QA/QC  › Site Paperwork & Coordination  › Non-Conformance Report (NCR)
Register · QC-SPW-REG-003
Non-Conformance Report (NCR) Log
21 checkpoints across 5 sections. Continuously throughout project; updated every time an NCR is raised or closed
21 Checkpoints
5 Sections
Daily updates; monthly trend review
QA Manager, Document Controller

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. REGISTER COLUMN DEFINITIONS
A1Column 1: NCR NO — unique sequential number YYYY-###
Acceptance: Format: NCR-YYYY-###; unique across project; no duplicates or gaps
Cl. 7.5.3 — Documented information control
OK
NC
NA
HOLD
A2Column 2: ISSUE DATE — date NCR was raised and issued
Acceptance: Date of detection not later than 2 working days from issue
Cl. 10.2.1 — Timely recording
OK
NC
NA
HOLD
A3Column 3: RAISED BY — person and party (consultant/QA/auditor)
Acceptance: Name and organization clear; authority to raise NCR documented in project plan
Cl. 10.2 — Accountability
OK
NC
NA
HOLD
A4Column 4: TRADE / DISCIPLINE AND LOCATION — where NC occurred
Acceptance: Trade specified; location (grid/floor/element) unambiguous; linked to drawing
Cl. 8.5.2 — Traceability
OK
NC
NA
HOLD
A5Column 5: NC DESCRIPTION — specific violation of spec/IS/drawing
Acceptance: Deviation from specific requirement stated (spec clause cited); measurable
Cl. 10.2.1 — Nonconformity description
OK
NC
NA
HOLD
A6Column 6: SEVERITY — Major / Minor / Observation
Acceptance: Major=safety/structural impact; Minor=quality deviation; Observation=improvement
Cl. 10.2.1 — Severity classification
OK
NC
NA
HOLD
A7Column 7: DISPOSITION — Use-As-Is / Rework / Repair / Reject / Regrade
Acceptance: Disposition decided by consultant/designer within 7 days; concession signed if UAI
Cl. 8.7 — Control of nonconforming outputs
OK
NC
NA
HOLD
A8Column 8: CORRECTIVE ACTION ISSUED — CAR reference
Acceptance: CAR number linked; root cause analysis required for Major NCRs
Cl. 10.2.1 — Corrective action
OK
NC
NA
HOLD
A9Column 9: STATUS — OPEN / PENDING REWORK / CLOSED / APPEAL
Acceptance: Status updated weekly; appeals escalated to project manager; CLOSED with date
Cl. 10.2.2 — Status tracking
OK
NC
NA
HOLD
A10Column 10: CLOSURE DATE / CLOSE-OUT SIGNATORY
Acceptance: Date closure verified; verified by issuer or delegated authority; evidence attached
Cl. 10.2.1 — Closure verification
OK
NC
NA
HOLD
B. NCR RAISING AND NOTIFICATION
B1Each NCR issued within 2 working days of detection on approved template (QC-SPW-FRM-NCR)
Acceptance: Template complete; evidence (photo, measurement) attached; signed by raiser
Cl. 10.2 — Timely action
OK
NC
NA
HOLD
B2Contractor, consultant, client project lead notified same-day of NCR issue
Acceptance: Email distribution list; acknowledgment within 24 h; escalation if unacknowledged
Cl. 7.4 — Communication
OK
NC
NA
HOLD
B3Affected work area flagged physically with NCR tag; unauthorized continuation prevented
Acceptance: Red tag or barrier tape visible; instruction STOP PENDING DISPOSITION clear
Cl. 8.7 — Segregation of NC output
OK
NC
NA
HOLD
C. DISPOSITION AND CLOSURE
C1Disposition decided within 7 days by qualified consultant/designer; supporting rationale
Acceptance: Use-As-Is needs concession; rework most common; reject returned to supplier
Cl. 8.7.1 — Disposition decision
OK
NC
NA
HOLD
C2Rework executed per approved method; re-inspection raised after rework
Acceptance: Re-inspection RFI raised; consultant witnesses; closure only if compliant
Cl. 10.2.1 — Rework
OK
NC
NA
HOLD
C3NCR closure requires documented evidence: photos, test reports, measurement
Acceptance: Evidence shows NC eliminated; attached to NCR file; signed closure statement
Cl. 10.2.1 — Closure evidence
OK
NC
NA
HOLD
Showing 16 of 21 checkpoints ·
A. REGISTER COLUMN DEFINITIONS
A1Column 1: NCR NO — unique sequential number YYYY-###
Cl. 7.5.3 — Documented information control (ISO 9001)
Format: NCR-YYYY-###; unique across project; no duplicates or gaps
OKNCNAHOLD
A2Column 2: ISSUE DATE — date NCR was raised and issued
Cl. 10.2.1 — Timely recording (ISO 9001)
Date of detection not later than 2 working days from issue
OKNCNAHOLD
A3Column 3: RAISED BY — person and party (consultant/QA/auditor)
Cl. 10.2 — Accountability (ISO 9001)
Name and organization clear; authority to raise NCR documented in project plan
OKNCNAHOLD
A4Column 4: TRADE / DISCIPLINE AND LOCATION — where NC occurred
Cl. 8.5.2 — Traceability (ISO 9001)
Trade specified; location (grid/floor/element) unambiguous; linked to drawing
OKNCNAHOLD
A5Column 5: NC DESCRIPTION — specific violation of spec/IS/drawing
Cl. 10.2.1 — Nonconformity description (ISO 9001)
Deviation from specific requirement stated (spec clause cited); measurable
OKNCNAHOLD
A6Column 6: SEVERITY — Major / Minor / Observation
Cl. 10.2.1 — Severity classification (ISO 9001)
Major=safety/structural impact; Minor=quality deviation; Observation=improvement
OKNCNAHOLD
A7Column 7: DISPOSITION — Use-As-Is / Rework / Repair / Reject / Regrade
Cl. 8.7 — Control of nonconforming outputs (ISO 9001)
Disposition decided by consultant/designer within 7 days; concession signed if UAI
OKNCNAHOLD
A8Column 8: CORRECTIVE ACTION ISSUED — CAR reference
Cl. 10.2.1 — Corrective action (ISO 9001)
CAR number linked; root cause analysis required for Major NCRs
OKNCNAHOLD
A9Column 9: STATUS — OPEN / PENDING REWORK / CLOSED / APPEAL
Cl. 10.2.2 — Status tracking (ISO 9001)
Status updated weekly; appeals escalated to project manager; CLOSED with date
OKNCNAHOLD
A10Column 10: CLOSURE DATE / CLOSE-OUT SIGNATORY
Cl. 10.2.1 — Closure verification (ISO 9001)
Date closure verified; verified by issuer or delegated authority; evidence attached
OKNCNAHOLD
B. NCR RAISING AND NOTIFICATION
B1Each NCR issued within 2 working days of detection on approved template (QC-SPW-FRM-NCR)
Cl. 10.2 — Timely action (ISO 9001)
Template complete; evidence (photo, measurement) attached; signed by raiser
OKNCNAHOLD
B2Contractor, consultant, client project lead notified same-day of NCR issue
Cl. 7.4 — Communication (ISO 9001)
Email distribution list; acknowledgment within 24 h; escalation if unacknowledged
OKNCNAHOLD
B3Affected work area flagged physically with NCR tag; unauthorized continuation prevented
Cl. 8.7 — Segregation of NC output (ISO 9001)
Red tag or barrier tape visible; instruction STOP PENDING DISPOSITION clear
OKNCNAHOLD
C. DISPOSITION AND CLOSURE
C1Disposition decided within 7 days by qualified consultant/designer; supporting rationale
Cl. 8.7.1 — Disposition decision (ISO 9001)
Use-As-Is needs concession; rework most common; reject returned to supplier
OKNCNAHOLD
C2Rework executed per approved method; re-inspection raised after rework
Cl. 10.2.1 — Rework (ISO 9001)
Re-inspection RFI raised; consultant witnesses; closure only if compliant
OKNCNAHOLD
C3NCR closure requires documented evidence: photos, test reports, measurement
Cl. 10.2.1 — Closure evidence (ISO 9001)
Evidence shows NC eliminated; attached to NCR file; signed closure statement
OKNCNAHOLD
Showing 16 of 21 ·