BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVE
QA/QC  › Flooring & Finishing  › Flooring Method Statement
Form · QC-FLR-FRM-001
Flooring Method Statement
28 checkpoints across 7 sections. Before flooring works commence; reviewed and approved at project kickoff
28 Checkpoints
7 Sections
One per project; revised if major changes to scope/methodology
QC Engineer, Contractor

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. PROJECT OVERVIEW & SCOPE
A1Scope of Work Description
Acceptance: Detailed description of areas, types, square meters
Clear definition of flooring work extent
OK
NC
NA
HOLD
A2Project Timeline (Phasing, Start/Completion Dates)
Acceptance: Phases defined per area; critical milestones identified
Establish schedule for execution
OK
NC
NA
HOLD
A3Applicable Standards and Codes Referenced
Acceptance: IS codes, design specifications, client standards listed
Document regulatory framework
OK
NC
NA
HOLD
B. MATERIALS & SPECIFICATIONS
B1Tile Specifications (Type, Size, Color, Grade, Source)
Acceptance: Manufacturer, batch sourcing, test certificates, approval sample
Define tile quality and sourcing
OK
NC
NA
HOLD
B2Adhesive Type (cement-based, epoxy, hybrid) with Brand and Data Sheet
Acceptance: Brand, batch control, pot life, curing time, coverage rate documented
Specify adhesive performance and compatibility
OK
NC
NA
HOLD
B3Grout Type (color, brand, properties per IS code)
Acceptance: Type (cement/epoxy/urethane), color, strength grade, curing period
Define grout characteristics
OK
NC
NA
HOLD
B4Substrate Material (concrete grade, levelling course composition)
Acceptance: Concrete grade, levelling mortar ratio, compaction requirements
Specify substrate requirements
OK
NC
NA
HOLD
C. EQUIPMENT & TOOLS
C1Mixing Equipment (capacity, type for adhesive/grout)
Acceptance: Mechanical mixer specified; batch capacity >10 kg recommended
Ensure uniform material preparation
OK
NC
NA
HOLD
C2Application Tools (notched trowels size, floats, squeegees)
Acceptance: Trowel sizes: 6-10 mm for tiles; grout float specified
Define tools for proper material application
OK
NC
NA
HOLD
C3Leveling and Alignment Tools (straightedge, spirit level, laser level)
Acceptance: 3 m straightedge, spirit level, tile spacers, grout spacers available
Ensure precision in tile placement
OK
NC
NA
HOLD
C4Testing Equipment (pull-off adhesion tester, moisture meter, scales)
Acceptance: Pull-off tester, moisture meter (≤8%), calibrated scales on site
Specify QC testing instruments
OK
NC
NA
HOLD
Showing 11 of 28 checkpoints ·
A. PROJECT OVERVIEW & SCOPE
A1Scope of Work Description
Clear definition of flooring work extent (IS 1237)
Detailed description of areas, types, square meters
OKNCNAHOLD
A2Project Timeline (Phasing, Start/Completion Dates)
Establish schedule for execution (IS 1237)
Phases defined per area; critical milestones identified
OKNCNAHOLD
A3Applicable Standards and Codes Referenced
Document regulatory framework (IS 1237)
IS codes, design specifications, client standards listed
OKNCNAHOLD
B. MATERIALS & SPECIFICATIONS
B1Tile Specifications (Type, Size, Color, Grade, Source)
Define tile quality and sourcing (IS 1237)
Manufacturer, batch sourcing, test certificates, approval sample
OKNCNAHOLD
B2Adhesive Type (cement-based, epoxy, hybrid) with Brand and Data Sheet
Specify adhesive performance and compatibility (IS 1237)
Brand, batch control, pot life, curing time, coverage rate documented
OKNCNAHOLD
B3Grout Type (color, brand, properties per IS code)
Define grout characteristics (IS 1237)
Type (cement/epoxy/urethane), color, strength grade, curing period
OKNCNAHOLD
B4Substrate Material (concrete grade, levelling course composition)
Specify substrate requirements (IS 1237)
Concrete grade, levelling mortar ratio, compaction requirements
OKNCNAHOLD
C. EQUIPMENT & TOOLS
C1Mixing Equipment (capacity, type for adhesive/grout)
Ensure uniform material preparation (IS 1237)
Mechanical mixer specified; batch capacity >10 kg recommended
OKNCNAHOLD
C2Application Tools (notched trowels size, floats, squeegees)
Define tools for proper material application (IS 1237)
Trowel sizes: 6-10 mm for tiles; grout float specified
OKNCNAHOLD
C3Leveling and Alignment Tools (straightedge, spirit level, laser level)
Ensure precision in tile placement (IS 1237)
3 m straightedge, spirit level, tile spacers, grout spacers available
OKNCNAHOLD
C4Testing Equipment (pull-off adhesion tester, moisture meter, scales)
Specify QC testing instruments (IS 1237)
Pull-off tester, moisture meter (≤8%), calibrated scales on site
OKNCNAHOLD
Showing 11 of 28 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED
Summary of Method
Name / Sign / Date
Key Quality Parameters
Name / Sign / Date
Contractor Representative Name
Name / Sign / Date
QC Engineer Name
Name / Sign / Date
Engineer-in-Charge Name
Name / Sign / Date

More related