📍 When to use this template
- When any work is instructed that is not in the original Bill of Quantities (BOQ) or drawings.
- Continuously updated throughout the project, whenever a new variation is identified or its status changes.
- Maintained by the Contractor's/PMC's billing engineer and reviewed jointly during monthly progress meetings.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract / Package No.
_____________
Register Title
_____________
Document No.
_____________
Last Updated Date
_____________
Prepared By (Name/Company)
_____________
Reviewed By (Name/Company)
_____________
2Variation Identification8 fields
VO Serial No.
_____________
Date Identified
_____________
Variation Description
_____________
Location / Chainage / Grid
_____________
Originator (Client/PMC/Contractor)
_____________
Reference Drawing No.
_____________
Reference RFI No.
_____________
Reference Site Instruction (SI) / Engineer's Instruction (EI) No.
_____________
3Justification & Nature5 fields
Reason for Variation (e.g., Design Change, Site Condition, Client Request, Value Engineering)
_____________
Nature of Variation (Addition / Omission / Substitution)
_____________
Impact on Schedule (Yes/No/Potential)
_____________
If Yes, EOT Claim Ref. No.
_____________
Impact on Other Works/Interfaces
_____________
4Cost Impact & Rate Analysis7 fields
Contractor's Quoted Amount (INR)
_____________
Rate Analysis Reference No.
_____________
Basis of Rate (BOQ Item / Derived from BOQ / Star Rate / Market Rate)
_____________
PMC's Recommended Amount (INR)
_____________
Client's Approved Amount (INR)
_____________
Rate Analysis Status (Submitted/Under Review/Approved/Rejected)
_____________
Cost Impact (Debit/Credit/Nil)
_____________
5Approval Status6 fields
VO Proposal Submission Date
_____________
PMC Recommendation Date
_____________
Client Approval Date
_____________
Approval Status (Pending/Approved/Rejected/On Hold)
_____________
Approved VO No. / Letter Ref.
_____________
Remarks / Reason for Rejection
_____________
6Execution & Billing Status6 fields
Work Execution Status (Not Started/In Progress/Completed)
_____________
Date of Completion
_____________
Included in RA Bill No.
_____________
Billed Quantity
_____________
Billed Amount (INR)
_____________
Cumulative Billed Amount (INR)
_____________
💡 Sample filled excerpt
VO Serial No.: 015
Variation Description: Providing additional 200mm thick RCC retaining wall near Gate-3 due to unforeseen soil conditions.
Approval Status: Approved
Approved Amount: ₹ 4,52,000/-
Included in RA Bill No.: RA-08
⚖ Compliance notes
- Fulfills requirements under FIDIC (Red Book 1999) Sub-Clause 13 [Variations and Adjustments] for instructing and valuing changes.
- Essential for substantiating claims and changes as per CPWD General Conditions of Contract (GCC), Clause 12.
- Provides a clear audit trail for financial reconciliation, budget control, and final bill settlement.
- Mandatory supporting document for RA Bills that include non-BOQ or varied items.