Daily Progress Report (DPR)
20 checkpoints across 8 sections. Every working day; submitted to client/PMC by end of day or start of next day
20 Checkpoints
8 Sections
Daily
Site Engineer, Project Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. REGISTER COLUMN DEFINITIONS — WORK PROGRESS LOG
A1Column 1: ACTIVITY ID / WBS CODE — unique reference from master programme
Acceptance: WBS code matches approved programme; traceability to master schedule maintained
Cl. 8.1 — Operational planning
OK
NC
NA
HOLD
A2Column 2: ACTIVITY DESCRIPTION — short description of work done today
Acceptance: Description clear, specific, and location-referenced (block/floor/grid)
Cl. 8.5 — Production control
OK
NC
NA
HOLD
A3Column 3: LOCATION / AREA — block, level, grid reference of work performed
Acceptance: Location precise; corresponds to approved drawing grid references
Cl. 4.3 — NBC site documentation
OK
NC
NA
HOLD
A4Column 4: QUANTITY TODAY — physical quantity executed (cu.m, sqm, tonnes, nos.)
Acceptance: Quantities measured per BOQ item unit; recorded to appropriate precision
Cl. 8.5 — Quantification
OK
NC
NA
HOLD
A5Column 5: CUMULATIVE QUANTITY & % COMPLETE — running total vs BOQ/target
Acceptance: Running total and % complete calculated and updated daily
Cl. 9.1 — Performance monitoring
OK
NC
NA
HOLD
A6Column 6: REMARKS — quality hold points, inspection calls, issues
Acceptance: Hold points, ITP inspections, NCRs, observations all noted with reference numbers
Cl. 7.5 — Documented information
OK
NC
NA
HOLD
B. MANPOWER DEPLOYMENT SUMMARY
B1Record total manpower by trade: engineers, supervisors, skilled, semi-skilled, unskilled
Acceptance: Each trade count entered; total reconciles with attendance register / biometric data
Cl. 7.1 — Resources
OK
NC
NA
HOLD
B2Record subcontractor-wise manpower separately from main contractor
Acceptance: Subcontractor names and headcount listed; signed by subcontractor supervisor
Cl. 8.4 — Externally provided
OK
NC
NA
HOLD
C. PLANT & EQUIPMENT DEPLOYMENT
C1Record plant deployed today with make, capacity, and hours used / idle
Acceptance: Each major plant item listed; running hours captured from hour-meter / log sheet
Cl. 4.3 — Plant records
OK
NC
NA
HOLD
C2Record any plant breakdown, cause, duration, and impact on progress
Acceptance: Breakdown root cause and corrective action noted; delay hours quantified
Cl. 10 — Improvement
OK
NC
NA
HOLD
Showing 10 of 20 checkpoints ·
A. REGISTER COLUMN DEFINITIONS — WORK PROGRESS LOG
A1Column 1: ACTIVITY ID / WBS CODE — unique reference from master programme
Cl. 8.1 — Operational planning (ISO 9001)
WBS code matches approved programme; traceability to master schedule maintained
OKNCNAHOLD
A2Column 2: ACTIVITY DESCRIPTION — short description of work done today
Cl. 8.5 — Production control (ISO 9001)
Description clear, specific, and location-referenced (block/floor/grid)
OKNCNAHOLD
A3Column 3: LOCATION / AREA — block, level, grid reference of work performed
Cl. 4.3 — NBC site documentation (NBC 2016)
Location precise; corresponds to approved drawing grid references
OKNCNAHOLD
A4Column 4: QUANTITY TODAY — physical quantity executed (cu.m, sqm, tonnes, nos.)
Cl. 8.5 — Quantification (ISO 9001)
Quantities measured per BOQ item unit; recorded to appropriate precision
OKNCNAHOLD
A5Column 5: CUMULATIVE QUANTITY & % COMPLETE — running total vs BOQ/target
Cl. 9.1 — Performance monitoring (ISO 9001)
Running total and % complete calculated and updated daily
OKNCNAHOLD
A6Column 6: REMARKS — quality hold points, inspection calls, issues
Cl. 7.5 — Documented information (ISO 9001)
Hold points, ITP inspections, NCRs, observations all noted with reference numbers
OKNCNAHOLD
B. MANPOWER DEPLOYMENT SUMMARY
B1Record total manpower by trade: engineers, supervisors, skilled, semi-skilled, unskilled
Cl. 7.1 — Resources (ISO 9001)
Each trade count entered; total reconciles with attendance register / biometric data
OKNCNAHOLD
B2Record subcontractor-wise manpower separately from main contractor
Cl. 8.4 — Externally provided (ISO 9001)
Subcontractor names and headcount listed; signed by subcontractor supervisor
OKNCNAHOLD
C. PLANT & EQUIPMENT DEPLOYMENT
C1Record plant deployed today with make, capacity, and hours used / idle
Cl. 4.3 — Plant records (NBC 2016)
Each major plant item listed; running hours captured from hour-meter / log sheet
OKNCNAHOLD
C2Record any plant breakdown, cause, duration, and impact on progress
Cl. 10 — Improvement (ISO 9001)
Breakdown root cause and corrective action noted; delay hours quantified
OKNCNAHOLD