QA/QC  › Generic Master Forms  › Daily Inspection Log
Register · QC-GEN-REG-002
Daily Inspection Log
20 checkpoints across 2 sections. DAILY — One log completed each day (or per shift for large projects). Primary record of QC activity on site. Used for weekly/monthly trend analysis, hold point management, and quality performance reporting.
20 Checkpoints
2 Sections
Daily completion, weekly review, monthly analysis
QC Inspector, QC In-charge

Checklist Preview

S.No.CheckpointIS RequirementStatus
LOGCOLUMNS. Daily Inspection Log — Column Definitions
COL_01S.No
Acceptance: Sequential from 1 to N, no gaps or duplicates. Restarts from 1 for each new day/week.
Sequential numbering of daily inspection entries
COL_02Date
Acceptance: Format: DD/MM/YYYY (e.g., 05/04/2026). One row per inspection (multiple inspections per day allowed).
Calendar date of inspection
COL_03Time (Start Time of Inspection)
Acceptance: Format: HH:MM (24-hour) (e.g., 09:30). Used to sequence multiple daily inspections.
Time when inspection commenced
COL_04Area / Zone / Location
Acceptance: Specific area name: e.g., 'Block A', 'Plot 5', 'Foundation — Grid 3-5 (A-C)', 'Basement Level-1, Column Line 4', 'North Wing, 3rd Floor, Zone B'
Physical location where inspection was done
COL_05Activity / Element Inspected
Acceptance: e.g., 'Concrete Pouring — Foundation Slab', 'Steel Erection — Beam Installation', 'Brick Masonry — Exterior Wall', 'Plumbing Installation — Roughing', 'Reinforcement Placement', 'Formwork Installation'
Specific construction activity or element checked
COL_06IS Code / Standard Reference
Acceptance: e.g., 'IS 456:2000', 'IS 875:1987 Part 3', 'IS 3786:1983', 'IS 1199:1959', 'IS 1123:1959', or clause number: 'IS 456 Clause 6.3'
Applicable IS code or standard for this activity
COL_07Inspection Type
Acceptance: VISUAL = Visual inspection only (surface finish, alignment, placement, appearance). DIMENSIONAL = Measurement-based (thickness, width, height, spacing, flatness, level). TEST = Destructive or non-destructive test (compression, slump, ultrasonic, pressure, tensile). COMBINED = Multiple types performed in same inspection.
Category of inspection or test performed
COL_08Result / Status
Acceptance: OK = Conforms to acceptance criteria, no deviations. NC (Non-Conformance) = Does not meet criteria, NCR raised. HOLD = Work stopped pending resolution. NA = Not Applicable to this batch/section. CONDITIONAL = Minor deviations accepted by authority (reference approval number).
Outcome of inspection
COL_09NCR Number (if NC status)
Acceptance: If Result = NC, enter linked NCR number (e.g., 'NCR-001', 'NCR-015'). If Result = OK/HOLD/NA, leave blank or enter 'N/A'. Allows traceability between daily log and NCR register.
Link to NCR if non-conformance found
COL_10Quantity / Extent Inspected
Acceptance: e.g., '100 m³ concrete' (if inspection was 100% of daily pour), '50m of rebar' (length checked), '120 bricks' (count of units), '60%' (portion of total), '3 cubes' (number of test samples), '5 of 10' (sample count)
Scope of inspection (volume, area, count, percentage)
COL_11Inspector Name / QC Engr. Name
Acceptance: Full name of QC engineer, site engineer, or inspector (e.g., 'Shri Rajesh Kumar', 'Ms. Priya Singh'). Used for accountability and skill tracking.
Identity of person conducting inspection
COL_12Remarks / Observations / Test Results
Acceptance: e.g., 'Slump 110mm (criteria: 100±25mm) — OK'. 'Surface finish level variation 2.5mm in 3m length (criteria: ≤3mm) — OK'. 'Rebar spacing found 165mm, design 150mm (tolerance: ±10mm) — Marginal, escalate'. 'Compression test: 31 MPa (criteria: ≥30 MPa) — PASS'. 'Honeycombing observed, ~0.3 m² area'. 'Weather: 28°C, clear, dry'.
Additional details, numerical results, or notes
COL_13Hold Point Released? (Y/N) — Release Details
Acceptance: If inspection was a hold point: Y/N. If released, enter: Released by (name), approval date, approval number. If not released: Reason pending, expected release date. Allows tracking of work blockages.
Track hold point resolution
SUMMARY. Daily / Weekly Summary Statistics
SUMMARY_01Total Inspections Conducted
Acceptance: e.g., 'Day 1: 12 inspections', 'Week 1: 58 inspections', 'Month: 240 inspections'
Count of all inspection entries in this log
SUMMARY_02Passed (OK) Count
Acceptance: e.g., '11 passed', '58 passed', '95% pass rate' (calculated as OK count / Total inspections)
Number of inspections with OK status
SUMMARY_03Non-Conformance (NC) Count
Acceptance: e.g., '1 NC found', '3 NCs raised', 'NCR-001, NCR-002, NCR-003' (list NCR numbers)
Number of inspections with NC status
SUMMARY_04Hold Points Count (Open / Released)
Acceptance: e.g., 'Total hold points: 4. Released: 2, Pending: 2', 'All 3 hold points from yesterday released today'
Number of hold points identified and their status
SUMMARY_05Not Applicable (NA) Count
Acceptance: e.g., 'NA: 2 (batch found unsuitable, testing skipped)', 'NA: 0 (all activities applicable)'
Number of NA inspections
SUMMARY_06Conditional Approvals Count (if any)
Acceptance: e.g., 'Conditional: 1 (Plaster finish approved by Engr. X despite 4.2mm level variation, ref: APP-045)'
Minor deviations accepted by authority
SUMMARY_07Trending / Key Observations
Acceptance: e.g., 'Concrete quality good — pass rate 95%. Rebar placement errors declining (3 issues past 2 weeks → 0 this week). Masonry finish still variable — consider additional training. No safety issues.' Or 'Week 1 pass rate: 85%. Week 2: 92%. Trend improving.'
Notable patterns or concerns for management attention
LOGCOLUMNS. Daily Inspection Log — Column Definitions
COL_01S.No
Sequential numbering of daily inspection entries (Recording Standard)
Sequential from 1 to N, no gaps or duplicates. Restarts from 1 for each new day/week.
COL_02Date
Calendar date of inspection (Time Tracking Standard)
Format: DD/MM/YYYY (e.g., 05/04/2026). One row per inspection (multiple inspections per day allowed).
COL_03Time (Start Time of Inspection)
Time when inspection commenced (Time Tracking Standard)
Format: HH:MM (24-hour) (e.g., 09:30). Used to sequence multiple daily inspections.
COL_04Area / Zone / Location
Physical location where inspection was done (Site Organization Standard)
Specific area name: e.g., 'Block A', 'Plot 5', 'Foundation — Grid 3-5 (A-C)', 'Basement Level-1, Column Line 4', 'North Wing, 3rd Floor, Zone B'
COL_05Activity / Element Inspected
Specific construction activity or element checked (Activity Identification Standard)
e.g., 'Concrete Pouring — Foundation Slab', 'Steel Erection — Beam Installation', 'Brick Masonry — Exterior Wall', 'Plumbing Installation — Roughing', 'Reinforcement Placement', 'Formwork Installation'
COL_06IS Code / Standard Reference
Applicable IS code or standard for this activity (Regulatory Reference Standard)
e.g., 'IS 456:2000', 'IS 875:1987 Part 3', 'IS 3786:1983', 'IS 1199:1959', 'IS 1123:1959', or clause number: 'IS 456 Clause 6.3'
COL_07Inspection Type
Category of inspection or test performed (Inspection Classification Standard)
VISUAL = Visual inspection only (surface finish, alignment, placement, appearance). DIMENSIONAL = Measurement-based (thickness, width, height, spacing, flatness, level). TEST = Destructive or non-destructive test (compression, slump, ultrasonic, pressure, tensile). COMBINED = Multiple types performed in same inspection.
COL_08Result / Status
Outcome of inspection (Result Recording Standard)
OK = Conforms to acceptance criteria, no deviations. NC (Non-Conformance) = Does not meet criteria, NCR raised. HOLD = Work stopped pending resolution. NA = Not Applicable to this batch/section. CONDITIONAL = Minor deviations accepted by authority (reference approval number).
COL_09NCR Number (if NC status)
Link to NCR if non-conformance found (Traceability Standard)
If Result = NC, enter linked NCR number (e.g., 'NCR-001', 'NCR-015'). If Result = OK/HOLD/NA, leave blank or enter 'N/A'. Allows traceability between daily log and NCR register.
COL_10Quantity / Extent Inspected
Scope of inspection (volume, area, count, percentage) (Sampling Standard)
e.g., '100 m³ concrete' (if inspection was 100% of daily pour), '50m of rebar' (length checked), '120 bricks' (count of units), '60%' (portion of total), '3 cubes' (number of test samples), '5 of 10' (sample count)
COL_11Inspector Name / QC Engr. Name
Identity of person conducting inspection (Responsibility Tracking Standard)
Full name of QC engineer, site engineer, or inspector (e.g., 'Shri Rajesh Kumar', 'Ms. Priya Singh'). Used for accountability and skill tracking.
COL_12Remarks / Observations / Test Results
Additional details, numerical results, or notes (Documentation Standard)
e.g., 'Slump 110mm (criteria: 100±25mm) — OK'. 'Surface finish level variation 2.5mm in 3m length (criteria: ≤3mm) — OK'. 'Rebar spacing found 165mm, design 150mm (tolerance: ±10mm) — Marginal, escalate'. 'Compression test: 31 MPa (criteria: ≥30 MPa) — PASS'. 'Honeycombing observed, ~0.3 m² area'. 'Weather: 28°C, clear, dry'.
COL_13Hold Point Released? (Y/N) — Release Details
Track hold point resolution (Hold Point Management Standard)
If inspection was a hold point: Y/N. If released, enter: Released by (name), approval date, approval number. If not released: Reason pending, expected release date. Allows tracking of work blockages.
SUMMARY. Daily / Weekly Summary Statistics
SUMMARY_01Total Inspections Conducted
Count of all inspection entries in this log (Activity Tracking Standard)
e.g., 'Day 1: 12 inspections', 'Week 1: 58 inspections', 'Month: 240 inspections'
SUMMARY_02Passed (OK) Count
Number of inspections with OK status (Pass Rate Tracking Standard)
e.g., '11 passed', '58 passed', '95% pass rate' (calculated as OK count / Total inspections)
SUMMARY_03Non-Conformance (NC) Count
Number of inspections with NC status (Failure Tracking Standard)
e.g., '1 NC found', '3 NCs raised', 'NCR-001, NCR-002, NCR-003' (list NCR numbers)
SUMMARY_04Hold Points Count (Open / Released)
Number of hold points identified and their status (Hold Point Management Standard)
e.g., 'Total hold points: 4. Released: 2, Pending: 2', 'All 3 hold points from yesterday released today'
SUMMARY_05Not Applicable (NA) Count
Number of NA inspections (Activity Tracking Standard)
e.g., 'NA: 2 (batch found unsuitable, testing skipped)', 'NA: 0 (all activities applicable)'
SUMMARY_06Conditional Approvals Count (if any)
Minor deviations accepted by authority (Approval Tracking Standard)
e.g., 'Conditional: 1 (Plaster finish approved by Engr. X despite 4.2mm level variation, ref: APP-045)'
SUMMARY_07Trending / Key Observations
Notable patterns or concerns for management attention (Quality Trend Tracking Standard)
e.g., 'Concrete quality good — pass rate 95%. Rebar placement errors declining (3 issues past 2 weeks → 0 this week). Masonry finish still variable — consider additional training. No safety issues.' Or 'Week 1 pass rate: 85%. Week 2: 92%. Trend improving.'
Inspection Sign-Off
Log Completed — All inspections recorded accurately
Log Incomplete — Pending inspection entries (details below)
Review Required — Quality concerns identified, escalation recommended
Log Prepared By (QC Inspector / Engr. Name)
Name / Sign / Date
Signature
Name / Sign / Date
Reviewed By (QC In-charge / QC Manager)
Name / Sign / Date
Signature
Name / Sign / Date
Approved By (Consultant QC Representative — if required)
Name / Sign / Date
Signature
Name / Sign / Date
Comments / Action Items for Next Day
Name / Sign / Date