IS 8142:1976 is the Indian Standard (BIS) for method of test for determining the setting time of concrete by penetration resistance. This standard details the method for determining the initial and final setting times of concrete by measuring penetration resistance. The test is performed on mortar sieved from a representative concrete sample, providing a more realistic assessment of in-situ setting behaviour compared to tests on cement paste alone.
Method of test for determining the setting time of concrete by penetration resistance
Key reference values — verify against the current code edition / project specification.
| Reference | Value | Clause |
|---|---|---|
| Measures | Setting time of CONCRETE (mortar wet-sieved out) | Scope |
| Initial set | ≈ penetration resistance 3.5 MPa | Critical |
| Final set | ≈ penetration resistance 27.6 MPa | Critical |
| Vs IS 4031 | That is cement-PASTE set — different test/time | Concept |
| Controls | Cold-joint window, finishing, slip-form, retarders | Application |
| Strongly affected by | Temperature (hot weather shortens set) | Caution |
| Admixtures | Retarder/accelerator effect quantified by this test | Cross-ref |
IS 8142:1976 is the method of test for determining the setting time of concrete by penetration resistance — measuring, on mortar wet-sieved from the concrete, how its penetration resistance rises with time to define the *initial* and *final* setting times of the concrete (distinct from the cement paste setting time of IS 4031). It is the test that quantifies *when concrete stiffens* — which governs cold-joint timing, finishing windows, slip-form rates and admixture/retarder behaviour.
It sits with fresh-concrete behaviour:
The test sieves mortar from the concrete, then periodically pushes standard needles in and records the force; penetration resistance vs time gives, by convention, initial set ≈ 3.5 MPa and final set ≈ 27.6 MPa. Those two times control real operations:
The engineering point: setting time is not a fixed number — it depends on cement, W/C, admixtures and especially temperature (hot weather sharply shortens it). This test measures it for *your* concrete in *your* conditions.
Scenario: a large hot-weather slab pour at risk of cold joints; a retarder is proposed.
Step 1 — baseline: run IS 8142 on the job mix *without* admixture at the expected placing temperature → initial/final set times.
Step 2 — with retarder: repeat at the proposed retarder dose, same temperature → the extended initial/final times.
Step 3 — plan the pour to the numbers: size pour bays and delivery so each successive layer lands and is vibrated into the previous one before its initial set (now safely extended); set the finishing crew's start to the measured final-set window.
Step 4 — verify in conditions: confirm at the actual site temperature (hot weather shortens set — a lab-temperature time is optimistic).
Result: a defensible pour plan and admixture dose tied to *measured* setting times, instead of a guessed 'it should be fine' that produces cold joints when the day runs hot.
1. Confusing concrete set (IS 8142) with cement-paste set (IS 4031). Different tests, different times — site decisions need the *concrete* setting time.
2. Ignoring temperature. Hot weather sharply shortens set; a lab-temperature time used to plan a hot pour produces cold joints.
3. Planning cold-joint/finishing windows by feel. The whole point is to *measure* the window rather than guess and discover the joint afterward.
4. Dosing retarders/accelerators without proving the shift. Admixture effect must be quantified on the job materials at job temperature, not taken from a brochure.
5. Sloppy wet-sieving / timing. The mortar fraction and the time intervals must follow the method or the set times are unreliable.
IS 8142 is reaffirmed and quietly decisive because cold joints and finishing defects are scheduling failures, and this is the test that turns 'when does it stiffen' from a guess into a number. The recurring real-world mistakes are conceptual: confusing concrete set with cement-paste set, and ignoring that temperature dominates — the same mix that gives a comfortable window in a cool lab can cold-joint on a 42 °C afternoon. Anywhere set timing actually matters — big monolithic pours, hot-weather work, retarded long-haul RMC, slip-form, time-critical finishing — measure it on the job mix at the job temperature, plan the pour and the admixture dose to those numbers, and the cold joint stops being a surprise. It is one of the few tests whose output is a direct construction-sequencing decision.
| Parameter | IS Value | International | Source |
|---|---|---|---|
| Initial Set Resistance | 3.5 MPa | 500 psi [3.5 MPa] | ASTM C403 / C403M |
| Final Set Resistance | 27.6 MPa | 4000 psi [27.6 MPa] | ASTM C403 / C403M |
| Standard Test Temperature | 27 ± 2°C | 23 ± 2°C [73.5 ± 3.5°F] | ASTM C403 / C403M |
| Sieve Size for Mortar Preparation | 4.75 mm | 4.75 mm (No. 4 Sieve) | ASTM C403 / C403M |
| Needle Penetration Depth | 25 ± 2 mm | 1 in. ± 1/16 in. [25 ± 2 mm] | ASTM C403 / C403M |
| Largest Needle Bearing Area | 650 mm² | 1 in.² [645 mm²] | ASTM C403 / C403M |
| Setting Resistance (for admixtures) | Not defined for this purpose | 0.5 MPa | BS EN 480-2:2006 |
| Minimum Mortar Depth in Container | 14 cm | 5.5 in. [140 mm] | ASTM C403 / C403M |