QA/QC  › Reports & Site Diary  › Weekly Progress Report
Register · QC-RPT-REG-002
Weekly Progress Report (WPR)
18 checkpoints across 8 sections. Every Monday (or first working day) for the previous week's progress; submitted to client / PMC
18 Checkpoints
8 Sections
Weekly
Project Manager, Planning Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. PROGRESS SUMMARY AND S-CURVE
A1Record cumulative planned vs actual progress (%) at end of week
Acceptance: Planned %, Actual %, Variance (+/-) calculated; S-curve updated
Cl. 9.1 — Monitoring
OK
NC
NA
HOLD
A2List physical quantities executed during the week with cumulative to date
Acceptance: Major BOQ items listed; weekly and cumulative quantities consistent with DPRs
Cl. 8.5 — Production
OK
NC
NA
HOLD
A3Record critical path status and any slippage on schedule-critical activities
Acceptance: Critical activities identified; slippage days reported; recovery plan stated
Cl. 6.1 — Risks
OK
NC
NA
HOLD
B. MAJOR ACTIVITIES COMPLETED DURING WEEK
B1List key milestones achieved during the week by block / WBS area
Acceptance: Milestones with dates; photographs attached for significant ones
Cl. 4.3 — Record
OK
NC
NA
HOLD
B2Summarize concrete pours, structural elements completed, finishing area turnover
Acceptance: Pour numbers and quantities; floor turn-over with date; snagging status
Cl. 8.5 — Output
OK
NC
NA
HOLD
C. LOOK-AHEAD: NEXT 2-WEEK PLAN
C1List activities planned for next 2 weeks with target quantities and resources
Acceptance: Activities with start/finish dates; resources allocated; pre-requisites identified
Cl. 6.2 — Planning
OK
NC
NA
HOLD
C2Identify constraints, permits, approvals, or material needs for next 2 weeks
Acceptance: Open RFIs, pending drawings, permit status tracked; owner assigned
Cl. 6.1 — Constraints
OK
NC
NA
HOLD
Showing 7 of 18 checkpoints ·
A. PROGRESS SUMMARY AND S-CURVE
A1Record cumulative planned vs actual progress (%) at end of week
Cl. 9.1 — Monitoring (ISO 9001)
Planned %, Actual %, Variance (+/-) calculated; S-curve updated
OKNCNAHOLD
A2List physical quantities executed during the week with cumulative to date
Cl. 8.5 — Production (ISO 9001)
Major BOQ items listed; weekly and cumulative quantities consistent with DPRs
OKNCNAHOLD
A3Record critical path status and any slippage on schedule-critical activities
Cl. 6.1 — Risks (ISO 9001)
Critical activities identified; slippage days reported; recovery plan stated
OKNCNAHOLD
B. MAJOR ACTIVITIES COMPLETED DURING WEEK
B1List key milestones achieved during the week by block / WBS area
Cl. 4.3 — Record (NBC 2016)
Milestones with dates; photographs attached for significant ones
OKNCNAHOLD
B2Summarize concrete pours, structural elements completed, finishing area turnover
Cl. 8.5 — Output (ISO 9001)
Pour numbers and quantities; floor turn-over with date; snagging status
OKNCNAHOLD
C. LOOK-AHEAD: NEXT 2-WEEK PLAN
C1List activities planned for next 2 weeks with target quantities and resources
Cl. 6.2 — Planning (ISO 9001)
Activities with start/finish dates; resources allocated; pre-requisites identified
OKNCNAHOLD
C2Identify constraints, permits, approvals, or material needs for next 2 weeks
Cl. 6.1 — Constraints (ISO 9001)
Open RFIs, pending drawings, permit status tracked; owner assigned
OKNCNAHOLD
Showing 7 of 18 ·
Inspection Sign-Off
REVIEWED
ACTION REQUIRED
Remarks
Name / Sign / Date
Prepared By
Name / Sign / Date
Reviewed / Approved By
Name / Sign / Date