S.No.CheckpointIS RequirementStatus
A. PIPE MATERIAL & CERTIFICATION
A1Pipe material is certified (ISI mark or equivalent); invoice/certificate matches pipe specifications
Acceptance: ISI mark visible on pipe, test certificate provided, material type matches design drawings, diameter/pressure verified
Cl. 3.1 — Material certification
OK
NC
NA
HOLD
A2Pipe is not dented, cracked, or deformed; no visible damage or defects
Acceptance: Pipe surface smooth, no dents > 2mm depth, no cracks or discoloration, ISI mark intact
Cl. 4.1 — Physical condition
OK
NC
NA
HOLD
A3Pipe coating/interior lining intact and free from corrosion (for GI/MS pipes)
Acceptance: GI coating continuous, no rust/pitting visible, internal coating applied if required, no bare metal exposed
Cl. 5.2 — Coating protection
OK
NC
NA
HOLD
B. TRENCH PREPARATION & LAYING
B1Trench bottom is firm, leveled, and free from sharp objects; minimum cushioning layer 100 mm sand/gravel provided
Acceptance: Trench bottom compacted (soft spots removed), 100 mm sand cushion layer installed, no sharp stones
Cl. 6.1 — Trench preparation
OK
NC
NA
HOLD
B2Pipe is laid on sand cushion; gradient/slope is as per design (typically 1:100 to 1:200 for horizontal runs)
Acceptance: Pipe gradient checked with level/theodolite, slope within design range, documented on as-laid drawing
Cl. 6.2 — Gradient design
OK
NC
NA
HOLD
B3Pipe depth is minimum 0.75 m below finished ground level (to avoid freeze-thaw and surface damage)
Acceptance: Measured depth ≥ 0.75 m from FGL, documented with depths at key points, recorded on as-laid drawing
Cl. 6.3 — Burial depth
OK
NC
NA
HOLD
B4Pipe spacing from parallel lines maintained: min. 0.3 m from sewerage, 0.5 m from electrical/gas underground
Acceptance: Clearances verified on site with measuring tape, non-crossing layout confirmed, parallel routing ≥ 0.3 m apart
Cl. 7.1 — Service co-ordination
OK
NC
NA
HOLD
B5Pipe is not laid under/over structures or in corrosive soils without protection (chemical analysis if required)
Acceptance: Layout avoids structures, corrosive soils analyzed if suspected, wrapping/coating applied per requirement
Cl. 7.2 — Environmental protection
OK
NC
NA
HOLD
C. PIPE SUPPORT & PROTECTION
C1Support layer (sand + fine gravel) placed over pipe, minimum 150 mm thickness before backfill
Acceptance: Support layer 150 mm thick, compacted properly, free from large stones, even distribution along pipe
Cl. 6.4 — Support layer
OK
NC
NA
HOLD
C2Backfill material is suitable (soil without stones >50 mm); compacted in layers of 200 mm maximum
Acceptance: Backfill material free from large stones/debris, compacted in 200 mm layers, compaction degree 90% standard Proctor
Cl. 6.5 — Backfill and compaction
OK
NC
NA
HOLD
C3Above-ground pipe runs protected with insulation jacket (if exposed to sun/temperature); support brackets at 1.5-2.0 m intervals
Acceptance: Insulation jacket applied on exposed runs, UV protection provided, support brackets bolted securely at ≤ 2.0 m spacing
Cl. 8.1 — Above-ground protection
OK
NC
NA
HOLD
C4In freeze-prone areas, pipe is buried below frost line or insulated (consult local frost depth)
Acceptance: Pipe depth ≥ frost line depth (if applicable), OR thermal insulation applied with R-value per design, documented
Cl. 9.1 — Freeze protection
OK
NC
NA
HOLD
Showing 12 of 20 checkpoints ·
A. PIPE MATERIAL & CERTIFICATION
A1Pipe material is certified (ISI mark or equivalent); invoice/certificate matches pipe specifications
Cl. 3.1 — Material certification (IS 2065)
ISI mark visible on pipe, test certificate provided, material type matches design drawings, diameter/pressure verified
OKNCNAHOLD
A2Pipe is not dented, cracked, or deformed; no visible damage or defects
Cl. 4.1 — Physical condition (IS 2065)
Pipe surface smooth, no dents > 2mm depth, no cracks or discoloration, ISI mark intact
OKNCNAHOLD
A3Pipe coating/interior lining intact and free from corrosion (for GI/MS pipes)
Cl. 5.2 — Coating protection (IS 1239)
GI coating continuous, no rust/pitting visible, internal coating applied if required, no bare metal exposed
OKNCNAHOLD
B. TRENCH PREPARATION & LAYING
B1Trench bottom is firm, leveled, and free from sharp objects; minimum cushioning layer 100 mm sand/gravel provided
Cl. 6.1 — Trench preparation (IS 2065)
Trench bottom compacted (soft spots removed), 100 mm sand cushion layer installed, no sharp stones
OKNCNAHOLD
B2Pipe is laid on sand cushion; gradient/slope is as per design (typically 1:100 to 1:200 for horizontal runs)
Cl. 6.2 — Gradient design (IS 2065)
Pipe gradient checked with level/theodolite, slope within design range, documented on as-laid drawing
OKNCNAHOLD
B3Pipe depth is minimum 0.75 m below finished ground level (to avoid freeze-thaw and surface damage)
Cl. 6.3 — Burial depth (IS 2065)
Measured depth ≥ 0.75 m from FGL, documented with depths at key points, recorded on as-laid drawing
OKNCNAHOLD
B4Pipe spacing from parallel lines maintained: min. 0.3 m from sewerage, 0.5 m from electrical/gas underground
Cl. 7.1 — Service co-ordination (IS 2065)
Clearances verified on site with measuring tape, non-crossing layout confirmed, parallel routing ≥ 0.3 m apart
OKNCNAHOLD
B5Pipe is not laid under/over structures or in corrosive soils without protection (chemical analysis if required)
Cl. 7.2 — Environmental protection (IS 2065)
Layout avoids structures, corrosive soils analyzed if suspected, wrapping/coating applied per requirement
OKNCNAHOLD
C. PIPE SUPPORT & PROTECTION
C1Support layer (sand + fine gravel) placed over pipe, minimum 150 mm thickness before backfill
Cl. 6.4 — Support layer (IS 2065)
Support layer 150 mm thick, compacted properly, free from large stones, even distribution along pipe
OKNCNAHOLD
C2Backfill material is suitable (soil without stones >50 mm); compacted in layers of 200 mm maximum
Cl. 6.5 — Backfill and compaction (IS 2065)
Backfill material free from large stones/debris, compacted in 200 mm layers, compaction degree 90% standard Proctor
OKNCNAHOLD
C3Above-ground pipe runs protected with insulation jacket (if exposed to sun/temperature); support brackets at 1.5-2.0 m intervals
Cl. 8.1 — Above-ground protection (IS 2065)
Insulation jacket applied on exposed runs, UV protection provided, support brackets bolted securely at ≤ 2.0 m spacing
OKNCNAHOLD
C4In freeze-prone areas, pipe is buried below frost line or insulated (consult local frost depth)
Cl. 9.1 — Freeze protection (IS 2065)
Pipe depth ≥ frost line depth (if applicable), OR thermal insulation applied with R-value per design, documented
OKNCNAHOLD
Showing 12 of 20 ·
Inspection Sign-Off
APPROVED FOR PRESSURE TEST
APPROVED WITH CONDITIONS
REJECTED — REWORK REQUIRED
Remarks
Name / Sign / Date
Inspected By
Name / Sign / Date
Reviewed By
Name / Sign / Date