PMC📐 Design CoordinationGFC Submission Tracker

GFC Submission Tracker

log
PMC-DES-LOG-002·v1.0-beta·⚠ Beta — review before use

Tracks GFC (Good for Construction) drawing submissions + approvals — by discipline, by area, by date. Critical to identify GFC bottlenecks that delay construction.

ReferencesFIDIC Sub-clause 5.2 (Contractor's Documents)ISO 19650 (BIM CDE)Project Document Control Procedure
Download
📍 When to use this template
  • Weekly tracking by design office + PMC.
  • Pre-NTP audit + verification.
  • Delay claim documentation (per FIDIC 8.4).
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Tracker Header4 fields
Project Reference
_____________
Status as of Date
_____________
Updated By
_____________
Total Drawings (Planned vs Issued)
_____________
2GFC Status by Discipline8 fields
Discipline
_____________
Total Drawings Planned
_____________
Issued Latest Revision
_____________
Pending GFC Status
_____________
Critical Path Impact
_____________
Target GFC Date
_____________
Designer Owner
_____________
Remarks
_____________
3Discipline-wise Detail (per Drawing)6 fields
Drawing Number
_____________
Title + Description
_____________
Submission Status
_____________
Revision
_____________
GFC Date (Issued / Pending)
_____________
Comments / Resubmission Required
_____________
4Issues + Escalation4 fields
Drawings Pending > 30 days
_____________
Critical Activity Affected
_____________
Escalation Status
_____________
Resolution Target
_____________
💡 Sample filled excerpt
12-May-2026. Total Planned: 245 drawings. GFC Issued: 168 (69 %). Pending: 77. By Discipline: Civil 95 % done, Struct 80 %, MEP 55 % (delayed by HVAC sub-consultant). Critical path: Foundation drawings 100 % done; MEP for L3 onwards critical. Escalation: HVAC consultant — target 30-May.
⚖ Compliance notes
  • Per FIDIC Sub-clause 5.2, designer's documents (GFC) must be issued per agreed schedule.
  • Delay in GFC issuance attributable to consultant / client = extension of time for contractor (Sub-clause 8.4).
  • Critical path GFC delay = project delay; closely tracked + escalated.
  • Construction without GFC = unauthorized work; rework risk.