Design Coordination Meeting MoM

mom
PMC-MTG-MOM-008·v1.0-beta·⚠ Beta — review before use

This document records the discussions, decisions, and action items from a meeting between the design team, execution team, and other consultants. It ensures everyone is aligned on design changes, clarifications, and drawing releases to avoid rework at the site.

ReferencesNational Building Code of India (NBC) 2016FIDIC Red Book (1999/2017) Clause 13FIDIC Red Book (1999/2017) Sub-Clause 4.1CPWD Works Manual
Download
📍 When to use this template
  • When there are clashes between different service drawings (e.g., HVAC vs. Electrical) or between architectural and structural drawings.
  • Held weekly or fortnightly during the design development and shop drawing submission phase, or whenever a major design issue is identified.
  • The PMC's design coordinator or project engineer chairs the meeting and is responsible for preparing and circulating the MoM within 24-48 hours.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Project & Meeting Details8 fields
Project Name
_____________
Contract / Package No.
_____________
MoM No.
_____________
Meeting Date
_____________
Meeting Time (Start/End)
_____________
Meeting Location (Physical/Virtual)
_____________
Prepared By (Name & Designation)
_____________
Circulation List
_____________
2Attendees List6 fields
Sr. No.
_____________
Name
_____________
Designation
_____________
Organisation (Client/PMC/Architect/Consultant/Contractor)
_____________
Contact No.
_____________
Email ID
_____________
3Review of Previous MoM Action Points7 fields
Previous MoM Ref. No.
_____________
Action Point ID
_____________
Description of Action
_____________
Responsibility
_____________
Original Due Date
_____________
Current Status (Open/Closed/Delayed)
_____________
Remarks / Reason for Delay
_____________
4New Discussion Points & Decisions6 fields
Item No.
_____________
Discipline (Arch/Struct/MEP/Façade)
_____________
Subject / Drawing Ref. No.
_____________
Discussion Summary
_____________
Decision Taken / Clarification Provided
_____________
Reference Document / Sketch No.
_____________
5Action Items for All Stakeholders5 fields
Action Item ID
_____________
Description of Action Required
_____________
Responsibility (Person & Organisation)
_____________
Target Date for Completion
_____________
Priority (High/Medium/Low)
_____________
6Drawing & Document Submission Status7 fields
Sr. No.
_____________
Drawing / Document Title & No.
_____________
Discipline
_____________
Submission Type (GFC/Shop Drawing/RFI)
_____________
Submission Date
_____________
Expected Return Date
_____________
Current Status (Approved/Approved with Comments/Resubmit)
_____________
7Next Meeting Details3 fields
Date of Next Meeting
_____________
Time of Next Meeting
_____________
Tentative Agenda
_____________
💡 Sample filled excerpt
Action Item ID: DCM-08-A-001 | Description: MEP Consultant to revise the basement level-1 coordinated services drawing (CSD) to resolve clash between fire-fighting pipe and main HVAC duct near Grid A-5. | Responsibility: Mr. Sharma (ABC Consultants) | Target Date: 25-JUL-2024
⚖ Compliance notes
  • Documents design changes which may lead to Variation Orders under FIDIC Clause 13 [Variations and Adjustments] or equivalent contract clauses.
  • Provides a record of design clarifications, crucial for defending against claims for delay or disruption (FIDIC Sub-Clause 20.2).
  • Ensures coordination between different agencies as per General Conditions of Contract, preventing abortive work and ensuring compliance with approved GFC drawings.
  • Can be used as supporting evidence for Extension of Time (EOT) claims if design information is delayed by consultants.