📍 When to use this template
- After every weekly progress meeting involving the Client, Consultant, PMC, and key Contractors.
- Prepared and circulated within 24-48 hours of the meeting to ensure timely action.
- Typically filled by the PMC's Project Coordinator or Site Engineer, then reviewed by the Project Manager.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Meeting Details8 fields
Project Name
_____________
Contract / Package No.
_____________
MoM Reference No.
_____________
Meeting Date & Time
_____________
Meeting Location (Physical/Virtual)
_____________
Prepared By (Name & Designation)
_____________
Approved By (Name & Designation)
_____________
2List of Attendees5 fields
Organisation (Client/PMC/Consultant/Contractor)
_____________
Email / Contact No.
_____________
3List of Absentees (with apologies)4 fields
Organisation
_____________
4Review of Previous MoM Action Points6 fields
Item Ref. (Prev. MoM No. & Item No.)
_____________
Action Point Description
_____________
Responsibility
_____________
Original Target Date
_____________
Current Status (Open/Closed/Ongoing)
_____________
Remarks / Reason for Delay
_____________
5Progress Review & Look Ahead Plan8 fields
Discipline (e.g., Civil, Structural, MEP, Finishes)
_____________
Planned Progress % (as per schedule)
_____________
Achieved Progress % (current week)
_____________
Cumulative Progress %
_____________
Slippage / Lead (%)
_____________
Key Activities Completed (Last Week)
_____________
Key Activities Planned (Next Week)
_____________
Resource Deployed (Manpower/Machinery)
_____________
6Key Discussions, Hindrances & Decisions7 fields
Issue / Hindrance Description
_____________
Impact (Cost/Time/Quality)
_____________
Discussion Summary
_____________
Decision Taken / Action Required
_____________
Responsibility (for resolution)
_____________
7HSE & Quality Observations7 fields
Observation Type (Safety Violation / Quality Non-Conformance / Housekeeping)
_____________
Location / Grid Reference
_____________
Observation Details
_____________
Corrective Action Required
_____________
Responsibility
_____________
💡 Sample filled excerpt
Section: Key Discussions, Hindrances & Decisions
Sr. No.: 04
Issue / Hindrance Description: Delay in receiving GFC drawing for Tower B, 5th floor slab from Architect.
Decision Taken / Action Required: Architect to release the final GFC drawing. PMC to escalate to Client's Head of Design if not received by target date.
Responsibility: Lead Architect
Target Date: 25-Jul-2024
⚖ Compliance notes
- Fulfills contractual obligations for regular progress reporting and record-keeping (often in General/Special Conditions of Contract).
- Serves as a primary record for substantiating claims for Extension of Time (EOT) under FIDIC Sub-clause 8.5 or equivalent contract clauses.
- Provides documented evidence of instructions and decisions, crucial during contract administration and dispute resolution.
- Acts as an official record for tracking compliance with safety observations as per BOCW Act, 1996 and site safety plan.