Plan · QC-ELC-PLN-001
Electrical Installation ITP
25 checkpoints across 8 sections. At project start; guides all inspection, testing, and approval activities throughout electrical installation
25 Checkpoints
8 Sections
One per project
QC Engineer, Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
ACTIVITY_1. Phase 1: Earth System Installation
1.1Earth pit excavation and preparation (pit dimensions, backfill material sourcing)
Acceptance: Pit excavated to depth, charcoal-salt backfill prepared, ready for electrode insertion
Completion of earth pit construction per IS 3043
OK
NC
NA
HOLD
1.2WITNESS POINT: Earth electrode insertion and bonding (QC must witness electrode driving)
Acceptance: Electrode driven vertically without bending, connections bolted, location marked on site plan
Earth electrode installation witnessed by QC
OK
NC
NA
HOLD
1.3Earth conductor routing from pit to DB (conduit/tray protection, earthing continuity verification)
Acceptance: Conductor routed and protected, continuity test performed ≤ 0.5 Ω, test report filed
Earth conductor installation and testing (≤ 0.5 Ω per 10 m)
OK
NC
NA
HOLD
1.4HOLD POINT: Earth resistance measurement (earthing system cannot be covered/backfilled until test approved)
Acceptance: Earth megger test ≤ 5 Ω, test report signed by QC, pit cover installation approved
Earth resistance test result ≤ 5 Ω approval required before pit cover installation
OK
NC
NA
HOLD
ACTIVITY_2. Phase 2: Conduit & Cable Tray Installation
2.1Conduit/cable tray routing layout verification (against design drawings; no clashes with structure/MEP)
Acceptance: Route verified on site, no structural/MEP clashes, changes documented if any, approved before installation
Route co-ordination and approval by Site Engineer
OK
NC
NA
HOLD
2.2Conduit/tray installation and support verification (spacing ≤ 1.5 m, bolts tight, no movement)
Acceptance: Support spacing verified ≤ 1.5 m, bolts torque-checked, no deflection/sagging, QC sign-off obtained
Visual inspection and QC approval of installed conduit/tray
OK
NC
NA
HOLD
2.3Unused conduit/tray entry sealing (to prevent pest/moisture ingress before cable laying)
Acceptance: Blanking plugs or caps fitted, visual confirmation, ready for cable laying
All unused entries sealed before cable installation
OK
NC
NA
HOLD
ACTIVITY_3. Phase 3: Cable Laying & Installation
3.1Cable laying method statement review and approval before work starts (routing, spacing, bend radius, protection)
Acceptance: Method statement submitted, reviewed, approved, and signed before cable laying commences
Method statement approved by QC/Site Engineer
OK
NC
NA
HOLD
3.2WITNESS POINT: Cable laying in conduit/tray (QC to witness cable handling, bend radius, arrangement, no damage)
Acceptance: QC witnesses cable laid per method statement, bend radius ≥ 6D, arrangement correct, no damage observed
QC inspection and witness of cable laying process
OK
NC
NA
HOLD
3.3Cable color-coding and labeling applied at all connection points (phase/neutral/earth identification)
Acceptance: Color coding applied (brown/red/black/green), labels affixed, matching circuit schedule, QC verified
All cables color-coded and labeled per IS 732
OK
NC
NA
HOLD
3.4Excess cable coiling and securing (radius ≥ 6D, secured with non-corrosive ties every 0.5 m)
Acceptance: Excess cable coiled with radius ≥ 6D, secured neatly, no kinks or damage, site-clean appearance maintained
Proper cable storage at outlets/DB
OK
NC
NA
HOLD
Showing 11 of 25 checkpoints ·
ACTIVITY_1. Phase 1: Earth System Installation
1.1Earth pit excavation and preparation (pit dimensions, backfill material sourcing)
Completion of earth pit construction per IS 3043 (IS 3043)
Pit excavated to depth, charcoal-salt backfill prepared, ready for electrode insertion
OKNCNAHOLD
1.2WITNESS POINT: Earth electrode insertion and bonding (QC must witness electrode driving)
Earth electrode installation witnessed by QC (IS 3043)
Electrode driven vertically without bending, connections bolted, location marked on site plan
OKNCNAHOLD
1.3Earth conductor routing from pit to DB (conduit/tray protection, earthing continuity verification)
Earth conductor installation and testing (≤ 0.5 Ω per 10 m) (IS 3043)
Conductor routed and protected, continuity test performed ≤ 0.5 Ω, test report filed
OKNCNAHOLD
1.4HOLD POINT: Earth resistance measurement (earthing system cannot be covered/backfilled until test approved)
Earth resistance test result ≤ 5 Ω approval required before pit cover installation (IS 3043)
Earth megger test ≤ 5 Ω, test report signed by QC, pit cover installation approved
OKNCNAHOLD
ACTIVITY_2. Phase 2: Conduit & Cable Tray Installation
2.1Conduit/cable tray routing layout verification (against design drawings; no clashes with structure/MEP)
Route co-ordination and approval by Site Engineer (IS 732)
Route verified on site, no structural/MEP clashes, changes documented if any, approved before installation
OKNCNAHOLD
2.2Conduit/tray installation and support verification (spacing ≤ 1.5 m, bolts tight, no movement)
Visual inspection and QC approval of installed conduit/tray (IS 732)
Support spacing verified ≤ 1.5 m, bolts torque-checked, no deflection/sagging, QC sign-off obtained
OKNCNAHOLD
2.3Unused conduit/tray entry sealing (to prevent pest/moisture ingress before cable laying)
All unused entries sealed before cable installation (IS 732)
Blanking plugs or caps fitted, visual confirmation, ready for cable laying
OKNCNAHOLD
ACTIVITY_3. Phase 3: Cable Laying & Installation
3.1Cable laying method statement review and approval before work starts (routing, spacing, bend radius, protection)
Method statement approved by QC/Site Engineer (IS 732)
Method statement submitted, reviewed, approved, and signed before cable laying commences
OKNCNAHOLD
3.2WITNESS POINT: Cable laying in conduit/tray (QC to witness cable handling, bend radius, arrangement, no damage)
QC inspection and witness of cable laying process (IS 732)
QC witnesses cable laid per method statement, bend radius ≥ 6D, arrangement correct, no damage observed
OKNCNAHOLD
3.3Cable color-coding and labeling applied at all connection points (phase/neutral/earth identification)
All cables color-coded and labeled per IS 732 (IS 732)
Color coding applied (brown/red/black/green), labels affixed, matching circuit schedule, QC verified
OKNCNAHOLD
3.4Excess cable coiling and securing (radius ≥ 6D, secured with non-corrosive ties every 0.5 m)
Proper cable storage at outlets/DB (IS 732)
Excess cable coiled with radius ≥ 6D, secured neatly, no kinks or damage, site-clean appearance maintained
OKNCNAHOLD
Showing 11 of 25 ·
Inspection Sign-Off
ITP APPROVED
ITP APPROVED WITH MODIFICATIONS
ITP REJECTED — REVISE
ITP Prepared By
Name / Sign / Date
Reviewed By (QC Engineer)
Name / Sign / Date
Approved By (Site Engineer)
Name / Sign / Date