PMC Risk · Issue · ChangeChange Request Register

Change Request Register

register
PMC-RSK-REG-002·v1.0-beta·⚠ Beta — review before use

This register is used to track all changes requested by the Client, Engineer, or Contractor during the project. It helps manage variations, extra items, and their impact on cost and time in a systematic way.

ReferencesFIDIC Red Book (1999/2017) Clause 13 [Variations and Adjustments]CPWD General Conditions of Contract, Clause 12 [Deviations/Variations/Extra Items]CPWD Works Manual (Chapter on Contract Management)IS 1200 (All Parts) - Referenced in subsequent rate analysis and billing for varied work
Download
📍 When to use this template
  • When any party (Client, PMC, Contractor) proposes a change from the original scope, drawing, or specification.
  • Updated continuously throughout the project lifecycle whenever a new change is identified or an existing one's status changes.
  • Maintained by the PMC/Engineer's contracts or planning team, with inputs from site execution staff.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Register Title
_____________
Document No.
_____________
Revision No.
_____________
Date of Issue
_____________
2Change Identification7 fields
Change Request No. (CRN)
_____________
Date Raised
_____________
Raised By (Client/PMC/Contractor)
_____________
Description of Proposed Change
_____________
Reason for Change (e.g., Site Condition, Design Error, Client Request, Value Engineering)
_____________
Reference Drawing/Specification No.
_____________
Location / Chainage / Grid Line
_____________
3Initial Impact Assessment5 fields
Nature of Change (Addition/Deletion/Substitution)
_____________
Anticipated Impact on Cost (Increase/Decrease/Nil)
_____________
Anticipated Impact on Time (Extension/Acceleration/Nil)
_____________
Impact on Quality/Performance
_____________
Urgency (High/Medium/Low)
_____________
4Analysis & Approval Status8 fields
Date Sent for Analysis
_____________
Contractor's Cost Proposal Ref.
_____________
Contractor's Time Impact Analysis (TIA) Ref.
_____________
PMC/Engineer's Recommendation
_____________
Date Submitted to Client
_____________
Client's Decision (Approved/Rejected/On Hold/Info Only)
_____________
Approval Date
_____________
Variation Order (VO) / Change Order (CO) No.
_____________
5Financial Impact6 fields
Estimated Cost (Initial)
_____________
Quoted Cost (by Contractor)
_____________
Approved Cost (Final)
_____________
Rate Analysis Reference No.
_____________
Related BOQ Item No. (if applicable)
_____________
Budget Head / Cost Code
_____________
6Schedule Impact4 fields
Estimated Time Impact (Days)
_____________
Approved Extension of Time (EOT) in Days
_____________
Impact on Critical Path (Yes/No)
_____________
Revised Milestone Dates (if any)
_____________
7Closure Status5 fields
Implementation Status (Implemented/Not Implemented/In Progress)
_____________
Date of Completion of Varied Work
_____________
RA Bill No. where claimed
_____________
Remarks / Final Notes
_____________
Closed By
_____________
💡 Sample filled excerpt
CRN: CR-PKG1-015 | Date Raised: 15-Jul-2023 | Raised By: Client | Description: Provide additional 200mm thick RCC retaining wall at Grid A/5-10 due to revised soil report. | Status: Approved | VO No.: VO-007 | Approved Cost: ₹ 4,50,000
⚖ Compliance notes
  • Helps administer variation claims under FIDIC Conditions of Contract (e.g., Sub-Clause 13.1 Right to Vary, 13.3 Variation Procedure).
  • Provides documentation for Extra/Substituted Items as per CPWD Works Manual, essential for processing deviation statements and supplementary agreements.
  • Forms the basis for justifying Extension of Time (EOT) claims under the contract (e.g., FIDIC Sub-Clause 8.4/8.5).
  • Creates a crucial audit trail for financial approvals and budget revisions, often scrutinized by internal and external auditors.