QA/QC  › Flooring & Finishing  › Flooring Works ITP
Plan · QC-FLR-PLN-001
Flooring Works ITP
24 checkpoints across 5 sections. Before flooring works commence; covers entire flooring phase from substrate to handover
24 Checkpoints
5 Sections
One ITP per project; updated if scope changes
QC Engineer, Engineer-in-Charge

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. INSPECTION HOLD POINTS
A1HOLD POINT 1: Substrate Preparation & Levelling
Acceptance: Level variation ≤5 mm in 3 m; compaction ≥95% SPD; cleanliness verified; moisture ≤8%
Inspect base and levelling course before tile laying
OK
NC
NA
HOLD
A2HOLD POINT 2: Material Approval (Tiles, Adhesive, Grout)
Acceptance: Test certificates received; batches approved; approved samples on site
Verify material quality before use
OK
NC
NA
HOLD
A3HOLD POINT 3: Tile Laying & Adhesion (First 50 m²)
Acceptance: Alignment ±2 mm/m, joints ±1 mm, pull-off ≥2.0 MPa; proceed if passed
Pilot check on initial layout before full-scale production
OK
NC
NA
HOLD
A4HOLD POINT 4: Adhesive Curing & Joint Cleaning
Acceptance: Minimum 48 hrs since laying; joints cleaned of adhesive; tiles stable
Verify adhesive set before grouting
OK
NC
NA
HOLD
A5HOLD POINT 5: Grouting Completion
Acceptance: Joints fully filled, no voids, uniform finish, excess removed, surface clean
Inspect grout quality before curing period
OK
NC
NA
HOLD
A6HOLD POINT 6: Final Inspection & Acceptance
Acceptance: All QC tests passed, no defects, slip resistance verified, documentation complete
Comprehensive final check before handover
OK
NC
NA
HOLD
B. TEST & INSPECTION SCHEDULE
B1Daily Substrate Inspection (Straightedge, Level, Cleanliness)
Acceptance: Flatness ±5 mm in 3 m; dust-free surface; no cracks >2 mm
Ongoing monitoring during substrate preparation
OK
NC
NA
HOLD
B2Daily Tile Laying Inspection (Alignment, Levelness, Joint Check)
Acceptance: Variation ≤2 mm in 1 m length; joint width ±1 mm; no lippage
Monitor laying quality each day
OK
NC
NA
HOLD
B3Pull-Off Adhesion Testing (Minimum 5 per 100 m²)
Acceptance: Average ≥2.0 MPa; minimum 4/5 samples pass; failures <1.5 MPa noted
Verify bond strength during laying phase
OK
NC
NA
HOLD
B4Grouting Inspection (Joint Fill, Surface Finish Quality)
Acceptance: Joints fully filled, uniform color, flush finish, no voids or cracks
Monitor grouting phase
OK
NC
NA
HOLD
B5Slip Resistance Testing (If Required)
Acceptance: PTV ≥36 dry, ≥24 wet (or R9+ classification per DIN 51130)
Safety verification for wet areas
OK
NC
NA
HOLD
B6Water Absorption Testing (Tile Batch Verification)
Acceptance: Absorption ≤10% for vitrified, ≤20% for ceramic; per IS standard
Confirm material specifications before laying
OK
NC
NA
HOLD
C. ACCEPTANCE CRITERIA
C1Substrate Acceptance
Acceptance: Flatness ±5 mm/3 m, compaction ≥95% SPD, moisture ≤8%, clean surface
Substrate must meet specifications for tiling
OK
NC
NA
HOLD
C2Tile Laying Acceptance
Acceptance: Level ±2 mm/m, joint ±1 mm, adhesion ≥2.0 MPa, no visible defects
Tiles properly placed with adequate adhesion
OK
NC
NA
HOLD
C3Grouting Acceptance
Acceptance: Joints fully filled, uniform finish, flush with tiles, no cracks, clean surface
Grout application and finish meets standard
OK
NC
NA
HOLD
C4Final Surface Acceptance
Acceptance: No visible defects, slip resistance verified, uniform appearance, ready for use
Overall floor appearance and functionality
OK
NC
NA
HOLD
Showing 16 of 24 checkpoints ·
A. INSPECTION HOLD POINTS
A1HOLD POINT 1: Substrate Preparation & Levelling
Inspect base and levelling course before tile laying (IS 1237)
Level variation ≤5 mm in 3 m; compaction ≥95% SPD; cleanliness verified; moisture ≤8%
OKNCNAHOLD
A2HOLD POINT 2: Material Approval (Tiles, Adhesive, Grout)
Verify material quality before use (IS 1237)
Test certificates received; batches approved; approved samples on site
OKNCNAHOLD
A3HOLD POINT 3: Tile Laying & Adhesion (First 50 m²)
Pilot check on initial layout before full-scale production (IS 1237)
Alignment ±2 mm/m, joints ±1 mm, pull-off ≥2.0 MPa; proceed if passed
OKNCNAHOLD
A4HOLD POINT 4: Adhesive Curing & Joint Cleaning
Verify adhesive set before grouting (IS 1237)
Minimum 48 hrs since laying; joints cleaned of adhesive; tiles stable
OKNCNAHOLD
A5HOLD POINT 5: Grouting Completion
Inspect grout quality before curing period (IS 1237)
Joints fully filled, no voids, uniform finish, excess removed, surface clean
OKNCNAHOLD
A6HOLD POINT 6: Final Inspection & Acceptance
Comprehensive final check before handover (IS 1237)
All QC tests passed, no defects, slip resistance verified, documentation complete
OKNCNAHOLD
B. TEST & INSPECTION SCHEDULE
B1Daily Substrate Inspection (Straightedge, Level, Cleanliness)
Ongoing monitoring during substrate preparation (IS 1237)
Flatness ±5 mm in 3 m; dust-free surface; no cracks >2 mm
OKNCNAHOLD
B2Daily Tile Laying Inspection (Alignment, Levelness, Joint Check)
Monitor laying quality each day (IS 1237)
Variation ≤2 mm in 1 m length; joint width ±1 mm; no lippage
OKNCNAHOLD
B3Pull-Off Adhesion Testing (Minimum 5 per 100 m²)
Verify bond strength during laying phase (IS 1237)
Average ≥2.0 MPa; minimum 4/5 samples pass; failures <1.5 MPa noted
OKNCNAHOLD
B4Grouting Inspection (Joint Fill, Surface Finish Quality)
Monitor grouting phase (IS 1237)
Joints fully filled, uniform color, flush finish, no voids or cracks
OKNCNAHOLD
B5Slip Resistance Testing (If Required)
Safety verification for wet areas (IS 1237)
PTV ≥36 dry, ≥24 wet (or R9+ classification per DIN 51130)
OKNCNAHOLD
B6Water Absorption Testing (Tile Batch Verification)
Confirm material specifications before laying (IS 1237)
Absorption ≤10% for vitrified, ≤20% for ceramic; per IS standard
OKNCNAHOLD
C. ACCEPTANCE CRITERIA
C1Substrate Acceptance
Substrate must meet specifications for tiling (IS 1237)
Flatness ±5 mm/3 m, compaction ≥95% SPD, moisture ≤8%, clean surface
OKNCNAHOLD
C2Tile Laying Acceptance
Tiles properly placed with adequate adhesion (IS 1237)
Level ±2 mm/m, joint ±1 mm, adhesion ≥2.0 MPa, no visible defects
OKNCNAHOLD
C3Grouting Acceptance
Grout application and finish meets standard (IS 1237)
Joints fully filled, uniform finish, flush with tiles, no cracks, clean surface
OKNCNAHOLD
C4Final Surface Acceptance
Overall floor appearance and functionality (IS 1237)
No visible defects, slip resistance verified, uniform appearance, ready for use
OKNCNAHOLD
Showing 16 of 24 ·
Inspection Sign-Off
APPROVED FOR EXECUTION
APPROVED WITH MODIFICATIONS
REJECTED
ITP Overview
Name / Sign / Date
Key Testing Points
Name / Sign / Date
Sampling Plan
Name / Sign / Date
Contractor Representative
Name / Sign / Date
QC Engineer Name
Name / Sign / Date
Engineer-in-Charge
Name / Sign / Date