RCC Box Culvert BOQ — Worked Example for a 2 × 2 m...

6 min read · BOQ · Estimation · Box Culvert · Cross-Drainage · IRC SP 13 · Worked Example
Home / Knowledge / RCC Box Culvert BOQ — Worked E
BOQEstimationBox CulvertCross-DrainageIRC SP 13Worked Example📖 6 min · 1,468 words

RCC Box Culvert BOQ — Worked Example for a 2 × 2 m PMGSY-Spec Box

RCC box culverts are the workhorse cross-drainage structure on Indian roads above 600 mm pipe equivalent — the PMGSY / state-PWD / NH / SH standard for any drainage span between 1 m and 3 m. Above 3 m span, slab culverts take over; below 1 m, Hume pipes are economical. The IRC SP 13 + IRC 6 + IRC 21 + IS 456 standard: single-cell M20 RCC box with monolithic raft + walls + deck slab, brick wing walls splayed 45°. This article walks through a complete BOQ for the PMGSY default — 2 × 2 m clear opening × 8 m long.

Project Scenario

You're estimating a box culvert under a PMGSY road crossing a small seasonal nallah with moderate catchment. Hydraulic sizing dictates 2 × 2 m clear opening. Carriageway 5.5 m + headwall extensions = 8 m total culvert length. Walls and slab 300 mm thick, raft 300 mm, founded 1.5 m below NGL.

Design specification at a glance
  • Length (along road): 8 m
  • Internal span (clear width): 2.0 m
  • Internal height (clear): 2.0 m
  • Wall thickness: 300 mm RCC M20
  • Deck slab thickness: 300 mm RCC M20
  • Raft thickness: 300 mm RCC M20
  • Wing walls: 4 nos × 2.0 m × 45° splay
  • Apron + curtain walls: 2 m × full width at each end

The Complete BOQ — 14 Items in CPWD DSR 2023

# DSR Code Item Description Unit Quantity
12.8.1Earthwork in foundation pit, all-kinds-of-soil48.64
24.1.8PCC 1:4:8 bed below raft, 100 mm thick2.32
35.1.2RCC M20 in raft slab, 300 mm thick6.24
45.2.2RCC M20 in vertical side walls (2 nos)9.60
55.3RCC M20 in deck slab, 300 mm thick6.24
65.9.1Centering & shuttering for raft20.80
75.9.2Centering & shuttering for walls (4 faces total)64.00
85.9.3Centering & shuttering for deck slab20.80
95.22.6TMT Fe-500D reinforcement (cut, bent, placed)kg2,649.60
106.4.2F.P.S. brick masonry in CM 1:6 — 4 wing walls (45° splay)3.20
114.1040 mm DPC course on wing walls1.84
127.1.1Stone pitching apron at U/S + D/S ends (2 m × 300 mm)3.12
137.1.1Curtain (cut-off) walls at U/S + D/S ends0.94
142.25Backfill above culvert with excavated earth, watered + compacted0 (deep set — none needed)

Total RCC volume = 22.08 m³. At 120 kg/m³ that's ~2.65 tonnes of steel — higher per-m³ ratio than a wall or drain because IRC 21 demands extra reinforcement for impact + fatigue. The live BOQ Builder evaluates these formulas in real time — change span (1-3 m), height, slab/wall/raft thickness, depth below NGL.

How Each Quantity Was Computed

1. Excavation — Item 2.8.1

External width = internal span + 2 × wall_thk = 2.0 + 0.6 = 2.6 m
External height = internal_h + slab_thk + raft_thk = 2.0 + 0.3 + 0.3 = 2.6 m
Trench width = 2.6 + 0.6 = 3.2 m (300 mm working space each side)
Excav depth = depth below NGL + raft + PCC = 1.5 + 0.3 + 0.10 = 1.90 m
Excavation = 8 × 3.2 × 1.90 = 48.64 m³

2. PCC bed — Item 4.1.8

PCC width = external_w + 0.30 = 2.9 m
PCC volume = 8 × 2.9 × 0.10 = 2.32 m³

3-5. RCC raft + walls + deck slab

Raft volume = 8 × 2.6 × 0.30 = 6.24 m³
Wall volume (2 walls × full internal height) = 2 × 8 × 0.30 × 2.0 = 9.60 m³
Deck slab volume = 8 × 2.6 × 0.30 = 6.24 m³

Note: walls run from raft top to slab underside, so wall height = internal clear height = 2.0 m.

6-8. Centering & shuttering

  • Raft: under-side only (raft cast on PCC bed) = 8 × 2.6 = 20.80 m²
  • Walls: 4 faces total (2 walls × 2 faces each) = 4 × 8 × 2.0 = 64 m²
  • Deck slab: under-side only = 8 × 2.6 = 20.80 m²

9. Reinforcement — Item 5.22.6

Total RCC = 6.24 + 9.60 + 6.24 = 22.08 m³
Steel = 22.08 × 120 = 2,649.60 kg (~2.65 tonnes)

120 kg/m³ is typical for box culverts under IRC Class A loading. Heavy IRC Class AA / 70R tracked-vehicle loading pushes this to 150-180 kg/m³.

10-11. Wing walls + DPC

Wing wall avg height = (external_h + 0.30) × 0.6 = 2.9 × 0.6 = 1.74 m
Wing wall brick (4 walls × 2 m × 0.23 m × 1.74 m) = 3.20 m³
Wing wall DPC = 4 × 2 × 0.23 = 1.84 m²

12-13. Apron + curtain walls

Apron (2 ends × 2.0 m × 2.6 m × 0.30 m) = 3.12 m³
Curtain wall (2 ends × 2.6 × 0.30 × 0.60) = 0.94 m³

When to Use Box Culvert vs Hume Pipe vs Slab Culvert

Span / dischargeRecommended structureBOQ Builder
≤ 0.6 m equivalent (small drain)NP3 / NP4 Hume pipeHume Pipe Culvert
0.9 - 1.2 m pipe equivalentSingle-line NP4 Hume pipeHume Pipe Culvert
1.0 - 3.0 m span (medium catchment)RCC box culvertCurrent article ⤴
4 - 12 m span (high catchment, open stream)Slab culvert / minor bridgeSlab Culvert
≥ 12 m span (proper bridge)T-beam / PSC girder bridgeCustom design (no template)

What This BOQ Excludes

  • Bearing pads / elastomeric bearings at slab-wall junction (only relevant for spans > 6 m + simply-supported design)
  • Haunches at slab-wall corner — small triangular RCC fillets, +5 % RCC volume
  • Parapet / railing on deck — for safe pedestrian use; mandatory on NH/SH
  • Expansion joints — every 30 m linear in long culverts
  • Waterproofing of deck top — only for culverts with < 600 mm earth cover
  • Approach slab on either side — 3.5 m × 0.30 m RCC prevents settlement transition; ~₹40-60k
  • Road overlay on top — separate bituminous or CC road BOQ

Common Estimation Mistakes

  • Using 100 kg/m³ steel "RCC standard" — box culverts under wheel loads need 120-150 kg/m³ for fatigue + impact. Under-steeling cracks the deck within first monsoon.
  • Forgetting wing walls — without them, soil from approach embankments slides into the culvert mouth, blocking flow within 2 monsoons.
  • Specifying RCC wing walls when brick suffices — for PMGSY rural roads, brick wing walls (DSR 6.4.2) are 30-40 % cheaper than RCC (5.2.2) and entirely adequate. RCC wing walls are needed only for NH/SH where wheel-impact loads are likely.
  • Skipping apron + curtain wall — at the discharge end, water exiting the culvert at high velocity scours the bed. Without apron + curtain wall, the headwall foundation is undermined within 2-3 monsoons.
  • Treating raft + walls + slab as one RCC item — they have different DSR rates (5.1.2 raft < 5.2.2 walls < 5.3 slab). Lumping under one rate misses ~₹50-80k per culvert.
  • Over-designing for "future-proofing" — bumping from 2 m span to 3 m "to be safe" adds ~₹3-5 lakh to a single culvert. PMGSY hydraulic sizing already includes 25-year storm + safety factor.

What Changes for a Different Box

  • 1 × 1 m (small drainage) — half the RCC volume, 250 mm walls/slab sufficient. ~₹3-4 lakh total.
  • 3 × 3 m (heavy duty NH) — 350 mm walls/slab/raft, M25 grade per IRC 21, steel ratio 150 kg/m³. Often paired with RCC wing walls + parapet.
  • Low earth cover (< 600 mm above slab) — add waterproofing membrane on deck top; bump slab thickness for direct-wheel-load consideration.
  • Two-cell box (high catchment, low road grade) — duplicate the slab + raft cost per cell; share the central wall.
  • Soft soil (SBC < 100 kN/m²) — bump raft to 400 mm + add pile foundation. Easily doubles foundation cost.
  • NH / SH carriageway — M25 design mix (DSR 4.20.1.4), 150 kg/m³ steel, RCC wing walls, M30 deck slab for IRC Class AA loading.

Get Your Box Culvert Cost in 30 Seconds

→ Open the Box Culvert BOQ Builder

Change span, height, wall / slab / raft thickness, length, wing wall length, depth — the Builder regenerates the BOQ + downloads Excel with formulas embedded. Customize for Your Project →

References & Companion Reading

Join InfraLens WhatsApp Channel
Get updates on new articles, tools, and IS code insights
More Articles
Clause references and parameter values are sourced from official BIS and international standards. Always refer to the original standard document for design decisions.
💬 Join the Discussion
Q: What has been your experience with this topic on site?
Q: Do you have any tips to share with fellow engineers?
Click a question to start your comment
Leave a Comment
0/500
No comments yet. Be the first to share your thoughts!