Drawing Register

log
PMC-DSN-LOG-001·v1.0-beta·⚠ Beta — review before use

This is a master log to track all project drawings. It helps everyone on site know the latest revision, its approval status, and when it was issued for construction, preventing work based on old or unapproved drawings.

ReferencesIS 962:1989 (Code of practice for architectural and building drawing)FIDIC Red Book (1999) Sub-clause 1.8 (Care and Supply of Documents)FIDIC Red Book (1999) Sub-clause 5.2 (Contractor's Documents)CPWD Works Manual (Chapter on Drawings and Record Keeping)
Download
📍 When to use this template
  • Maintained continuously from the first drawing receipt until project handover.
  • Updated immediately whenever a new drawing or a new revision is received from the architect/consultant.
  • Typically managed by the Document Controller or a designated Planning/Site Engineer.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Register ID / Doc. No.
_____________
Date (Last Updated)
_____________
Prepared By (Document Controller)
_____________
Approved By (Project Manager)
_____________
2Drawing Identification7 fields
Sl. No.
_____________
Drawing Number
_____________
Drawing Title
_____________
Discipline (Arch, Struc, MEP, Finishes, etc.)
_____________
Area / Building / Floor
_____________
Drawing Scale
_____________
Drawing Size (A0, A1, etc.)
_____________
3Revision & Version Control4 fields
Current Revision No. (R0, R1, R2...)
_____________
Revision Date
_____________
Revision Description / Purpose
_____________
Supersedes Drawing No. / Rev.
_____________
4Submission & Approval Status6 fields
Date Received from Consultant
_____________
Date Submitted to Client/PMC for Approval
_____________
Approval Status (A, B, C, D or Approved, Approved with Comments, Resubmit, Rejected)
_____________
Date of Approval Received
_____________
Approval Reference No.
_____________
Remarks / Comments
_____________
5Issuance for Construction (GFC)4 fields
Current Status (e.g., GFC, Tender, For Information)
_____________
Date Issued for Construction (GFC Date)
_____________
Issued To (e.g., Site Team, Subcontractor)
_____________
Transmittal Note / Letter No.
_____________
6As-Built Drawing Details4 fields
As-Built Revision No.
_____________
As-Built Submission Date
_____________
As-Built Approval Date
_____________
Final Handover Status
_____________
💡 Sample filled excerpt
Sl. No: 25 | Drawing No: ACME/STR/BLKA/FN/005 | Title: Foundation Plan - Block A | Discipline: Structural | Current Rev: R2 | Rev Date: 15-May-2023 | Status: GFC | Approval Status: A (Approved) | GFC Date: 20-May-2023
⚖ Compliance notes
  • Fulfills contract requirements for document control and maintaining a record of 'Good for Construction' (GFC) drawings.
  • Essential for ISO 9001 quality audits to demonstrate process control for design and development outputs (Clause 7.5).
  • Supports FIDIC Sub-clause 5.2 (Contractor's Documents) by tracking all design documents and their status.
  • Acts as primary evidence during dispute resolution regarding which drawing version was current at the time of execution.