QA/QC  › Site Paperwork & Coordination  › Snag List Register
Register · QC-SPW-REG-001
Snag List Register
18 checkpoints across 4 sections. Pre-handover snagging walk; ongoing through project finishing phase until zero-snag certification
18 Checkpoints
4 Sections
Weekly through finishing; daily near handover
QA Manager, Consultant

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. REGISTER COLUMN DEFINITIONS
A1Column 1: SNAG NO — unique sequential number per area/unit
Acceptance: Format: AREA-SNAG-### (e.g. T1-SNAG-001); unique in register; no duplicates
Cl. 10.2 — Nonconformity recording
OK
NC
NA
HOLD
A2Column 2: AREA / ROOM / GRID — exact location of snag
Acceptance: Floor, room number, wall/face, grid reference; location unambiguous
Cl. 8.5.2 — Identification and traceability
OK
NC
NA
HOLD
A3Column 3: TRADE / DISCIPLINE — Civil, MEP, Finishes, External
Acceptance: Trade tag allows filtering to responsible contractor/subcontractor
Cl. 8.4 — Responsibility allocation
OK
NC
NA
HOLD
A4Column 4: SNAG DESCRIPTION — specific, measurable defect description
Acceptance: Action-verb description (e.g. 'chip 25x15 mm on skirting'); photo reference
Part 5 — Defect recording
OK
NC
NA
HOLD
A5Column 5: SEVERITY — A (Critical), B (Major), C (Minor), D (Cosmetic)
Acceptance: A=safety/function, B=affects use, C=visible defect, D=cosmetic only
Cl. 10.2.1 — Severity classification
OK
NC
NA
HOLD
A6Column 6: RESPONSIBLE PARTY — contractor / subcontractor name
Acceptance: Name of firm and individual contact; phone/email available
Cl. 8.4.1 — Supplier accountability
OK
NC
NA
HOLD
A7Column 7: TARGET DATE — agreed date for rectification
Acceptance: Realistic date agreed by contractor; Severity A <7 days, B <14, C <21 days
Cl. 10.2.2 — Timely correction
OK
NC
NA
HOLD
A8Column 8: STATUS — OPEN, IN PROGRESS, CLOSED, RE-OPENED
Acceptance: Status updated weekly; re-opened if rectification unacceptable
Cl. 10.2 — Action tracking
OK
NC
NA
HOLD
A9Column 9: CLOSURE DATE AND VERIFIER — actual date and person who verified
Acceptance: Closure verified by QA engineer or consultant; signature/initials on record
Cl. 10.2 — Verification of action
OK
NC
NA
HOLD
B. SNAG LOGGING PROCEDURE
B1Snag walk conducted systematically: room by room, top-down, left-to-right
Acceptance: Walk route defined; no area skipped; checklist per room filled consistently
Cl. 9.1 — Monitoring method
OK
NC
NA
HOLD
B2Each snag photographed with room number marker visible; photo numbered same as snag
Acceptance: Photo file named with snag no; visible label in frame; close-up and context shots
Cl. 7.5.3 — Record evidence
OK
NC
NA
HOLD
B3Snag marked physically on location (colored tape/sticker) for contractor reference
Acceptance: Low-tack tape color-coded by severity; removed only on closure verification
Part 5 — Defect identification
OK
NC
NA
HOLD
C. RECTIFICATION AND CLOSURE PROCEDURE
C1Contractor notified of snags within 2 working days of walk; acknowledgment received
Acceptance: Snag list shared (email/portal); contractor acknowledges receipt in writing
Cl. 10.2 — Communication of nonconformity
OK
NC
NA
HOLD
C2Rectified items offered for re-inspection; location tape removed only after acceptance
Acceptance: Contractor raises re-inspection request; QA verifies on site; defect no longer visible
Cl. 10.2 — Verification of correction
OK
NC
NA
HOLD
C3Re-opened snags (failed re-inspection) clearly flagged; additional corrective action required
Acceptance: Re-opened count tracked; root cause analysis for repeat failures; escalated to PM
Cl. 10.2.1 — Escalation
OK
NC
NA
HOLD
Showing 15 of 18 checkpoints ·
A. REGISTER COLUMN DEFINITIONS
A1Column 1: SNAG NO — unique sequential number per area/unit
Cl. 10.2 — Nonconformity recording (ISO 9001)
Format: AREA-SNAG-### (e.g. T1-SNAG-001); unique in register; no duplicates
OKNCNAHOLD
A2Column 2: AREA / ROOM / GRID — exact location of snag
Cl. 8.5.2 — Identification and traceability (ISO 9001)
Floor, room number, wall/face, grid reference; location unambiguous
OKNCNAHOLD
A3Column 3: TRADE / DISCIPLINE — Civil, MEP, Finishes, External
Cl. 8.4 — Responsibility allocation (ISO 9001)
Trade tag allows filtering to responsible contractor/subcontractor
OKNCNAHOLD
A4Column 4: SNAG DESCRIPTION — specific, measurable defect description
Part 5 — Defect recording (NBC 2016)
Action-verb description (e.g. 'chip 25x15 mm on skirting'); photo reference
OKNCNAHOLD
A5Column 5: SEVERITY — A (Critical), B (Major), C (Minor), D (Cosmetic)
Cl. 10.2.1 — Severity classification (ISO 9001)
A=safety/function, B=affects use, C=visible defect, D=cosmetic only
OKNCNAHOLD
A6Column 6: RESPONSIBLE PARTY — contractor / subcontractor name
Cl. 8.4.1 — Supplier accountability (ISO 9001)
Name of firm and individual contact; phone/email available
OKNCNAHOLD
A7Column 7: TARGET DATE — agreed date for rectification
Cl. 10.2.2 — Timely correction (ISO 9001)
Realistic date agreed by contractor; Severity A <7 days, B <14, C <21 days
OKNCNAHOLD
A8Column 8: STATUS — OPEN, IN PROGRESS, CLOSED, RE-OPENED
Cl. 10.2 — Action tracking (ISO 9001)
Status updated weekly; re-opened if rectification unacceptable
OKNCNAHOLD
A9Column 9: CLOSURE DATE AND VERIFIER — actual date and person who verified
Cl. 10.2 — Verification of action (ISO 9001)
Closure verified by QA engineer or consultant; signature/initials on record
OKNCNAHOLD
B. SNAG LOGGING PROCEDURE
B1Snag walk conducted systematically: room by room, top-down, left-to-right
Cl. 9.1 — Monitoring method (ISO 9001)
Walk route defined; no area skipped; checklist per room filled consistently
OKNCNAHOLD
B2Each snag photographed with room number marker visible; photo numbered same as snag
Cl. 7.5.3 — Record evidence (ISO 9001)
Photo file named with snag no; visible label in frame; close-up and context shots
OKNCNAHOLD
B3Snag marked physically on location (colored tape/sticker) for contractor reference
Part 5 — Defect identification (NBC 2016)
Low-tack tape color-coded by severity; removed only on closure verification
OKNCNAHOLD
C. RECTIFICATION AND CLOSURE PROCEDURE
C1Contractor notified of snags within 2 working days of walk; acknowledgment received
Cl. 10.2 — Communication of nonconformity (ISO 9001)
Snag list shared (email/portal); contractor acknowledges receipt in writing
OKNCNAHOLD
C2Rectified items offered for re-inspection; location tape removed only after acceptance
Cl. 10.2 — Verification of correction (ISO 9001)
Contractor raises re-inspection request; QA verifies on site; defect no longer visible
OKNCNAHOLD
C3Re-opened snags (failed re-inspection) clearly flagged; additional corrective action required
Cl. 10.2.1 — Escalation (ISO 9001)
Re-opened count tracked; root cause analysis for repeat failures; escalated to PM
OKNCNAHOLD
Showing 15 of 18 ·
Inspection Sign-Off
REVIEWED
ACTION REQUIRED
Remarks
Name / Sign / Date
Inspected By
Name / Sign / Date
Reviewed By
Name / Sign / Date