PMC Risk · Issue · ChangeExtension of Time (EOT) Calculation Sheet

Extension of Time (EOT) Calculation Sheet

form
PMC-RSK-FRM-003·v1.0-beta·⚠ Beta — review before use

Detailed calculation of Extension of Time (EOT) — days of delay attributable to specified causes per contract. Companion to Variation Orders or claims.

ReferencesFIDIC Sub-clause 8.4 (Extension of Time for Completion)FIDIC Sub-clause 8.5 (Force Majeure)Indian Contract Act 1872 (Frustration / Force Majeure)Project-specific Contract
Download
📍 When to use this template
  • Notice of delay event raised.
  • Quantification of delay days for EOT request.
  • Engineer's determination per FIDIC Sub-clause 3.5.
  • DAB / Arbitration evidence.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Delay Event5 fields
Event Description
_____________
Date of Event
_____________
Cause Category (FIDIC Sub-clause 8.4 list)
_____________
Notice Date (per FIDIC 20.1 — within 28 days)
_____________
Continuing Cause (Y/N)
_____________
2Affected Activities5 fields
Affected Activities (Critical Path)
_____________
Original Planned Duration
_____________
Actual Duration Affected
_____________
Logic / Float Analysis
_____________
Schedule Impact Analysis Method (Time Slice / As-Planned vs As-Built / Window Analysis)
_____________
3Quantification of Delay5 fields
Delay to Critical Path (Calendar Days)
_____________
Concurrent Delays (Attributable to Other Causes)
_____________
Net Delay Attributable to Event
_____________
Cost of Delay (Prolongation Costs)
_____________
Loss of Productivity Calculation
_____________
4Contractual Provisions4 fields
FIDIC Sub-clause Referenced
_____________
Contractor's Entitlement (Days + Cost)
_____________
Client's Counter-claim (if any)
_____________
Engineer's Determination per Sub-clause 3.5
_____________
5Final EOT5 fields
Approved Extension (Days)
_____________
Revised Contract Completion Date
_____________
Cost Adjustment Approved
_____________
Settlement Conditions
_____________
Both Parties Sign-off
_____________
💡 Sample filled excerpt
EOT Calculation for GFC delay event. Cause: Client's GFC drawing delay (FIDIC 8.4(a)). Notice: 12-Mar-2026 (within 28 days). Affected: Foundation activities. Original schedule: Mar-Apr. Actual: Mar-Jun (60 days late, 3 of which concurrent with rain delay). Net attributable: 57 days. Prolongation cost: ₹25 lakh/month × 1.9 = ₹48 lakh. Engineer's determination: 50 days + ₹40 lakh.
⚖ Compliance notes
  • Per FIDIC Sub-clause 20.1, EOT notice within 28 days of cause of action.
  • FIDIC Sub-clause 8.4 lists eligible causes: instructed variations, unforeseeable obstructions, exceptional weather, force majeure, contractor's not-attributable delays.
  • Schedule Impact Analysis methodology must be agreed: Time Slice, As-Planned vs As-Built, or Window Analysis.
  • Concurrent delays (multiple causes) require careful apportionment — often the source of disputes.
  • Engineer's determination per Sub-clause 3.5 is binding unless objected within 14 days.
  • Cost component is separate from time — typically prolongation + loss of productivity claims.