PMC🏗 Equipment & PlantCrane Inspection Checklist (Daily)

Crane Inspection Checklist (Daily)

checklist
PMC-EQP-CHK-001·v1.0-beta·⚠ Beta — review before use

This is a daily checklist to ensure the crane is safe to operate before starting any lifting work. It helps prevent accidents and complies with safety regulations as per BOCW Act.

ReferencesBOCW Act, 1996BOCW Central Rules, 1998 (Rule 55, 61, 239)IS 14735: Code of practice for selection, installation, operation and maintenance of cranes and hoistsIS 4573: Power driven mobile cranesFactory Act, 1948 (Section 29)
Download
📍 When to use this template
  • Before the first lift of the day for any mobile or tower crane.
  • Daily, filled out by the crane operator and verified by the site supervisor or safety officer.
  • A copy is kept in the crane cabin and another is filed with the site safety records.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Identification9 fields
Project Name
_____________
Contract Package No.
_____________
Checklist No.
_____________
Date
_____________
Crane Make & Model
_____________
Crane ID / Registration No.
_____________
Location of Crane on Site
_____________
Operator Name & License No.
_____________
Third Party Inspection (TPI) Validity Date
_____________
2Pre-Start Checks (Engine Off)8 fields
Check for Leaks (Hydraulic, Engine Oil, Coolant)
_____________
Tyre Condition & Pressure (for mobile cranes)
_____________
Track Condition (for crawler cranes)
_____________
Fluid Levels (Engine Oil, Hydraulic, Coolant, Fuel)
_____________
Battery & Terminals Condition
_____________
Fire Extinguisher (Present, Charged, & Correct Type)
_____________
General Housekeeping (Cabin Cleanliness)
_____________
Mirrors & Windows Condition (Clean, Unbroken)
_____________
3Operational Checks (Engine On)8 fields
All Gauges & Indicators Functional
_____________
Horn & Reverse Alarm Working
_____________
Lights (Headlights, Indicators, Beacon) Functional
_____________
Slew Lock / Brake Operation
_____________
Boom Extension/Retraction Smoothness
_____________
Hoist (Main & Aux) Operation (Up/Down)
_____________
Emergency Stop Functionality
_____________
Outrigger Operation & Leveling
_____________
4Safety Devices & Load Handling Gear8 fields
Safe Load Indicator (SLI) / LMI Test (Functioning Correctly)
_____________
Anti-Two Block / Over-Hoist Limit Switch Checked
_____________
Slew Limit Switch Checked
_____________
Wire Rope Condition (No Kinks, Broken Strands, Corrosion)
_____________
Hook & Safety Latch Condition
_____________
Sheaves & Pulleys Condition
_____________
Outrigger Pads & Base Condition
_____________
Slings, Shackles & Lifting Tackle Inspected (as per separate register)
_____________
5Remarks & Sign-off7 fields
Defects Noted (If any)
_____________
Action Taken / Required
_____________
Crane Certified Fit for Use (Yes/No)
_____________
Operator's Name & Signature
_____________
Rigger's Name & Signature
_____________
Supervisor's/Safety Officer's Name & Signature
_____________
Time of Inspection
_____________
💡 Sample filled excerpt
Defects Noted: Minor hydraulic fluid seepage near front right outrigger jack. Action Taken: Wiped clean, will monitor throughout the day. Not affecting operation. Crane Certified Fit for Use: Yes. Operator: Ramesh Kumar. Supervisor: S.K. Sharma.
⚖ Compliance notes
  • Fulfills requirements under the BOCW Act, 1996 and Central Rules, 1998 (Rule 55, 61) regarding daily examination of lifting appliances.
  • Serves as evidence of due diligence during safety audits or accident investigations, as required by law.
  • Supports compliance with IS 14735 (Code of practice for selection, installation, operation and maintenance of cranes and hoists).
  • Mandatory record for ISO 45001 (OH&S Management Systems) compliance and contractor safety management.