QA/QC  › Plumbing & Water Supply  › Hydrostatic Pressure Test
Test-report · QC-PLB-TST-001
Hydrostatic Pressure Test Report
14 checkpoints across 4 sections. Before water supply system handover; mandatory quality test per IS 2065
14 Checkpoints
4 Sections
Per system section/phase
QC Engineer, Plumbing Supervisor

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. TEST PREPARATION & SETUP
A1All pipe joints and connections fully completed and cured (solvent welds aged minimum 2 hours at 20°C)
Acceptance: Cure time documented, solvent joint color uniform indicating full cure, visual inspection passed
Cl. 13.1 — Joint readiness
OK
NC
NA
HOLD
A2System is isolated; all open ends capped and sealed securely
Acceptance: Caps bolted/welded securely, pressure-tested separately before main system test, no leakage at caps
Cl. 13.2 — End sealing
OK
NC
NA
HOLD
A3Air vent points identified and opened; drain/sump point identified for evacuation after test
Acceptance: Vent locations marked on drawing, drain sump prepared, drain valve operational
Cl. 13.3 — Venting strategy
OK
NC
NA
HOLD
A4Pressure gauge (0-2.5 bar range minimum, accuracy ±2%) connected at lowest point of system
Acceptance: Gauge calibrated within 12 months, range adequate for test pressure, mounted at low point
Cl. 13.4 — Pressure measurement
OK
NC
NA
HOLD
B. PRESSURE BUILD-UP & STABILIZATION
B1Pressure increased in increments (0.2-0.3 bar every minute); no sudden pressure jumps
Acceptance: Pressure gauge reading every minute recorded, pressure increase gradual (no spikes), pump operated smoothly
Cl. 13.5 — Gradual pressurization
OK
NC
NA
HOLD
B2System stabilized at test pressure (1.5 × design) for 5-10 minutes before measuring leakage
Acceptance: Test pressure held steady for 10 minutes, pressure fluctuation ≤0.1 bar, gauge stable reading
Cl. 13.6 — Pressure stabilization
OK
NC
NA
HOLD
B3Initial system pressure recorded when stabilized; all leakage monitored from this baseline
Acceptance: Initial pressure recorded with time stamp, baseline pressure verified by second observer, documented
Cl. 13.7 — Baseline recording
OK
NC
NA
HOLD
C. LEAKAGE MONITORING & ACCEPTANCE
C1Pressure drop monitored for 30 minutes at test pressure; allowable leakage ≤0.5 bar drop (per 100 m pipeline)
Acceptance: Pressure readings taken every 5 minutes, drop ≤0.5 bar over 30 minutes recorded, table of readings prepared
Cl. 13.8 — Leakage limit
OK
NC
NA
HOLD
C2Visible leakage at any joint: ZERO seepage observed; water droplets or streams indicate failure
Acceptance: System visually inspected throughout test duration, all joints observed dry, no moisture or seepage noted
Cl. 13.9 — Visual inspection
OK
NC
NA
HOLD
C3If pressure drop exceeds 0.5 bar in 30 minutes: system FAILS test; fault location identified and repaired
Acceptance: If failed: depressurize system, locate leak (usually visible seeping), repair joint/connection, re-test
Cl. 13.10 — Failure procedure
OK
NC
NA
HOLD
C4System PASSES test if pressure drop ≤0.5 bar and zero visible leakage; test certificate issued
Acceptance: Pass verdict recorded, test certificate prepared and signed by QC engineer, system approved for service
Cl. 13.11 — Acceptance
OK
NC
NA
HOLD
Showing 11 of 14 checkpoints ·
A. TEST PREPARATION & SETUP
A1All pipe joints and connections fully completed and cured (solvent welds aged minimum 2 hours at 20°C)
Cl. 13.1 — Joint readiness (IS 2065)
Cure time documented, solvent joint color uniform indicating full cure, visual inspection passed
OKNCNAHOLD
A2System is isolated; all open ends capped and sealed securely
Cl. 13.2 — End sealing (IS 2065)
Caps bolted/welded securely, pressure-tested separately before main system test, no leakage at caps
OKNCNAHOLD
A3Air vent points identified and opened; drain/sump point identified for evacuation after test
Cl. 13.3 — Venting strategy (IS 2065)
Vent locations marked on drawing, drain sump prepared, drain valve operational
OKNCNAHOLD
A4Pressure gauge (0-2.5 bar range minimum, accuracy ±2%) connected at lowest point of system
Cl. 13.4 — Pressure measurement (IS 2065)
Gauge calibrated within 12 months, range adequate for test pressure, mounted at low point
OKNCNAHOLD
B. PRESSURE BUILD-UP & STABILIZATION
B1Pressure increased in increments (0.2-0.3 bar every minute); no sudden pressure jumps
Cl. 13.5 — Gradual pressurization (IS 2065)
Pressure gauge reading every minute recorded, pressure increase gradual (no spikes), pump operated smoothly
OKNCNAHOLD
B2System stabilized at test pressure (1.5 × design) for 5-10 minutes before measuring leakage
Cl. 13.6 — Pressure stabilization (IS 2065)
Test pressure held steady for 10 minutes, pressure fluctuation ≤0.1 bar, gauge stable reading
OKNCNAHOLD
B3Initial system pressure recorded when stabilized; all leakage monitored from this baseline
Cl. 13.7 — Baseline recording (IS 2065)
Initial pressure recorded with time stamp, baseline pressure verified by second observer, documented
OKNCNAHOLD
C. LEAKAGE MONITORING & ACCEPTANCE
C1Pressure drop monitored for 30 minutes at test pressure; allowable leakage ≤0.5 bar drop (per 100 m pipeline)
Cl. 13.8 — Leakage limit (IS 2065)
Pressure readings taken every 5 minutes, drop ≤0.5 bar over 30 minutes recorded, table of readings prepared
OKNCNAHOLD
C2Visible leakage at any joint: ZERO seepage observed; water droplets or streams indicate failure
Cl. 13.9 — Visual inspection (IS 2065)
System visually inspected throughout test duration, all joints observed dry, no moisture or seepage noted
OKNCNAHOLD
C3If pressure drop exceeds 0.5 bar in 30 minutes: system FAILS test; fault location identified and repaired
Cl. 13.10 — Failure procedure (IS 2065)
If failed: depressurize system, locate leak (usually visible seeping), repair joint/connection, re-test
OKNCNAHOLD
C4System PASSES test if pressure drop ≤0.5 bar and zero visible leakage; test certificate issued
Cl. 13.11 — Acceptance (IS 2065)
Pass verdict recorded, test certificate prepared and signed by QC engineer, system approved for service
OKNCNAHOLD
Showing 11 of 14 ·
Inspection Sign-Off
PASS
FAIL — RETEST REQUIRED
Remarks / Observations
Name / Sign / Date
Tested By
Name / Sign / Date
Reviewed By (QC Engineer)
Name / Sign / Date