Slab Culvert / Minor Bridge BOQ — Worked Example f...

8 min read · BOQ · Estimation · Slab Culvert · Minor Bridge · IRC SP 13 · Worked Example
Home / Knowledge / Slab Culvert / Minor Bridge BO
BOQEstimationSlab CulvertMinor BridgeIRC SP 13Worked Example📖 8 min · 1,785 words

Slab Culvert / Minor Bridge BOQ — Worked Example for a 6 m Span × 7.5 m Deck

Slab culverts fill the gap between box culverts (up to 3 m span) and major bridges (12+ m span with T-beam superstructure). The IRC SP 13 + IRC 5 + IRC 21 standard configuration for 4-12 m spans: RCC abutments + RCC deck slab + brick masonry wing walls + RCC parapet + RCC approach slabs + stone-pitched apron. Standard for PMGSY high-discharge cross-drainage, state-PWD minor bridges over canals + small streams, urban service-road crossings. This article walks through a complete BOQ for the most common configuration — 6 m span × 7.5 m deck length.

Project Scenario

You're estimating a slab culvert under a PMGSY road crossing a perennial stream that's too wide for a box culvert. Span: 6 m clear between abutments. Deck length: 7.5 m (5.5 m carriageway + 1 m extension each side). Abutments 2.5 m high (NGL to deck soffit). Wing walls 3 m at 45° splay, RCC parapet on deck edges, stone-pitched apron downstream.

Design specification at a glance
  • Clear span (between abutments): 6.0 m
  • Deck length (carriageway crossing): 7.5 m
  • Deck slab thickness: 600 mm RCC M20
  • Abutment height (NGL to deck soffit): 2.5 m
  • Abutment wall thickness: 500 mm
  • Abutment foundation: 0.9 m deep, 1.7 m wide
  • Wing walls: 4 nos × 3 m each, 345 mm brick
  • Parapet: 150 mm × 1.1 m RCC on both deck edges
  • Approach slabs: 2 nos × 7.5 × 3.5 × 0.30 m at both ends
  • Apron + backfill: standard

The Complete BOQ — 14 Items in CPWD DSR 2023

# DSR Code Item Description Unit Quantity
12.8.1Earthwork in abutment foundation trench (both abutments)32.40
24.1.8PCC 1:4:8 below abutment foundation2.89
35.1.2RCC M20 in abutment foundation strips12.75
45.2.2RCC M20 in abutment walls (vertical)18.75
55.3RCC M20 in deck slab, 600 mm thick29.70
65.1.2RCC M20 in approach slabs (2 nos × 7.5 × 3.5 × 0.30)15.75
75.9.1Centering & shuttering for abutment foundation25.50
85.9.2Centering & shuttering for abutment walls (both faces, 2 abutments)75.00
95.9.3Centering & shuttering for deck slab (under-side, scaffolded)49.50
105.22.6TMT Fe-500D reinforcement (cut, bent, placed)kg9,180.00
116.4.2F.P.S. brick masonry — 4 wing walls (45° splay)7.25
125.2.2RCC M20 in parapets (both deck edges)2.48
137.1.1Stone pitching apron (both ends, 2 m × full width × 300 mm)9.00
142.25Backfill behind abutments + approach embankment56.25

Total RCC volume = 61.2 m³ split across abutment foundations + walls + deck + parapets + approach slabs. At 150 kg/m³ that's ~9.2 tonnes of steel. The live BOQ Builder evaluates these formulas in real time — change span (4-12 m), deck length, abutment height, deck thickness, wing wall length, parapet toggle.

How Each Quantity Was Computed

Geometry

Foundation depth = 0.9 m below NGL
Foundation size = abut_thk + 1.2 = 0.5 + 1.2 = 1.7 m wide (per abutment)
Total deck width = span + 2 × 0.3 m bearing seat = 6.0 + 0.6 = 6.6 m
Deck cross-section per metre of length: 6.6 × 0.60 = 3.96 m²

1-2. Excavation + PCC

Excavation (2 abutments × foundation pit each): 2 × (7.5+0.6) × (1.7+0.3) × (0.9+0.1)
= 2 × 8.1 × 2.0 × 1.0 = 32.40 m³
PCC bed = 2 × (7.5+0.3) × (1.7+0.15) × 0.10 = 2 × 7.8 × 1.85 × 0.10 = 2.89 m³

3-4. Abutment foundation + walls

Foundation (RCC strip, 2 abutments × deck length × foundation width × 0.5 m thick):
= 2 × 7.5 × 1.7 × 0.5 = 12.75 m³
Walls (2 abutments × deck length × wall thk × full height):
= 2 × 7.5 × 0.5 × 2.5 = 18.75 m³

5. Deck slab — Item 5.3

Deck volume = (span + 0.6) × deck_length × deck_thk
= 6.6 × 7.5 × 0.60 = 29.70 m³

Deck thickness 600 mm is standard for 6 m span per IRC 21. The Builder defaults match the IRC tabulated values: 4 m → 400 mm, 6 m → 500-600 mm, 8 m → 600 mm, 10 m → 700 mm, 12 m → 800 mm.

6. Approach slabs

Approach (2 ends × deck_length × 3.5 m × 0.30 m):
= 2 × 7.5 × 3.5 × 0.30 = 15.75 m³

Approach slabs prevent settlement transition between approach embankment and bridge deck — a "jump" forms over time without them. Standard 300 mm RCC × 3.5 m long for IRC Class A loading.

7-9. Centering & shuttering

  • Abutment foundation (5.9.1): 2 × (deck_l × foundation_width) = 2 × (7.5 × 1.7) = 25.50 m²
  • Abutment walls (5.9.2): 2 abutments × 2 faces × deck_l × abut_h = 2 × 2 × 7.5 × 2.5 = 75 m²
  • Deck slab (5.9.3): under-side only (scaffolded from natural ground or temporary props) = 6.6 × 7.5 = 49.50 m²

10. Reinforcement

Total RCC = 12.75 + 18.75 + 29.70 = 61.2 m³
Steel = 61.2 × 150 = 9,180 kg (~9.2 tonnes)

150 kg/m³ is typical for slab culverts under IRC Class A loading. For IRC Class AA / 70R tracked, push to 180-200 kg/m³.

11. Wing walls

Wing wall avg height = abutment_h × 0.7 = 1.75 m
Brick masonry = 4 × 3.0 × 0.345 × 1.75 = 7.25 m³

12. Parapet

Parapet volume = 2 (sides) × deck_length × 0.15 m thk × 1.1 m height
= 2 × 7.5 × 0.15 × 1.1 = 2.48 m³

1.1 m height is the IRC safety standard. Parapets can be solid RCC (current spec), open-rail steel (cheaper but less crash protection), or precast crash-barrier sections.

13-14. Apron + backfill

Stone apron = 2 ends × 7.5 m × 2.0 m × 0.30 m = 9.0 m³
Backfill behind abutments = 2 × 7.5 × 1.5 × 2.5 = 56.25 m³

When Slab Culvert Beats Box Culvert vs Bridge

Span rangeRecommended structureWhy
≤ 3 mBox culvertMonolithic raft + walls + slab is most economical at small spans
3 - 4 mBox culvert (still economical) OR slab culvertCrossover zone — site-specific
4 - 12 mSlab culvert (current article ⤴)Open-bottom design saves raft concrete; natural stream bed preserved
≥ 12 mT-beam or PSC girder minor bridgeSlab self-weight too high; need beam-supported deck

Construction Sequence (IRC 21 Compliant)

  1. Earthwork in foundation trench (both banks)
  2. PCC bed below abutment foundation
  3. RCC abutment foundation (raft strip)
  4. RCC abutment walls (vertical or slightly battered)
  5. Curing of abutments — minimum 7 days
  6. Centering of deck slab (props from natural ground or temporary scaffold spanning the stream)
  7. RCC deck slab (span + 0.3 m bearing seat each side)
  8. Curing of deck — 14 days minimum per IRC 21, ideally 28 days
  9. Wing walls cast / built
  10. Approach slabs at both ends
  11. Parapets on deck edges
  12. Stone-pitched apron at base of abutments
  13. Backfill around abutments + approach road tapering
  14. Removal of centering only after 28-day cube test ≥ design strength

What This BOQ Excludes

  • Bearing pads / elastomeric bearings at deck-abutment junction (₹3-5k each × 4 nos)
  • Expansion joint sealant at deck-approach slab transition
  • Reflective markers + parapet end-caps
  • Signage (warning, restriction) — IRC 67
  • Approach road tapering + transition to existing carriageway
  • Dewatering during foundation work — typical extra 15-25 % in waterlogged sites
  • Pile foundation if SBC < 100 kN/m² (separate scope — significantly increases cost)
  • Curtain walls (cut-off walls upstream/downstream) — for scour-prone sites, add ~₹40-60k as 5.2.2 RCC of 300 × 450 mm cross-section
  • Crash barriers in addition to parapet (NH/SH requirement)

Common Estimation Mistakes

  • Using M20 grade for spans > 6 m — IRC 21 requires M25 minimum for spans 6-9 m, M30 above. Bump grade and re-rate using DSR 4.20.X design-mix items.
  • Under-sized abutments — abutments take both vertical load (deck + traffic) AND horizontal load (earth pressure from backfill). 400 mm walls undersized for 2.5 m high abutments; default to 500 mm.
  • Skipping approach slabs — without them, a 50-100 mm "jump" forms at the deck-approach interface within 6-12 months from backfill settlement. Dangerous for high-speed traffic.
  • Open-rail parapet on rural road — IRC standard is solid RCC parapet for bridges with traffic speed > 40 kmph. Open-rail is acceptable only for low-speed urban service road.
  • Wing walls in brick when RCC is needed — for spans > 8 m or NH/SH applications, RCC wing walls (5.2.2) are recommended over brick (6.4.2). More durable; resists scour.
  • Forgetting cushion/curtain walls — at the discharge end, water exiting at high velocity scours the apron. Curtain walls (300 × 450 mm RCC, 600 mm deep) anchor the apron + headwall foundation.
  • Treating deck slab as one-way slab — for spans 6+ m it's two-way bending; reinforcement must be designed bothways with main steel along short span.

What Changes for a Different Slab Culvert

  • 4 m span (smaller, possibly box-vs-slab borderline) — deck 400 mm, abutment height down to 1.5-2 m. Total cost ~50 % less.
  • 10 m span (large stream) — deck 700 mm, M25 design mix per IRC 21, steel ratio 180 kg/m³, deeper abutment foundations.
  • 12 m span (max for slab culvert) — deck 800 mm, M30 grade, often paired with T-beam superstructure as alternative. Borderline economic case.
  • Two-lane carriageway (10-12 m deck length) — proportional scale-up of all quantities except span-related items.
  • High-discharge perennial stream — add deeper curtain walls + larger apron + scour protection
  • NH / SH grade — M25 grade everywhere, RCC wing walls (5.2.2 instead of 6.4.2), crash-barrier in addition to parapet, full traffic management overlay
  • Pile foundation for soft soil — adds 20-40 % to abutment cost

Get Your Slab Culvert Cost in 30 Seconds

→ Open the Slab Culvert BOQ Builder

Change span (4-12 m), deck length + thickness, abutment height + thickness, wing wall length, parapet toggle — the Builder regenerates the BOQ + downloads Excel with formulas embedded. Customize for Your Project →

References & Companion Reading

Join InfraLens WhatsApp Channel
Get updates on new articles, tools, and IS code insights
More Articles
Clause references and parameter values are sourced from official BIS and international standards. Always refer to the original standard document for design decisions.
💬 Join the Discussion
Q: What has been your experience with this topic on site?
Q: Do you have any tips to share with fellow engineers?
Click a question to start your comment
Leave a Comment
0/500
No comments yet. Be the first to share your thoughts!