PMC🏗 Equipment & PlantScaffold Register

Scaffold Register

register
PMC-EQP-REG-002·v1.0-beta·⚠ Beta — review before use

This register is used to maintain a complete inventory and inspection record of all scaffolding components on site. It helps the site team track material from receipt to erection, ensuring only safe and compliant materials are used for work at height.

Download
📍 When to use this template
  • Maintained continuously from the start of the project whenever scaffolding material is received, issued, or returned.
  • Updated daily or weekly by the Storekeeper and cross-verified by the Safety Officer.
  • Filled by the Storekeeper for material movement and by the certified Scaffolding Supervisor/Inspector for erection and inspection details.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Info6 fields
Project Name
_____________
Contract Package No.
_____________
Register No.
_____________
Date
_____________
Prepared By (Storekeeper)
_____________
Reviewed By (Safety Officer)
_____________
2Material Receipt Details9 fields
GRN / DC No.
_____________
Date of Receipt
_____________
Supplier Name
_____________
Vehicle No.
_____________
Material Description (e.g., Pipe 48.3mm OD, Right Angle Coupler)
_____________
Unit (Nos./Mtr/Kg)
_____________
Quantity Received
_____________
Inspection Status (Accepted/Rejected)
_____________
Remarks / Storage Location
_____________
3Stock & Issuance Record8 fields
Date of Issue
_____________
Issue Slip No.
_____________
Issued To (Contractor/Dept)
_____________
Location / Gridline of Erection
_____________
Item Description
_____________
Quantity Issued
_____________
Balance Stock
_____________
Receiver's Signature
_____________
4Return & Damage Record9 fields
Date of Return
_____________
Return Slip No.
_____________
Returned From (Contractor/Dept)
_____________
Item Description
_____________
Quantity Returned (Good Condition)
_____________
Quantity Returned (Damaged/Bent)
_____________
Reason for Damage
_____________
Scrap Note No. (if applicable)
_____________
Storekeeper's Signature
_____________
5Scaffolding Erection & Initial Inspection Log10 fields
Scaffold ID / Tag No.
_____________
Location / Structure ID
_____________
Date of Erection Completion
_____________
Erected By (Supervisor Name)
_____________
Type of Scaffold (e.g., Independent Tied, Birdcage, Cantilever)
_____________
Load Class (Light/Medium/Heavy Duty)
_____________
Date of Initial Inspection
_____________
Inspected By (Competent Person Name/ID)
_____________
Inspection Result (Safe - Green Tag / Unsafe - Red Tag)
_____________
Next Inspection Due Date (Max 7 days)
_____________
6Periodic Inspection Record (Weekly)8 fields
Scaffold ID / Tag No.
_____________
Inspection Date
_____________
Inspected By (Competent Person)
_____________
Observations / Defects Noted
_____________
Corrective Action Taken
_____________
Action By
_____________
Date of Rectification
_____________
Re-inspection Status (Safe/Unsafe)
_____________
💡 Sample filled excerpt
Scaffold ID: SF-T2-B1-014; Location: Tower 2, Block 1, Grid A-C/5-7; Erection Completion: 15-Apr-2024; Inspected By: R. K. Sharma (CP/087); Result: Safe for Use (Green Tag); Next Inspection Due: 22-Apr-2024
⚖ Compliance notes
  • Fulfills mandatory requirements under the BOCW (Building and Other Construction Workers) Rules, 1998, specifically Rule 45 (Scaffolds) and Rule 213 (Register of Scaffolds).
  • Provides evidence of compliance with IS 3696 (Safety code for scaffolds) and IS 4014 (Code of practice for steel tubular scaffolding).
  • Essential documentation for safety audits, accident investigations (falls from height), and for supporting the 'Work at Height' permit system.
  • Helps track material assets and quantify damages for back-charging subcontractors or for insurance claims.