Plan · QC-PLB-PLN-001
Plumbing & Water Supply ITP
8 checkpoints across 6 sections. Project start; guides plumbing installation activities
8 Checkpoints
6 Sections
One per project
QC Engineer, Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
PHASE_1. Phase 1: Pipe Laying
1.1Method statement review and approval by QC before laying starts
Acceptance: Method statement signed, QC approval obtained
Method approval
1.2WITNESS POINT: Trench preparation and pipe laying - QC present during laying
Acceptance: QC observes laying, bend radius verified, gradient correct
QC witnessing
1.3As-laid drawing prepared showing actual routing and depths
Acceptance: Drawing updated with actual conditions, signed by QC
Record drawing
PHASE_2. Phase 2: Joint Inspection
2.1All joints visually inspected; no seepage observed at low pressure
Acceptance: All joints dry, no water droplets, documentation complete
Visual inspection
PHASE_3. Phase 3: Pressure Testing
3.1HOLD POINT: Hydrostatic pressure test (1.5×design pressure, 30 min) - zero leakage required
Acceptance: Test passed, pressure maintained, no visible leakage, test report signed
Pressure test approval
Showing 5 of 8 checkpoints ·
PHASE_1. Phase 1: Pipe Laying
1.1Method statement review and approval by QC before laying starts
Method approval (IS 2065)
Method statement signed, QC approval obtained
1.2WITNESS POINT: Trench preparation and pipe laying - QC present during laying
QC witnessing (IS 2065)
QC observes laying, bend radius verified, gradient correct
1.3As-laid drawing prepared showing actual routing and depths
Record drawing (IS 2065)
Drawing updated with actual conditions, signed by QC
PHASE_2. Phase 2: Joint Inspection
2.1All joints visually inspected; no seepage observed at low pressure
Visual inspection (IS 2065)
All joints dry, no water droplets, documentation complete
PHASE_3. Phase 3: Pressure Testing
3.1HOLD POINT: Hydrostatic pressure test (1.5×design pressure, 30 min) - zero leakage required
Pressure test approval (IS 2065)
Test passed, pressure maintained, no visible leakage, test report signed
Showing 5 of 8 ·
Inspection Sign-Off
ITP APPROVED
ITP APPROVED WITH MODS
ITP REJECTED
Prepared By
Name / Sign / Date
Reviewed By (QC)
Name / Sign / Date