All BOQ templates

Slab Culvert / Minor Bridge (4-12 m span)

Single-span RCC slab bridge — RCC abutments + RCC deck slab + wing walls + approach slabs + parapet + bearing pads. The economic crossover between box culverts (≤ 3 m span) and proper bridges (≥ 12 m span). Standard for PMGSY high-discharge crossings + state-PWD minor bridges over canals + streams. Rates: CPWD DSR Vol 1 (2023).

Visual confirmation
Plan · 6 m span × 7.5 m wide deck
DECK SLAB6 m span7.5 m
Long elevation (across stream) · 6 m span
6 m2.5 mStream bed
Cross-section · 7.5 m wide deck × 600 mm thick
Stream flowing under deck7.5 mDECK 600 mm
Bill of Quantities14 items · CPWD DSR Vol 1 (2023)
#CodeDescriptionUnitQtyRate (₹)Amount (₹)
12.8.1ExcavationEarth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.Cum32.40260.308,433.72
24.1.8Pcc BedProviding and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)Cum2.896,812.0019,686.68
35.1.2Rcc Abut FoundProviding and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum12.759,045.751,15,333.31
45.2.2Rcc AbutmentReinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum18.7510,852.952,03,492.81
55.3Rcc Deck SlabReinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Cum29.7011,505.503,41,713.35
65.1.2Rcc Approach SlabProviding and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum15.759,045.751,42,470.56
75.9.1Shutter Abut FoundCentering and shuttering including strutting, propping etc. and removal of form for — Foundations, footings, bases of columns, etc. for mass concreteSqm25.50392.159,999.82
85.9.2Shutter AbutmentCentering and shuttering including strutting, propping etc. and removal of form for — Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.Sqm75.00842.5063,187.50
95.9.3Shutter Deck SlabCentering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platformSqm49.50927.2545,898.88
105.22.6SteelSteel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.Kg9,180.00107.859,90,063.00
116.4.2Wing Walls BrickBrick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : — Cement mortar 1:6 (1 cement : 6 coarse sand)Cum7.249,105.9565,927.08
125.2.2Parapet RccReinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum2.4810,852.9526,915.32
137.1.1Stone ApronRandom rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : — Cement mortar 1:6 (1 cement : 6 coarse sand)Cum9.007,311.2565,801.25
142.25BackfillFilling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.Cum56.25196.0011,025.00
Your inputsClear span 6 m · Deck length 7.5 m · Deck slab thk 600 mm · Abutment height 2.5 m · Abutment wall thk 500 mm · Wing wall length each 3 m · RCC parapet on deck edgesTOTAL₹21,09,948
12.8.1₹8,434
Excavation
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.
32.40 Cum× ₹260.30
24.1.8₹19,687
Pcc Bed
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
2.89 Cum× ₹6,812.00
35.1.2₹1,15,333
Rcc Abut Found
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
12.75 Cum× ₹9,045.75
45.2.2₹2,03,493
Rcc Abutment
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
18.75 Cum× ₹10,852.95
55.3₹3,41,713
Rcc Deck Slab
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
29.70 Cum× ₹11,505.50
65.1.2₹1,42,471
Rcc Approach Slab
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
15.75 Cum× ₹9,045.75
75.9.1₹10,000
Shutter Abut Found
Centering and shuttering including strutting, propping etc. and removal of form for — Foundations, footings, bases of columns, etc. for mass concrete
25.50 Sqm× ₹392.15
85.9.2₹63,188
Shutter Abutment
Centering and shuttering including strutting, propping etc. and removal of form for — Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
75.00 Sqm× ₹842.50
95.9.3₹45,899
Shutter Deck Slab
Centering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platform
49.50 Sqm× ₹927.25
105.22.6₹9,90,063
Steel
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.
9,180.00 Kg× ₹107.85
116.4.2₹65,927
Wing Walls Brick
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : — Cement mortar 1:6 (1 cement : 6 coarse sand)
7.24 Cum× ₹9,105.95
125.2.2₹26,915
Parapet Rcc
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
2.48 Cum× ₹10,852.95
137.1.1₹65,801
Stone Apron
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : — Cement mortar 1:6 (1 cement : 6 coarse sand)
9.00 Cum× ₹7,311.25
142.25₹11,025
Backfill
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.
56.25 Cum× ₹196.00
Clear span 6 m · Deck length 7.5 m · Deck slab thk 600 mm · Abutment height 2.5 m · Abutment wall thk 500 mm · Wing wall length each 3 m · RCC parapet on deck edges
Estimated total
₹21,09,948
Notes & assumptions
  • Span limit: 4-12 m. Above 12 m, design as proper minor bridge with T-beam superstructure (separate template). Below 4 m, use Box Culvert instead — slab culvert is uneconomical at small spans.
  • RCC grade: M25 minimum for spans > 6 m per IRC 21. M30 for > 9 m. The Builder uses 5.X (M20 nominal) as approximation — engineer should verify and bump to M25 design mix (DSR 4.20.X) manually for critical spans.
  • Steel reinforcement uses 150 kg/m³ of total RCC — typical for slab culverts under IRC Class A loading. For IRC AA / 70R tracked loading, push to 180-200 kg/m³.
  • Wing walls are 4 nos × full external length × 45° splay outward. Default 3 m length each. Brick masonry CM 1:6 (DSR 6.4.2). For NH / SH applications, switch to RCC wing walls (5.2.2) — more durable.
  • Parapet (DSR 5.2.2 used as proxy) is a 150 mm thick × 1.1 m high RCC band on both deck edges — IRC standard safety barrier. Excludes precast crash barrier (W-beam) or stainless steel railing — quote separately if needed.
  • Approach slab (300 mm thick RCC × 3.5 m long each side) prevents settlement of approach embankment + provides smooth transition from earthen road to culvert deck.
  • Stone-pitched apron (2 m × 300 mm thick RRM each end) protects abutment base from scour. Curtain walls (cut-off walls) downstream/upstream — also recommended, NOT in this BOQ; add manually as 5.2.2 RCC of 300×450 mm cross-section.
  • Excludes: bearing pads (elastomeric, ₹3-5k each, 4 nos under deck-abutment junction); expansion joint sealant at deck-approach slab transition; reflective markers + parapet end-caps; signage (warning, restriction); approach road tapering + transition to existing carriageway; dewatering during foundation work (typical extra 15-25% in waterlogged sites); pile foundation if SBC < 100 kN/m².

**Slab culverts / minor bridges** fill the gap between **box culverts** (up to 3 m span) and **major bridges** (12+ m span with T-beam or PSC girder superstructure). The IRC SP 13 + IRC 5 + IRC 21 standard configuration for 4-12 m spans: RCC abutments + RCC deck slab + brick masonry wing walls + RCC parapet + RCC approach slabs + stone-pitched apron. Standard for PMGSY high-discharge cross-drainage, state-PWD minor bridges over canals + small streams, urban service-road crossings. This BOQ Builder generates the complete cost per CPWD DSR 2023.

When slab culvert beats box culvert

**Box culvert** is the right answer for spans 1-3 m: monolithic raft + walls + deck slab forms a closed box, simple to construct, economical at small spans. **Above 3 m span**, the box-culvert raft becomes very heavy (deflection control needs disproportionately thick raft) and economics flip. **Slab culvert** uses an OPEN-BOTTOM design (just abutments on either bank, no raft connecting them) — saves significant concrete volume + allows the stream to flow over natural bed. The economic crossover is around 3-4 m span. Above 12 m, slab self-weight becomes excessive; T-beam superstructure (separate beams supporting a thinner deck) becomes more economical → proper minor bridge.

Construction sequence + IRC standards

(1) Earthwork in foundation trench, both banks. (2) PCC bed below abutment foundation. (3) RCC abutment foundation (raft strip, full deck length × abutment-base width). (4) RCC abutment walls (vertical or slightly battered, full deck length × abutment height). (5) Curing of abutments (minimum 7 days). (6) Centering of deck slab (props from natural ground or from temporary scaffold). (7) RCC deck slab (span + 0.3 m bearing seat each side). (8) Curing of deck (14 days minimum per IRC 21). (9) Wing walls cast or built. (10) Approach slabs (RCC 300 mm thick) at both ends. (11) Parapet on deck edges. (12) Stone-pitched apron at base of abutments. (13) Backfill around abutments + approach road tapering. (14) Removal of centering after 28-day cube test ≥ design strength.

Frequently asked questions
Using CPWD DSR 2023 rates for default 6 m span × 7.5 m length × 500 mm deck + 2.5 m abutment + wing walls + parapet + apron: approximately **₹14-18 lakh**. State PWD rates run 8-15% below DSR. Per-span-metre: roughly ₹2.3-3.0 lakh per metre of span. Compared to a box culvert of equivalent discharge (1.5×2 m span at 6 m would be ₹10-12 lakh), slab culvert is roughly 30-40% more expensive but handles much higher discharge.

More related

Disclaimer: Rates sourced from CPWD DSR Vol 1 (2023). Indicative for estimation only — actual tender quotations are governed by market forces, locality factors and current input prices. Quantities follow IS 1200 measurement. Always verify with a local quote before finalising. © InfraLens — infralens.in