QA/QC  › Plumbing & Water Supply  › Pipe Leakage Test
Test-report · QC-PLB-TST-002
Pipe Leakage Test Report
6 checkpoints across 2 sections. After hydrostatic pressure test; joint-level leakage verification
6 Checkpoints
2 Sections
Per test cycle
QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. VISUAL LEAKAGE INSPECTION
A1System pressurized to test pressure (1.5 × design pressure); pressure held steady for 30 minutes minimum
Acceptance: Test pressure maintained throughout, gauge stable reading, no pressure drops >0.1 bar
Cl. 13.1 — Pressure holding
OK
NC
NA
HOLD
A2All visible joints and fittings inspected for water seepage; inspection done every 5 minutes during test
Acceptance: Visual inspection at 5-min intervals, dry surface at all joints, no water droplets or streams
Cl. 13.2 — Periodic inspection
OK
NC
NA
HOLD
A3If seepage observed at any joint: test FAILED; joint location marked, system depressurized, repair initiated
Acceptance: Leaking joint isolated, repaired (retightened/re-solvent/re-seal), re-tested individually before main system re-test
Cl. 13.3 — Failure response
OK
NC
NA
HOLD
A4After 30 minutes: zero visible leakage = PASS; full test report prepared with photos if available
Acceptance: No seepage at any location, system passes, test certificate issued and signed by QC engineer
Cl. 13.4 — Acceptance
OK
NC
NA
HOLD
B. LEAKAGE DOCUMENTATION
B1All test readings recorded in table: Time, Pressure (bar), Observations (any seepage location)
Acceptance: Readings tabulated every 5 minutes, locations of any seepage noted with dimensions/identifiers
Cl. 14.1 — Record keeping
OK
NC
NA
HOLD
B2Final verdict: PASS (zero leakage) or FAIL (seepage detected) with location/extent documented
Acceptance: Pass/Fail clearly stated, leakage location (if any) marked on drawing, remedial action documented
Cl. 14.2 — Final verdict
OK
NC
NA
HOLD
A. VISUAL LEAKAGE INSPECTION
A1System pressurized to test pressure (1.5 × design pressure); pressure held steady for 30 minutes minimum
Cl. 13.1 — Pressure holding (IS 2065)
Test pressure maintained throughout, gauge stable reading, no pressure drops >0.1 bar
OKNCNAHOLD
A2All visible joints and fittings inspected for water seepage; inspection done every 5 minutes during test
Cl. 13.2 — Periodic inspection (IS 2065)
Visual inspection at 5-min intervals, dry surface at all joints, no water droplets or streams
OKNCNAHOLD
A3If seepage observed at any joint: test FAILED; joint location marked, system depressurized, repair initiated
Cl. 13.3 — Failure response (IS 2065)
Leaking joint isolated, repaired (retightened/re-solvent/re-seal), re-tested individually before main system re-test
OKNCNAHOLD
A4After 30 minutes: zero visible leakage = PASS; full test report prepared with photos if available
Cl. 13.4 — Acceptance (IS 2065)
No seepage at any location, system passes, test certificate issued and signed by QC engineer
OKNCNAHOLD
B. LEAKAGE DOCUMENTATION
B1All test readings recorded in table: Time, Pressure (bar), Observations (any seepage location)
Cl. 14.1 — Record keeping (IS 2065)
Readings tabulated every 5 minutes, locations of any seepage noted with dimensions/identifiers
OKNCNAHOLD
B2Final verdict: PASS (zero leakage) or FAIL (seepage detected) with location/extent documented
Cl. 14.2 — Final verdict (IS 2065)
Pass/Fail clearly stated, leakage location (if any) marked on drawing, remedial action documented
OKNCNAHOLD
Inspection Sign-Off
PASS
FAIL — REPAIR & RETEST REQUIRED
Remarks
Name / Sign / Date
Tested By
Name / Sign / Date
Reviewed By
Name / Sign / Date