
A3All specified supporting documents attached (technical data, certificates, test reports, drawings)
Part 5 — Materials documentation (NBC 2016)
Attachment checklist verified; no missing items; each document stamped and signed
OKNCNAHOLD
B. MATERIAL/PRODUCT COMPLIANCE
B1Material/product complies with specification, IS code, or NBC 2016 Part 5 requirements
Part 5 Section 1 — Material standards (NBC 2016)
IS/ISO compliance statement present; spec clause satisfied; deviations listed if any
OKNCNAHOLD
B2Manufacturer test certificates (MTC) within validity; third-party lab reports where required
Cl. 5.2 — Quality of material (IS 456)
MTC not older than 6 months; 3rd-party test by NABL-accredited lab; batch linkage shown
OKNCNAHOLD
B3ISI mark / BIS license / BEE star rating as applicable; license valid
Part 5 — Certification marks (NBC 2016)
ISI mark visible; BIS license number valid; BEE rating matches spec (e.g. 5-star AC)
OKNCNAHOLD
B4Previous usage / track record demonstrated (past project references, warranty)
Cl. 8.4.2 — Type and extent of control (ISO 9001)
Two past project references minimum; warranty terms clear; duration ≥12 months
OKNCNAHOLD
C. DRAWING/METHOD-STATEMENT TECHNICAL REVIEW
C1Shop drawings show all dimensions, materials, connections, tolerances clearly
Cl. 5.4 — Design and drawings (IS 456)
Title block complete; scale noted; all notes legible; rev cloud on changes
OKNCNAHOLD
C2Method statement covers safety, sequence, resources, QA checks, hold points
Cl. 8.5.1 — Production controls (ISO 9001)
All MS sections present (safety/sequence/resources/QC/hold); signed by QC and safety
OKNCNAHOLD
C3Calculations (structural, thermal, hydraulic) attached where required; signed by qualified engineer
Cl. 5.4 — Design verification (IS 456)
Calcs stamped by licensed engineer; assumptions stated; software/version noted
OKNCNAHOLD
Showing 10 of 15 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED — NCR RAISED
Remarks
Name / Sign / Date
Inspected By
Name / Sign / Date
Reviewed By
Name / Sign / Date