PMC🏗 Equipment & PlantEquipment Mobilization Form

Equipment Mobilization Form

form
PMC-EQP-FRM-001·v1.0-beta·⚠ Beta — review before use

This form is the official request to bring any major machinery or equipment to the site. It's used to verify that the equipment is safe, has all necessary legal documents like TPI and insurance, and that a qualified operator is available.

ReferencesBOCW (Building and Other Construction Workers) Rules, 1998 (Rules 56, 57, 62-73)IS 4573: Power-driven mobile cranesIS 13367: Guidelines for safe use of mobile cranesThe Motor Vehicles Act, 1988
Download
📍 When to use this template
  • Before any major equipment (e.g., Tower Crane, Batching Plant, Excavator, DG Set) is transported to the project site.
  • Submitted by the Contractor's Plant & Machinery (P&M) in-charge to the PMC/Client for approval.
  • A separate form is required for each individual piece of major equipment.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information8 fields
Project Name
_____________
Contract Package No.
_____________
Form Reference No.
_____________
Date of Submission
_____________
Contractor Name
_____________
Prepared By (Contractor P&M)
_____________
Reviewed By (PMC)
_____________
Approved By (Engineer-in-Charge)
_____________
2Equipment Details8 fields
Equipment Name / Type
_____________
Make & Model
_____________
Equipment ID / Serial No.
_____________
Year of Manufacture
_____________
Capacity / Rating (e.g., 10 Ton, 500 KVA)
_____________
Proposed Location on Site (Attach Layout Drawing)
_____________
Expected Date of Arrival
_____________
Expected Duration on Site
_____________
3Operator & Crew Details6 fields
Operator Name
_____________
Operator License No. & Validity
_____________
Operator Experience (Years)
_____________
Helper/Rigger Name(s)
_____________
Skill Certification / Training Records (Attached)
_____________
Medical Fitness Certificate (Attached)
_____________
4Statutory & Safety Compliance Checklist8 fields
Third Party Inspection (TPI) Certificate (Attached)
_____________
TPI Certificate Validity Date
_____________
Road Tax / RTO Permit Copy (Attached)
_____________
Comprehensive Insurance Policy Copy (Attached)
_____________
Pollution Under Control (PUC) Certificate (Attached)
_____________
Original Purchase Invoice / Ownership Proof (Attached)
_____________
Operator's Competency Certificate (as per BOCW Rules)
_____________
Load Test Certificate (for lifting equipment)
_____________
5Mobilization Logistics5 fields
Transportation Method (e.g., Self-propelled, Trailer)
_____________
Proposed Route to Site
_____________
Required Site Preparations (e.g., Hardstand, Foundation)
_____________
Assembly / Erection Plan (if applicable)
_____________
Power / Fuel Requirement on Site
_____________
6PMC/Client Verification & Approval5 fields
Documents Verified By (PMC)
_____________
Physical Inspection Status (Pending / Done)
_____________
Remarks / Deficiencies Noted
_____________
Approval Status (Approved / Rejected / Approved with Conditions)
_____________
Signature & Stamp (Engineer-in-Charge)
_____________
💡 Sample filled excerpt
Equipment Name: Crawler Crane | Make & Model: SANY SCC600A | Capacity: 60 Ton | TPI Certificate Validity: 25-Dec-2024 | Operator Name: Mr. Suresh Kumar | License No.: MH0420180012345 (Valid till 15-Jul-2026) | Proposed Location: Grid A-5, near Tower 3.
⚖ Compliance notes
  • Helps comply with BOCW Rules, 1998, Rule 56 (Transport and Earth Moving Equipment) and Rule 57 (Lifting Appliances).
  • Provides necessary documentation for safety audits and inspections by the Labour Department or client safety teams.
  • Forms a key part of the Contractor's Plant & Machinery (P&M) records, often required for bill certification.
  • Fulfills contractual obligations under the General Conditions of Contract (GCC) regarding equipment fitness and safety.