Equipment Daily Log

log
PMC-EQP-LOG-001·v1.0-beta·⚠ Beta — review before use

This is a daily log for tracking the usage of machinery on site. It helps record which equipment (like JCB, crane, batching plant) was used, for how long, and if it was working or idle, which is crucial for billing and progress monitoring.

ReferencesBOCW Rules, 1998 (Rule 55 - Transport and earth moving equipment)CPWD Works Manual (Chapter on Plant & Machinery)FIDIC Conditions of Contract (Clauses related to Contractor's Equipment)IS 1200 (All Parts) - As backup for work quantities measured
Download
📍 When to use this template
  • Filled daily for each major piece of equipment deployed on site.
  • Used to calculate equipment hire charges for contractor bills or internal cost allocation.
  • Typically filled by the site supervisor or equipment operator and verified by the engineer.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Log Sheet No.
_____________
Date
_____________
Prepared By (Supervisor/Operator)
_____________
Verified By (Engineer)
_____________
2Equipment Identification5 fields
Equipment Type (e.g., Excavator, Dumper, Crane)
_____________
Equipment Make & Model
_____________
Equipment ID / Registration No.
_____________
Operator Name
_____________
Operator License Details
_____________
3Daily Log - Working Hours6 fields
Start Time (HH:MM)
_____________
End Time (HH:MM)
_____________
Total Working Hours
_____________
Start HMR (Hour Meter Reading)
_____________
End HMR
_____________
Total HMR Hours
_____________
4Daily Log - Idle / Breakdown Hours7 fields
Idle Time From (HH:MM)
_____________
Idle Time To (HH:MM)
_____________
Reason for Idle (e.g., No Work, Operator Absent, Fuel Shortage)
_____________
Breakdown Time From (HH:MM)
_____________
Breakdown Time To (HH:MM)
_____________
Reason for Breakdown
_____________
Action Taken
_____________
5Work Details4 fields
Location of Work (Grid/Chainage)
_____________
Activity Performed (e.g., Excavation, Concreting, Lifting)
_____________
Quantity of Work Done (if applicable)
_____________
Remarks / Observations
_____________
6Fuel & Consumables4 fields
Fuel Issued (Litres)
_____________
Engine Oil / Hydraulic Oil Topped Up (Litres)
_____________
Greasing Done (Yes/No)
_____________
Any other consumables used
_____________
💡 Sample filled excerpt
Equipment: JCB 3DX, ID: MH-04-AB-1234. Start HMR: 5432.1, End HMR: 5439.6. Total Working: 7.5 hrs. Activity: Trench excavation for footing F3 at Grid A/5. Idle: 1.5 hrs (waiting for layout marking).
⚖ Compliance notes
  • Supports billing verification as per contract clauses related to equipment hire charges in RA Bills.
  • Acts as a supporting document for claims related to idle machinery under FIDIC Sub-Clause 2.1 (Right of Access to the Site) or similar contract provisions.
  • Helps in monitoring equipment health and maintenance records, indirectly supporting compliance with BOCW Rules regarding safe machinery.
  • Provides data for reconciliation of contractor's Running Account (RA) Bills and fuel consumption records.