BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVE
QA/QC  › Waterproofing  › Waterproofing Application Method
Form · QC-WPF-FRM-001
Waterproofing Application Method Statement
29 checkpoints across 9 sections. Before waterproofing work starts; required contractual document
29 Checkpoints
9 Sections
Once per project or section; updated if significant changes required
Contractor, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
1. SCOPE & OBJECTIVES
1.1Scope: Define areas to be waterproofed (zones, rooms, structures); total area in m²
Acceptance: Clear identification of building/floor/zones; total area quantified; high-risk areas identified
Cl. 401 — Scope definition
1.2Objectives: State waterproofing standard, durability target, performance requirements
Acceptance: IS 2645 compliance; 10-20 year durability typical; zero seepage target; flood test mandatory
Cl. 401 — Goal setting
2. MATERIALS & SPECIFICATION
2.1Waterproofing product: Type (liquid/sheet), brand, grade, approval; supplier & test certs
Acceptance: Approved waterproofing system; test certificates <6 months old; storage/shelf-life confirmed
Cl. 401 — Material approval
2.2Primer/Bonding Agent: Type, consumption rate (kg/m²), drying time specification
Acceptance: Primer consumption 0.5 kg/m² typical; drying 24-48 hrs before main coat; compatibility confirmed
Cl. 401 — Primer specification
2.3Application rate: Liquid (kg/m² per coat) or sheet (weight/area); total DFT target
Acceptance: Liquid: 1-1.5 kg/m² 1st coat, 0.5-1.5 kg/m² 2nd coat; total DFT ≥2.5mm typical
Cl. 401 — Application specification
2.4Quality Standard: IS 2645 compliance; zero-seepage requirement; flood test protocol
Acceptance: All materials and procedures conform to IS 2645; flood test 72 hours minimum
Cl. 401 — Standard compliance
3. EQUIPMENT & TOOLS
3.1Application equipment: Spray gun, roller, brush type/condition; calibration verified
Acceptance: Spray gun: 2-3 bar pressure, 0.3-0.5m fan width; roller: 10mm nap; brush: synthetic, lint-free
Cl. 401 — Equipment specification
3.2Measuring equipment: Scales (material weight), measuring tape (area), thickness gauge (DFT)
Acceptance: Scales calibrated ±2%; measuring tape certified; DFT gauge calibrated ±25 microns
Cl. 401 — Measurement tools
3.3Environmental monitoring: Thermometer (air/substrate), hygrometer (humidity), barometer
Acceptance: Thermometer ±1°C; hygrometer ±5%; monitoring 2x daily minimum
Cl. 401 — Environmental control
Showing 9 of 29 checkpoints ·
1. SCOPE & OBJECTIVES
1.1Scope: Define areas to be waterproofed (zones, rooms, structures); total area in m²
Cl. 401 — Scope definition (IS 2645)
Clear identification of building/floor/zones; total area quantified; high-risk areas identified
1.2Objectives: State waterproofing standard, durability target, performance requirements
Cl. 401 — Goal setting (IS 2645)
IS 2645 compliance; 10-20 year durability typical; zero seepage target; flood test mandatory
2. MATERIALS & SPECIFICATION
2.1Waterproofing product: Type (liquid/sheet), brand, grade, approval; supplier & test certs
Cl. 401 — Material approval (IS 2645)
Approved waterproofing system; test certificates <6 months old; storage/shelf-life confirmed
2.2Primer/Bonding Agent: Type, consumption rate (kg/m²), drying time specification
Cl. 401 — Primer specification (IS 2645)
Primer consumption 0.5 kg/m² typical; drying 24-48 hrs before main coat; compatibility confirmed
2.3Application rate: Liquid (kg/m² per coat) or sheet (weight/area); total DFT target
Cl. 401 — Application specification (IS 2645)
Liquid: 1-1.5 kg/m² 1st coat, 0.5-1.5 kg/m² 2nd coat; total DFT ≥2.5mm typical
2.4Quality Standard: IS 2645 compliance; zero-seepage requirement; flood test protocol
Cl. 401 — Standard compliance (IS 2645)
All materials and procedures conform to IS 2645; flood test 72 hours minimum
3. EQUIPMENT & TOOLS
3.1Application equipment: Spray gun, roller, brush type/condition; calibration verified
Cl. 401 — Equipment specification (IS 2645)
Spray gun: 2-3 bar pressure, 0.3-0.5m fan width; roller: 10mm nap; brush: synthetic, lint-free
3.2Measuring equipment: Scales (material weight), measuring tape (area), thickness gauge (DFT)
Cl. 401 — Measurement tools (IS 2645)
Scales calibrated ±2%; measuring tape certified; DFT gauge calibrated ±25 microns
3.3Environmental monitoring: Thermometer (air/substrate), hygrometer (humidity), barometer
Cl. 401 — Environmental control (IS 2645)
Thermometer ±1°C; hygrometer ±5%; monitoring 2x daily minimum
Showing 9 of 29 ·
Inspection Sign-Off
APPROVED
APPROVED WITH MODIFICATIONS
REJECTED
Prepared By
Name / Sign / Date

More related